C05 - Amendment A00002 - 127EAW27Q0002 - Solar Batteries Frenchman Work Center.pdf
PDF 6 MB Posted
- Solicitation number
- 127EAW27Q0002
- Issued by
-
Department of Agriculture Forest Service
About this file
This is Amendment A00002 to solicitation 127EAW27Q0002, a solar battery installation project issued by the USDA Forest Service, Procurement Operations Construction and A-E Division, West. The amendment incorporates a revised Statement of Work, provides responses to 35 timely submitted Requests for Information, and extends the quote submission due date to Friday, November 27, 2026, at 4:00 PM local time. The project involves replacing a failed battery bank at Frenchman Work Center, Plumas National Forest, California, with a minimum capacity of 2,100 Ah at 48V (minimum 100 kWh) to allow two buildings to operate for two days without recharge. The basis-of-design battery is the HomeGrid LV Stack'd Series with Heated Module, with "or equal" alternatives permitted if they demonstrate full compliance with Buy American requirements, compatibility with existing OutBack equipment (Radian GS8048A inverters, Flexmax FM80 charge controllers, MATE3 controller), and reliable operation from 15°F to 100°F. The contractor must remove existing equipment and racking, complete all work within 30 calendar days of Notice to Proceed, and provide one year of onsite warranty service with 24-hour critical and 72-hour noncritical response times.
Installation must be performed by a California C-10 licensed electrical contractor (prime or qualified subcontractor), with personnel meeting all manufacturer-specific training and certification requirements to preserve warranties. No bid guarantee is required for quotes between $35,000 and $150,000, though alternate payment protection (100% payment bond or deposit) is required upon award for quotes of $35,000 or more. No fire box, organized site visit, or Fire Plan submission is required; offerors are responsible for self-inspection with prior notification to the Contracting Officer. The contractor must provide independent portable generators for all construction power, coordinate Wi-Fi connectivity through Forest Service networks for off-site monitoring, and comply with applicable Davis-Bacon wage requirements. The site is at approximately 5,650 feet elevation with typical winter accessibility, though unusually severe weather may qualify for schedule extensions through Contracting Officer modification.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
15C. DATE SIGNED 16C. DATE SIGNED
PAGE OF PAGES
CODE
(X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
A00002
6. ISSUED BY
USDA FOREST SERVICE
BUSINESS OPERATIONS
PROCUREMENT OPERATIONS CONSTRUCTION AND A-E
DIVISION, WEST
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)
COMPANY INFORMATION
9A. AMENDMENT OF SOLICITATION NUMBER
127EAW27Q0002
1 8
11/17/2026
9B. DATED (SEE ITEM 11)
11/05/2026
1177860
7EAW
X 1
X
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
127EAW27Q0002, Solar Batteries Frenchman Work Center, Plumas National Forest, California
The purpose of Amendment A00002 is to incorporate the revised Statement of Work, provide responses to all timely submitted Requests for Information, and extend the quote submission due date.
See attached pages for the RFI responses and the updated SOW requirements.
Offerors must acknowledge receipt of this amendment and adhere to these updated requirements;failure to do so may render a quote non-responsive.
The due date for receipt of quotes is hereby extended to Friday, November 27, 2026, at 16:00 (4:00 PM) local time.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remain unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
TANYA I. TORRES
TanyaTorres Highlight
Page | 2
Request For Information Responses
Solar Batteries Frenchman Work Center
127EAW27Q0002
Plumas National Forest
RFI 1: Could you please confirm whether the existing Outback Radian GS8048A inverters, Flexmax FM80 charge controllers, and MATE3 controller are known to be operational independently of the failed battery bank?
Answer: Confirmed. To the best of the Government's knowledge, the listed OutBack components are operational independently of the failed battery bank.
RFI 2: Are any additional close-up photos available showing the nameplates for those components and the existing batteries? The current photo attachment does not show readable equipment labels.
Answer: Attachment 4 – Photos provides the extent of available nameplate information for the existing equipment in the trailer. Specific model numbers for the existing equipment are provided in the SOW.
