This is a Request for Quotation (RFQ) for construction services issued by the USDA Forest Service for the Pine Canyon Barracks Replacement Project located on the Los Padres National Forest in California. The solicitation number is 127EAW26Q0052, with a requisition number of 1166816. This is a Total Small Business Set-Aside with a disclosed project magnitude between $100,000 and $250,000. The North American Industry Classification Standard Code is 238160 (All Other Specialty Trade Contractors), with a small business size standard of $19 million.

The work scope involves removal and disposal of an existing fire station mobile home-style barracks and replacement with a new wildland urban interface (WUI) rated, barracks-style mobile home, including all necessary utility connections for a habitable structure. The contractor must commence work within 10 calendar days after receiving the notice to proceed and complete all work within 60 calendar days. A firm fixed price contract will be awarded to a single offeror who must submit pricing for all items. Quotations are due by email to Gregory.Cunningham@usda.gov no later than August 11, 2026, at 10:00 AM Pacific Time. Requests for Information must be submitted by August 4, 2026, at 10:00 AM Pacific Time using the provided RFI Form.

Evaluation will be based on technical approach (work plan, capability, safety plan, quality control plan), key personnel qualifications, performance schedule, active California Class A or B contractor's license, past performance on three similar projects within the last three years, and fair and reasonable pricing. A bid guarantee equal to 20 percent of the bid price or $1,000,000, whichever is less, is required in the form of a bond, certified check, cashier's check, or irrevocable letter of credit. Performance and payment bonds are required, with submittal within 10 calendar days of award. The offeror must hold an active SAM.gov registration and comply with all applicable FAR and USDA AGAR clauses, including Davis-Bacon Act prevailing wage requirements, construction wage rate requirements, and numerous federal labor and compliance regulations.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

127EAW26Q0052

USDA FOREST SERVICE

PROCUREMENT OPERATIONS

CONSTRUCTION AND A-E, DIVISION WEST

127EAW26Q0052 - Pine Canyon Barracks Replacement

Set Aside: Total Small Business Set Aside

Disclosure of Project Magnitude: Between $100,000 and $250,000.This information is provided for general guidance only.

IMPORTANT NOTES:

- See Section "Required Quote Submission Documents" for the Documents to Submit with Your Proposal

- A FS organized site visit will NOT be held. The project locations are open to the public and can be viewed by each prospective offeror. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

- Requests For Information (RFI’s) are required to be submitted on attachment “RFI Form” and are due to the Contracting Officer (Gregory.Cunningham@usda.gov) via email no later than August 4th, 2026, 10:00 AM Pacific Time. No questions will be accepted after this date and time.

-- All quotes shall be emailed to the Contracting Officer (Gregory.Cunningham@usda.gov) no later than August 11th, 2026, 10:00 AM Pacific Time.

GREGORY.CUNNINGHAM@USDA.GOV

1166816

GREGORY CUNNINGHAM (530) 575-7569

1 OF 2007/22/2026

08/11/2026

1000 AM PT

10 Calender days

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

E-mail:________________ UEI #:________________

7EAW

USDA FOREST SERVICE

PROCUREMENT OPERATIONS

CONSTRUCTION AND A-E, DIVISION WEST

Invoice Processing Platform, www.ipp.gov

GREGORY CUNNINGHAM

Pine Canyon Barracks Replacement Solicitation 127EAW26Q0052

Page | 3

Table of Contents

Acquisition Description Statement of Requirement Schedule Of Items Technical Data Project Location Solicitation Information Quate Evaluation and Basis for Award Evaluation Method Quote Submission Requirements

Page | 4

Acquisition Description This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Overhaul Part 12. This announcement constitutes the only solicitation; offers are being requested, and a separate written solicitation will not be issued.

Solicitation number 127EAW26Q0052 is issued as a Request for Quotation (RFQ) for Pine Canyon Barracks Replacement Project located on the Los Padres National Forest, California.

This acquisition is set-aside for small business concerns. This solicitation incorporates provisions and clauses by reference. The full text of provisions and clauses may be accessed electronically at www.acquisition.gov.

The applicable North American Industry Classification Standard Code is 238160 - All Other Specialty Trade Contractors. The small business size standard is $19M. This acquisition is a Total Small Business Set-Aside. All responsible sources may submit a quotation which will be considered by the agency.

This document titled "127EAW26Q0020 - Pine Canyon Barracks Replacement" encompasses details pertaining to applicable clauses, instructions, and evaluation criteria.

Statement of Requirement The purpose and intent of this solicitation is for, but not limited to, removal and disposal of the existing fire station mobile home-style barracks and replace it with a new wildland urban interface (WUI) rated, barracks-style mobile home. Performance shall include all necessary details to connect utilities for a habitable structure.

See Attachment 1. Statement of Work for additional information

Disclosure of Project Magnitude This information is provided for general guidance only and does not represent the Government’s estimate. Between $100,000 and $250,000.

Schedule Of Items

The Contractor is required to complete the Schedule of Items, as detailed in Attachment 2, and submit it as part of their quotation package.

Technical Data Technical data and supporting documentation associated with this solicitation are available through the following sources:

Solicitation Attachments The following documents are included as attachments to this solicitation and can be accessed via the “Attachments/Links” section of the posting.

Attachment 1. Statement of Work Attachment 2. Schedule Of Items Attachment 3. Barracks Specifications Attachment 4. Pine Canyon FS Barracks Plan Attachment 5. Pine Canyon Maps & Photos Attachment 6. Davis-Bacon Act WD # CA20260014 - 05_18_2026

Page | 5

Attachment 7. Contract Administration Information Attachment 8. RFI Form

Project Location

See solicitation attachment “1. Statement of Work”

Definitization of Equitable Adjustments for Change Orders - Pursuant to FAR 36.101-4(b), information regarding USDA’s definitization of equitable adjustments for change orders under construction contracts may be found at FAR 36.211 | USDA. USDA’s procedures that apply to the definitization of equitable adjustments for change orders under construction contracts may be found in AGAR 443.304 -70.

Federal Acquisition Regulation (FAR) and United States Department of Aquiculture Acquisition Regulation (AGAR) Clauses and Provisions The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.

Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.

As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

52.252-2 Clauses Incorporated by Reference Feb 1998 This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025)

This is a commercial construction acquisition. FAR 52.212-4 is amended as follows:

(b) Inspection/Acceptance. Inspection and Acceptance will be conducted in accordance with FAR 52.246-12, Inspection of Construction (Aug 1996).

(d) Changes. Changes will be handled in accordance with the following FAR clause(s):

☒ FAR 52.243-4, Changes (Nov 2025)

(o) FAR 52.246-21, Warranty of Construction is applicable to this contract.

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024)

Page | 6

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)

The following clauses are applicable if checked:

☒ 52.204-13 System for Award Management—Maintenance (Nov 2025) ☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) ☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) ☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025) ☒ 52.219-8 Utilization of Small Business Concerns (Nov 2025) ☒ 52.219-14 Limitations on Subcontracting (Nov 2025) ☒ 52.222-3 Convict Labor (June 2003) ☒ 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Nov 2025) ☒ 52.222-35 Equal Opportunity for Veterans (Nov 2025) ☒ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025) ☒ 52.222-37 Employment Reports on Veterans (Nov 2025) ☒ 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) ☒ 52.222-54 Employment Eligibility Verification (Nov 2025) ☒ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ☒ 52.222-90 Addressing DEI Discrimination by Federal Contractors (Apr 2026) ☒ 52.223-23 Sustainable Products and Services ☒ 52.225-1 Buy American-Supplies (Nov 2025) ☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018)

The Contractor shall comply with the following FAR Clauses for Commercial Construction.

52.222-6 Construction Wage Rate Requirements (Nov 2025) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (July 2021) 52.222-9 Apprentices and Trainees (July 2025) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (Nov 2025) 52.222-12 Contract Termination-Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certificate of Eligibility (May 2014) 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) (Nov 2025) 52.236-5 Material and Workmanship (July 2025)

The following clauses are applicable when checked:

☒ 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Pricing Method (Aug 2018)

Page | 7

☒ 52.222-55 Minimum Wages for Construction Workers under Executive Order 14026 (Nov 2025) ☒ 52.223-2 Reporting of Biobased Products under Service and Construction Contracts (Nov 2025) ☒ 52.225-9 Buy American-Construction Materials (Nov 2025)