RFI 3: Will the contractor be allowed to visit the site on their own? If we do, will we be able to see if inside or should we rely on the pictures provided?
Answer: No organized site visit will be held, and offerors are responsible for self-inspection. Self-inspection visits are permitted with prior notification to the Contracting Officer/ COR listed in the solicitation.
However, the Government cannot guarantee station staffing to provide interior access to the trailer at the time of the visit.
You can contact the COR at Justine.Zeni@usda.gov for site access only prior to award. Following award, the designated COR will serve as the point of contact to coordinate all site access for delivery and installation.
RFI 4: Bid guarantee: Is a bid guarantee (SF-24) required with the quote for this solicitation? If no bid guarantee is required, please confirm that only the alternate payment protection (100% payment bond, SF- 25A, or 100% deposit) applies if the quoted amount is $35,000 or more, and that no bond or payment protection is required if the quote is under $35,000.
Answer: Per page 16 of the solicitation, no bid guarantee is required for quotes between $35,000.00 and $150,000.00. No bonds or payment protections are required for quotes less than $35,000.00, but alternate payment protection (such as a 100% payment bond via SF-25A or a 100% deposit) is required upon award for quotes of $35,000.00 or more. Review the solicitation, page 15, for additional information.
RFI 5: Attachment 7 project name. Attachment 7, page 2, under "Designation of Contracting Officer's Representative," identifies the project as "Fox Ridge Road Repair — Six Rivers National Forest." Please confirm this is a typographical error and that Attachment 7 in fact applies to the Solar Batteries, Frenchman Work Center project under solicitation 127EAW27Q0002.
Answer: This is an error. An updated Attachment 7 is posted.
RFI 6: "Or equal" battery approval and Buy American evaluation. The Statement of Work identifies the Homegrid LV Stack'd Series with Heated Module as the basis of design, "or equal," with equal proposals to be submitted during the Q&A period with full technical specifications, data sheets, and compatibility documentation. Please confirm:
(a) the exact submittal the Government requires for an "or equal" battery proposal (specifications, data sheets, compatibility with the Outback FM80 / GS8048A / MATE 3, 15°F–100°F charge/discharge mailto:Justine.Zeni@usda.gov
FOR OFFICIAL USE ONLY
Page | 3 performance, monitoring, and warranty documentation);
Answer: Per the SOW, the submittal the Government requires for an “or equal” battery proposal must include comprehensive technical specifications and manufacturer data sheets. In addition, the documentation must explicitly demonstrate compliance with all minimum salient characteristics outlined in the SOW, including, but not limited to, compatibility with the Outback FM80, GS8048A, and MATE 3 components, charge and discharge performance from 15F to 100F, system monitoring capabilities, and complete warranty documentation, along with documentation verifying the country of origin in accordance with the solicitation's Buy American clauses.
(b) Whether the heated-module feature itself is a mandatory salient characteristic, or whether any battery demonstrating the full 15°F–100°F charge/discharge range in the unconditioned trailer is acceptable; and Answer: A battery demonstrating full, reliable operation between 15F-100F is acceptable.
(c) How the Government will evaluate Buy American compliance (FAR 52.225-9, with no foreign construction material excepted) for the battery — specifically, what manufacturer documentation or certification the offeror must provide to demonstrate that the proposed battery (Homegrid or equal) is a domestic construction material, and whether the Government will accept a manufacturer's written Buy American certification for the exact configuration proposed.
Answer: The Contractor must submit sufficient technical data and country-of-origin documentation that clearly demonstrates compliance with the Buy American requirements for the exact battery system and configuration proposed, including all applicable components and manufacturing processes. While the Government may consider a manufacturer's written certification as part of its evaluation, the Government reserves the right to request additional supporting documentation.
RFI 7: Fire Plan Fire Box requirement (minor clarification). Attachment 5 (Fire Plan) appears to contain both a "requires" and a "does not require" statement regarding a Fire Box. Please confirm whether a Fire Box is required for this project.