(b)(2) Foreign construction material excepted from the requirements of the Buy American statute: None

☒ 52.228-2 Additional Bond Security (Oct 1997) ☒ 52.228-5 Insurance-Work on Government Installation (Jan 1997) ☒ 52.228-11 Individual Surety-Pledge of Assets (Feb 2021) ☒ 52.228-14 Irrevocable Letter of Credit (Nov 2014) ☒ 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) ☒ 52.228-17 Individual Surety-Pledge of Assets (Bid Guarantee) (Feb 2021) ☒ 52.236-2 Differing Site Conditions (Jul 2025) ☒ 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) ☒ 52.236-6 Superintendent by the Contractor (Jul 2025) ☒ 52.236-7 Permits and Responsibilities (Jul 2025) ☒ 52.236-8 Other Contracts (Jul 2025) ☒ 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) ☒ 52.336-10 Operations and Storage Areas (Jul 2025) ☒ 52.236-11 Use and Possession Prior to Completion (Jul 2025) ☒ 52.236-12 Cleaning Up (Jul 2025) ☒ 52.236-13 Accident Prevention (Jul 2025) ☒ Alternate I (Nov 1991) of 52.236-13 ☒ 52.236-14 Availability and Use of Utility Services (Jul 2025) ☒ 52.236-15 Schedules for Construction Contracts (Jul 2025) ☒ 52.236-16 Quantity Surveys (Jul 2025) ☒ 52.236-17 Layout of Work (Jul 2025) ☒ 52.236-21 Specifications and Drawings for Construction (Jul 2025) ☒ Alternate II (Apr 1984) of 52.236-21 ☒ 52.242-14 Suspension of Work (Apr 1984) ☒ 52.248-3 Value Engineering (Oct 2025)

The Contractor shall comply with the following FAR Clauses for Commercial Services.

Other Applicable Clauses

52.203-3 Gratuities (APR 1984) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) Alternate I.

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform Employees of

Whistleblower Rights (NOV 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(JAN 2017)

52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014)

Page | 8

52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (SEP 2025) 52.236-5 Material and Workmanship (JULY 2025) 52.236-10 Operations and Storage Areas (APR 1984) 52.242-13 Bankruptcy (JUL 1995) 52.253-1 Computer Generated Forms (JAN 1991)

AGAR Clauses 452.204–70 Modification for Contract Closeout (Nov 2025)

(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (Contracting Officer) shall issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but will not be required to provide a signature. The Contracting Officer shall immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(b) Upon contract closeout for contracts utilizing SAP: if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation.

The contractor will receive a copy of the modification and will be required to provide a signature.

(The Contracting Officer may also request a “Contractor Release of Claims” be completed by the contractor, although not required for contracts and orders using SAP.) If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 60 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(c) Upon contract closeout for contracts utilizing anything other than cost reimbursement, if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and a ‘‘Contractor Release of Claims’’ and will be required to provide a signature on both forms. If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 120 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(End of Clause)

452.203-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025)

(a) By entering into this contract, the Contractor certifies that:

(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.

(2) Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution, and the Contractor and any subcontractor or teaming partner will not do so for the duration of the contract.

(b) If the Contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not

Page | 9 limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the Contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The Contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the Contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to Contractor’s compliance with the above requirements and/or eligibility for the contract may subject the Contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.

(f) The Contractor must include the provisions of this clause in all subcontract solicitations.

(g) Failure on the part of the Contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.

(End of Clause)

452.232-71 Progress Payments for Commercial Construction Contracts (Dec 2025)

(a) Contractor entitlement to progress payments. The Contractor may request progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished that meets the standards of quality established under the contract, as approved by the Contracting Officer.

(b) Computation of amounts. Progress payments will be authorized when the payment requested is properly due in accordance with this contract; the work will be performed in accordance with the contract; and there has been no impairment or diminution of the Government’s security under this contract. The Contracting Officer may authorize consideration of:

(3) Materials delivered on site and preparatory work;

(4) Materials delivered to the Contractor at locations other than the site, if:

i. Specifically authorized by the contract; and

ii. The Contractor provides satisfactory evidence of title and intended use in the contract.

(c) Contractor request for progress payments. The Contractor’s request for progress payments shall include the following:

(1) An itemization of the amounts requested, related to the various elements of work required by the contract;

(2) A listing of the amount included for work performed by each subcontractor;

(3) A listing of the total amount of each subcontract;

(4) A listing of the amounts previously paid to each subcontractor; and

(5) Additional supporting data in a form and detail required by the Contracting Officer.

(d) Contractor Certification. Each request for progress payment shall be accompanied by the following certification:

I hereby certify, to the best of my knowledge and belief, that— The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(1) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the

Page | 10 payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(2) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(3) This certification is not to be construed as final acceptance of a subcontractor’s performance.

________________________________________________(name) ________________________________________________(title) ________________________________________________(date)

(e) Access for verification of payment entitlement. To verify the Contractor’s entitlement to progress payments under this contract, the Contractor shall provide the Government, upon request and during normal business hours, access to the following:

(1) Records and Documentation:

(i) Certified progress payment requests and supporting documentation;

(ii) Subcontractor and supplier invoices, payment records, and lien waivers;

(iii)Updated schedule of values and progress schedules;

(iv) Quality assurance and inspection reports;

(v) Payroll records, if applicable under labor provisions.

(2) Facilities and Worksite Access:

(i) Physical access to the construction site for inspection of work progress;

(ii) Access to off-site storage locations for materials billed but not yet incorporated into the work; or (iii)Access to any fabrication facilities where contract-related work is being performed.

(3) Access to electronic invoicing or project management systems used to track progress and payments, if such systems are used in contract performance.

(f) Dates for payment. A progress payment under this clause is a contract progress payment under the Prompt Payment clause of this contract, and except as provided in paragraph (g) of this clause, approved requests shall be paid within 30 days of submittal of a proper request for payment.

(g) Liquidation of progress payments. Progress payments shall be liquidated by deducting from the payment of each item the total unliquidated amount of progress payments made for that separately priced unit of that line item. The liquidation amounts for each line item shall be clearly delineated in each request for progress payment submitted by the Contractor.

(h) Security for progress payments. In the event the Contractor fails to provide adequate security as required in this contract, no progress payment shall be made under this contract. Upon receipt of adequate security, progress payments shall be made, including all previous payments to which the Contractor is entitled, in accordance with the terms of the contract. If at any time the Contracting Officer determines that the security provided by the Contractor is insufficient, the Contractor shall promptly provide such additional security as the Contracting Officer determines necessary. In the event the Contractor fails to provide such additional security, the Contracting Officer may collect or liquidate such security that has been provided, and suspend further payments to the Contractor; the Contractor shall repay to the Government the amount of unliquidated progress payments as the Contracting Officer at his sole discretion deems repayable.

(i) Special terms regarding termination for cause. If this contract is terminated for cause, the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments. The Government shall be liable for no payment except as provided by the Termination for Cause paragraph of the clause at Federal Acquisition Regulation 52.212-4, Contract Terms and Conditions—Commercial Products and Commercial Services.

(j) Reservation of rights.

Page | 11

(1) No payment, vesting of title under this clause, or other action taken by the Government under this clause shall-

(i) Excuse the Contractor from performance of obligations under this contract; or

(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.

(2) The Government’s rights and remedies under this clause-

(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(k) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

(1) Notify the Contracting Officer of such performance deficiency; and

(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-

(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(l) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(m) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-

(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or

(2) Waiving the right of the Government to require the fulfillment of all the terms of the contract.

(3) The Government’s rights and remedies under this clause-

(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(n) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the

Page | 12

Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (l) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(o) Final payment. The Government shall pay the amount due the Contractor under this contract after-

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed voucher; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).

(p) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(End of clause)

Page | 13

Solicitation Information

Award Type It is anticipated that a Firm Fixed Price will be awarded as a result of this synopsis/solicitation.

The Government intends to make one award from this solicitation. Therefore, to be considered responsive, contractors must submit pricing for all items.

Period of Performance The Contractor shall be required to commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed and the entire work ready for use not later than 60 calendar days after NTP. The time stated for completion shall include final cleanup of the premises.

Organized Site Visit A FS organized site visit will NOT be held. The project locations are open to the public and can be viewed by each prospective offeror. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

It is the responsibility of the contractor to inspect the site to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance. Please be advised that failure to inspect the site will not constitute grounds for any claims after the contract award.