Answer: This contract does not require a fire box.
RFI 8: Site self-inspection and winter access (confirmation only). Please confirm that no organized site visit will be held, that offerors are responsible for self-inspection, and whether the Contracting Officer's Representative (once designated at award) is the point of contact for coordinating site access for delivery and installation during winter conditions, or whether any pre-award access coordination is available through your office.
Answer: Confirmed. See response to RFI 3.
RFI 9: Does the prime contractor need to hold a California C-10 Electrical Contractor license, or may the prime contractor subcontract all electrical/battery installation work to a properly licensed and qualified C-10 subcontractor? If subcontracting is permitted, what license information must be included with the quote?
Answer: The prime contractor is not required to hold a California C-10 Electrical Contractor license directly. The prime contractor may subcontract the electrical and battery installation work to a properly licensed and qualified C-10 subcontractor. Include this information with the quote.
In accordance with FAR 52.236-7, Permits and Responsibilities, the contractor is responsible for ensuring that it and its subcontractors possess all licenses, certifications, permits, and qualifications required to perform the work. The contractor shall also be responsible for obtaining any necessary licenses and permits and for complying with all applicable Federal, State, and local laws, codes, ordinances, and regulations related to contract performance. Compliance with these requirements remains the responsibility of the prime contractor regardless of subcontracting arrangements.
RFI 10: If the prime contractor has general construction/remodeling experience but no prior solar-battery installation experience, may the proposed licensed electrical subcontractor’s directly relevant solar/battery
Page | 4 experience be considered when evaluating the team’s technical capability? Please identify any minimum experience or manufacturer-certification requirements.
Answer: The Government will evaluate all quotes strictly in accordance with the evaluation criteria established in the solicitation. Regarding experience requirements, the Past Performance criteria state:
"Furnish a list of three (3) projects of similar magnitude completed by the firm within the last three (3) years." The Government will assess quotes based on the information submitted and in accordance with the evaluation factors set forth in the solicitation. No additional minimum experience requirements, manufacturer certifications, or evaluation criteria beyond those expressly identified in the solicitation and Statement of Work will be applied. Past Performance is rated as acceptable, neutral or unacceptable.
Note that installation personnel must meet all applicable manufacturer-specific training and certification requirements necessary to maintain and preserve the product warranties for the approved battery configuration.
RFI 11: SF 1442 Block 13(b) indicates that an offer guarantee is required, while the bonding threshold table on solicitation page 16 appears to state that no bid guarantee is required for projects below $150,000. The stated project magnitude is 25,000−100,000. Please confirm whether an offer guarantee is required and clarify which performance/payment bond or alternative payment protection requirements apply.
Answer: See response to RFI 4.
RFI 12: If an offeror has fewer than three directly comparable solar-battery projects, may it submit its available relevant construction/remodeling project experience and explain the experience of its proposed electrical subcontractor? Please confirm whether fewer than three projects will affect evaluation or make an offer nonresponsive.
Answer: See response to RFI 10.
RFI 13: Davis-Bacon wages and payroll. For this work in Plumas County, please identify the applicable Davis-Bacon wage classifications for battery removal/recycling, electrical installation, testing, and related work. Please confirm the certified payroll submission and recordkeeping requirements for the prime contractor and subcontractors.
Answer: The applicable Davis-Bacon Wage Determination is included in the solicitation as Attachment 6, "Davis-Bacon Act WD CA20260007." Contractors are responsible for properly classifying all laborers based on the actual work performed and for paying wages in accordance with the applicable wage determination. Certified payroll submissions are required in accordance with FAR 52.222-8, Payrolls and Basic Records, and the contractor shall maintain and submit payroll records as required by the clause and all applicable labor standards provisions.
RFI 14: Utilities and site facilities. Attachment 2, Statement of Work, indicates that water and restrooms are available at the Forest Service station and that the contractor must provide independent portable generators for construction. Please confirm the controlling requirements for water, electricity/generator power, and restroom access, including whether another solicitation attachment changes these requirements.