Requests For Information (RFI’s) Questions shall be submitted via email to Gregory.Cunningham@usda.gov and are due no later than August 4th, 2026, 10:00 AM Pacific Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email. No questions will be accepted after this date and time.

Quote Due Date All quotes shall be emailed to the Contracting Officer (Gregory.Cunningham@usda.gov) no later than August 11th, 2026, 10:00 AM Pacific Time.

Page | 14

Quate Evaluation and Basis for Award

The provision at FAR Overhaul 52.212-2, Evaluation—Commercial Products and Commercial Services is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR Overhaul 12.203 based on the criteria listed below. Award will be made to the offeror representing the most advantageous procurement to the Government.

1. Technical Approach:

The technical approach will evaluate the ability of the offeror to provide a sound, compliant approach offeror's ability to provide a sound and compliant approach that meets all requirements and shows a thorough understanding of them. It is the contractor's responsibility to ensure their quotation clearly demonstrates their capability to meet these requirements. All offerors must provide the following minimum information and documentation with their quotations to be considered responsive and have their offers evaluated:

I. Work Plan / Capability of the Offeror (NTE 5 pages): The technical approach should be in as much detail as the offeror considers necessary to fully explain the proposed technical approach or method. The offeror shall compose a narrative detailing a response to the below questions / statements.

a. Capability and Subcontracting Plan: Provide a detailed explanation of your capability to execute the work outlined in the Statement of Work. This should include a comprehensive description of the specific tasks you intend to subcontract. Clearly articulate your technical approach for completing the project tasks to meet the Government's performance requirements. If subcontractors are part of your proposed team, describe their roles in the project and specify the percentage of work they will perform. Note: that a major subcontractor is defined as one performing over 25% of the total work.

b. Additional Relevant Information: The offeror shall include any other pertinent information that demonstrates a thorough understanding of the solicitation requirements and your technical capability to fulfill them. This may encompass methodologies, innovative solutions, or any unique competencies that enhance your ability to meet the Government's needs effectively.

c. Site-Specific Safety Plan: Develop and implement a comprehensive safety plan tailored to the specific site conditions. This plan should detail the safety protocols and procedures that will be adhered to in order to safeguard workers and the environment, ensuring compliance with applicable safety regulations and standards.

d. Quality Control Plan: Establish a robust quality control framework that outlines the measures and processes to be employed to ensure adherence to the contract specifications and standards. This plan should include methodologies for monitoring, inspecting, and verifying the quality of work to maintain compliance and achieve the desired project outcomes.

II. Key Personnel (NTE 3 pages): The offeror must submit a detailed summary of relevant experience and a letter of intent for project assignment. Include a list of personnel with job titles, years of experience, crew composition, and backgrounds. Provide the names and

Page | 15 qualifications of the prime contractor’s project manager and on-site superintendent, including tenure with the contractor and total experience. Both roles must demonstrate, through professional resumes, oversight experience on similar projects of equal or greater magnitude.

III. Performance Schedule (NTE 2 pages): The Contractor is required to submit a comprehensive performance schedule that outlines the planned sequencing of all work activities. This schedule must be presented in the form of a time-scaled Network Diagram, Critical Path Method (CPM) Schedule, or Gantt chart. It should clearly delineate the critical path and indicate the commencement and completion dates for the entire project within the stipulated contract period of performance.

The schedule must be detailed enough to show each segment of work, including its planned start and finish dates, and should be expressed in calendar days. It is imperative that the schedule is realistic, taking into account potential challenges and contingencies.

The performance period must encompass all aspects of the work, including the advance ordering of long lead items, to ensure timely completion within the contract's requirements.

PAGE LIMITATIONS: Pages that exceed limitation will not be evaluated. A page is defined as one side of a sheet of paper. Do not use less than 10pt font. Pages will be evaluated in order received, any pages beyond the stated maximum will not be evaluated.

2. Contractors License: Offerors must hold and submit an active and valid California Class A or

B contractor’s license, which must be active at the time of quote submission and remain active throughout contract performance. Offerors shall provide the license number and a copy of the active license with their quote, or the quote may be deemed non-responsive.