Answer: Water and restroom facilities are currently available for contractor use. However, the availability of these facilities is not guaranteed and may be suspended without advance notice. Should these facilities become unavailable, the contractor shall be responsible for providing alternative water and sanitation services at no additional cost to the Government.
Contractors are strictly prohibited from using the station generator or facility outlets for daily work. The contractor must provide independent portable generators for all construction, tools, and testing power at their own expense.
RFI 15: Key personnel. May one qualified individual fill more than one contractor-designated role, where appropriate (for example, Project Manager, Superintendent, Quality Control Manager, and Safety Manager)?
Page | 5
Answer: Yes, a single qualified individual may fill more than one contractor-designated role, provided they meet all qualifications and certifications required for each position. Provided combining these responsibilities does not negatively impact project oversight, safety management, or the 30-calendar-day completion schedule.
RFI 16: Attachment 5 Fire Plan: Must the Fire Plan be submitted with the quote? and which apply during performance?
Answer: No. The solicitation does not require you to submit a Fire Plan as part of your quote. The Fire Plan provided establishes requirements applicable throughout the entire period of performance.
RFI 17: Are there specific electrical installation experience or qualification requirements?
Answer: Contractor installing batteries and completing the final connection to the existing system must be a licensed Electrical Contractor.
RFI 18: Are there any additional licensing or certification requirements for the personnel performing the battery replacement?
Answer: No additional licenses are required beyond those stated in RFI 9 and RFI 17; however, personnel must meet any manufacturer-specific training or certification requirements necessary to preserve the battery warranty per RFI 10.
RFI 19: Approved equal: We would like to propose Discover Energy Helios, LFP battery as an equal to the HomeGrid LV Stack'd heated system. Datasheets attached. Please confirm whether it's acceptable, or let us know what documentation you need to evaluate it. They are heated, same as the HomeGrid but we have more experience and faith in the Discover, Helios equipment.
Answer: While the Discover Energy Helios LFP battery appears technically comparable, the submitted documentation does not explicitly demonstrate compliance with the Buy American Act, on-site monitoring requirements, or full integration with the existing Outback equipment. Because the submittal does not verify compliance with all minimum salient characteristics and solicitation requirements, this "or equal" request is not approved.
RFI 20: Schedule and winter access: Is the Frenchman Work Center accessible by road through the winter?
Given the 30-day completion window after NTP, will weather or snow delays be treated as excusable?
Answer: The road to the Frenchman Work Center is typically accessible throughout the winter; however, the contractor must coordinate with the Contracting Officer's Representative (COR) prior to mobilization to verify current site access conditions.
Unusually severe weather or snow conditions that prevent reasonable site access may be evaluated as excusable delays. If severe weather prevents access, the Contracting Officer (CO) may issue a formal stop-work/suspension directive or execute a bilateral modification to pause or extend the Period of Performance calendar days accordingly.
RFI 21: Warranty response: For the 24-hour critical response requirement, will initial remote diagnosis count as response, with on-site arrival to follow as needed?
Answer: If the critical issue can be fully resolved remotely within 24 hours, remote resolution is acceptable.
However, if the issue cannot be resolved remotely within that timeframe, on-site arrival is required within the 24-hour critical response window.
RFI 22: Capacity and acceptance basis – The SOW specifies 2,100 Ah at 48 V. The existing battery label shows 150 Ah at 51.4 V nominal, and the SOW identifies 14 existing batteries. Please clarify whether the minimum is 2,100 Ah at the proposed battery’s rated nominal voltage, 100.8 kWh nominal energy for a 48 V-class system, or another usable-energy requirement. Please identify any required discharge-rate, temperature or depth-of-discharge basis and capacity acceptance test.
Page | 6
Answer: The site (one engine garage and one barracks) is required to run off of batteries for a total of 2 days without recharge. This is the 2,100 Ah at the existing battery nominal voltage. Contractor is responsible for providing a new battery bank that allows for a fully functioning system including surge and operational temperature requirements listed in the SOW, a minimum of 100-kwhs.
RFI 23: OutBack integration - May compliance be demonstrated through manufacturer-supported open-loop voltage-based charging/discharging with independent battery BMS protection and separate local/remote state-of-charge monitoring, or is closed-loop battery-to-OutBack communications required? Please provide available existing equipment quantities, firmware/configuration information and electrical single-line/as-built drawings for the FM80, GS8048A and MATE3 installation.
Answer: Battery voltage and state of charge must be viewable on Outback MATE3 controller, similar to existing functionality of system or on the battery/battery stack as listed in the SOW. No single-line diagrams or firmware/configuration records exist for the trailer interior. All available equipment quantities are shown in Attachment 4 – Photos.
RFI 24: Compressor starting load and commissioning - The SOW identifies an Ingersoll Rand compressor motor, 56283138, 230 V, 15 A FLA. Please provide available locked-rotor/starting-current data, starting method, and concurrent loads that must be supported. Please identify the required commissioning/load-test duration and pass/fail criteria, including any required generator integration test.
Answer: All available information on the motor has been provided in the SOW. The air compressor is required to operate with all other loads on the site at any given time. The generator is currently tied into the solar system as an automatic start based upon various battery load conditions from the MATE3 controller.
Generator shall always be connected to the solar system to ensure proper functionality as a back-up.
RFI 25: Trailer installation and pre-bid verification - The photographs show approximate dimensions and require contractor field verification. Please provide any available trailer floor-load rating, anchoring/structural restrictions, required equipment working clearances, and existing busbar/disconnect/protective-device ratings. We understand there is no organized site visit. Please advise the authorized process and contract information for arranging individual pre-bid access through your office to verify dimensions, wiring and installation conditions.
Answer: Reference RFI 3 and RFI 8 regarding pre-award site access. Trailer floor-load ratings and existing busbar/disconnect/protective-device ratings are not available, and there are no known structural anchoring restrictions. All installations must comply with applicable National Electrical Code (NEC) working clearance requirements. The contractor is responsible for field-verifying all dimensions, ratings, and site conditions.
RFI 26: Remote monitoring connection - The SOW identifies Wi-Fi in the Engine Garage Office and requires the contractor to evaluate adequacy or provide a gateway. Please clarify the permitted network connection method and any applicable IT/security requirements. If a cellular or other separately subscribed gateway is necessary, please specify who is responsible for recurring service charges and the required service period.
Answer: The answer from Amendment A00001 is removed. The SOW has been revised to remove the requirement for a separate gateway. The monitoring system shall connect to the existing Forest Service Wi- Fi network located in the nearby Office. The contractor shall coordinate directly with the Forest Service for network connection access. Off-site monitoring must be provided via a mobile application or web-based portal included as a standard, fee-free feature of the hardware. A cellular gateway or separately subscribed connectivity service is not required, and no recurring software or data service charges are authorized.
RFI 27: Onsite warranty service qualifications - For the one-year onsite service requirement and 24-hour critical / 72-hour noncritical response, please define the required certified-technician credential and whether response means physical arrival onsite within the stated period. Would manufacturer-trained personnel working through an appropriately licensed electrical contractor meet the certification requirement? This question does not request a waiver of licensing or warranty obligations.
This page is revised via Amendment A00002
Page | 7
Answer: Reference RFI 10 and RFI 21. Response times (24-hour critical / 72-hour non-critical) require physical arrival onsite within the stated timeframe unless the issue can be resolved remotely with Government concurrence. Personnel performing warranty service must hold a valid Electrical Contractor license (or work directly under an appropriately licensed electrical contractor) and meet all applicable manufacturer-specific training or certification requirements necessary to maintain the equipment warranty.
RFI 28: Conflicting administration provisions - The SOW makes government water hose bibs and restrooms available, while Attachment 7 states the contractor is responsible for water, electricity and restrooms.
Attachment 7 also refers to Fox Ridge Road Repair and Six Rivers National Forest. Please confirm the applicable Frenchman requirements and issue corrected administration language as needed. We understand the SOW prohibits use of station power/generator for construction or routine testing, except the specifically authorized final integration test.
Answer: See response to RFI 5 and RFI 14.
RFI 29: Past-performance attribution - The solicitation requests three similar projects completed by the firm within the last three years and provides for neutral evaluation when no relevant past-performance record is available. May a proposed major installation subcontractor’s relevant projects be submitted and evaluated when clearly attributed to that subcontractor and its proposed role, alongside the offeror’s own record?
Please clarify how an offeror should document fewer than three qualifying firm projects without misattributing subcontractor experience.
Answer: See response to RFI 10.
RFI 30: Licensing. The solicitation requires the contractor to possess "all professional licenses required to perform the work." Please confirm whether a California C-10 Electrical Contractor license is specifically required of the prime contractor, or whether the requirement is satisfied where (a) the prime holds an active out-of-state master electrician license and contractor registration in its home state, and (b) installation work is performed under a California C-10 licensed subcontractor.
Answer: Reference RFI #9. The installation is required to be completed by a properly licensed and qualified C-10 contractor.
RFI 31: Warranty response. The 24-hour (critical) / 72-hour (non-critical) on-site response obligation runs for one year after final acceptance. Please confirm this obligation may be performed by the prime contractor's named California-based subcontractor or service partner, provided response times are met and the subcontractor is identified in the technical approach.
Answer: This is acceptable. Prime contractor should include warranty response plan with applicable contact details in technical proposal.
RFI 32: "Or equal" product. Our quote intends to propose the basis-of-design product (HomeGrid LV Stack'd Series with Heated Module). Please confirm no "or equal" technical submittal is required for the basis-of-design product during the question period.
Answer: Contractors proposing the specified product are not required to submit an "or equal" technical equivalency package.
RFI 33: Schedule and winter access. The period of performance requires work to begin within 10 calendar days of Notice to Proceed and complete within 30 calendar days. Given the site elevation (~5,650 ft) and winter conditions, please advise:
(a) the anticipated award/NTP timeframe Answer: It is the intent to award and complete this project as expeditiously as practicable, with performance commencing shortly after award. The objective is to complete the work during this calendar year, prior to the onset of winter conditions.
(b) whether weather-related access delays beyond the contractor's control can support a time extension;
Page | 8
Answer: See response to RFI 20.
(c) whether camping within the construction limits will be considered if requested.
Answer: Camping may be considered if requested with quote submission, but it is not guaranteed.
RFI 34: Trailer space and existing equipment. Please confirm the new battery system must fit the existing trailer footprint shown in Attachment 4, and whether any dimensional drawing of the trailer interior is available beyond the photographs. May the existing racking be reused?
Answer: Confirmed. The new battery system must fit within the existing trailer footprint shown in Attachment 4 – Photos. No dimensional drawings of the trailer interior are available beyond the provided photographs;
contractors are responsible for field-verifying all interior dimensions. Note that the existing racking will need to be removed.
RFI:35 Please confirm the basis-of-design HomeGrid Stack'd Series with Heated Module is considered compliant with Buy American, and that any 'or equal' battery must also be manufactured in the United States.
Answer: Confirmed. Any proposed "or equal" battery must also be fully compliant under the Buy American Act.
Site Reference Photo:
For site orientation purposes, the structure visible in the right corner of the attached photograph is the Engine Garage Office, and the trailer shown in the background identifies the designated location for the battery installation.
| Request For Information Responses |
| C05 - Amendment A00001 - 127EAW27Q0002 - Solar Batteries Frenchman Work Center.pdf |
| Amendment A00001 - 127EAW26Q0059 - 26 ANF Oak Flats HVAC System Replacement.pdf |
| A00001 - 127EAW24R0017 - Crestline Group CG Renovation |
| Amendment - A00001 - 127EAW23R0011 - Sky Ranch Road |
SF 30 Continuation Page
File details come from the government source that posted it. Updated .