3. Past Performance (NTE 3 pages):

Furnish a list of three (3) projects of similar magnitude completed by the firm within the last three (3) years. The list should include work similar in nature and complexity to that required by this solicitation. Include contracts with the Federal Government, agencies of state, local governments, and commercial customers. For each project cited, provide the following:

Name and location of the project;

Project Point of Contact’s name, phone, email address, and fax numbers; Total cost of the project;

A brief narrative of the project (include size, i.e. acres, square feet; date of start, and completion or anticipated completion date).

The Government may utilize any references provided by the Contractor, along with information available from past contracts/orders with the USDA and any information found using sources such as Federal Government sources or the Contractor Performance Assessment Reporting System (CPARS) to determine if the Contractor has acceptable or neutral Past Performance.

Past Performance will be evaluated using the following rating system:

Acceptable: The contractor shows a demonstrated ability to meet contract requirements in prior or current contracts, including quality of work, timeliness, cost control, business relations, and adherence to contract terms.

Page | 16

Neutral: Offeror does not have a past performance record.

Unacceptable: The contractor has a documented history of failing to meet contract requirements, including poor quality, missed deadlines, cost overruns, lack of responsiveness, or unethical behavior.

4. Price:

The offeror’s quotation will be evaluated in accordance with FAR Overhaul 12.204, to determine if it is fair and reasonable. The offeror shall provide pricing as requested by completing the Schedule Of Items.

Evaluation Method

Quotations determined to be unreasonably high, unbalanced, or otherwise unrealistic in price may be deemed non‑competitive. In such cases, the Government reserves the right to remove those quotations from further consideration and discontinue their technical evaluation.

All responsive and competitively priced quotations will be evaluated to determine the offeror providing the most technically advantageous solution based on the stated evaluation criteria.

Once the highest technically rated offeror is identified, their price will be evaluated to determine whether it is fair and reasonable. Past performance will also be assessed to ensure it is acceptable or neutral.

Award will be made to the offeror whose proposal is determined to be the highest technically rated, provided that:

1. The proposed price is fair and reasonable, and

2. Technical proposal is most advantageous to the Government

3. Past performance is assessed as acceptable or neutral.

Award will not necessarily be made to the lowest-priced offeror. Tradeoffs will not be conducted.

Page | 17

52.252-1 Solicitation Provisions Incorporated by Reference Feb 1998 This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-1 Instructions to Offerors - Commercial Products and Commercial Services (Nov 2025)

FAR 52.212-1 is amended as follows:

Period for acceptance of offers.

The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers.

Offeror must have an active entity registration at https://www.sam.gov/ in order to submit a quote.

Quote Submission Requirements

All quote submissions shall include:

1. Completed, Signed Offer SF1442 and Acknowledgment of Solicitation Amendment(s).

o Complete all required sections of the SF 1442, including Fill-ins, Blocks 14, 15, 16, 17, and 20a–c.

o If amendment(s) are issued, acknowledge them by signing and completing the SF 30 or by completing Blocks 19 and 20a–c of the SF 1442.

o The SF 1442 must be signed by an individual authorized to bind the firm.

2. Attachment 2. Schedule of Items.

This solicitation requires submission of a quote on ALL items. Include unit pricing and totals for all bid items. Failure to do so may result in the quote being rejected without further consideration. All pricing shall be rounded to the nearest cent and not more than two decimal places. Unit prices will govern any total errors unless otherwise determined by the Contracting Officer. Complete fill ins Company Name, POC, E-mail, SAM UEI #, TAX ID #, POC Name, POC E-mail.

3. Technical Approach / Contractors License / Past Performance.

Please refer to the following technical approach, Contractors License, and past performance requirements on pages 14 through 16.

4. Bid Guarantees – See FAR Overhaul 52.228-1: Scanned copies of a fully executed Bid

Guarantee (Standard Form 24) and the accompanying Power of Attorney shall be submitted with the quote. If requested by the Government, the original Bid Guarantee on Standard Form 24 and the original Power of Attorney shall be mailed in hardcopy to the address that will be provided.

Page | 18

Contractors electing to submit a cashier’s check as the bid guarantee, in lieu of a Standard Form 24, shall provide the original cashier’s check directly to the Contracting Officer.

Photocopies, scanned images, or photographs are not acceptable and do not satisfy the bid guarantee requirement under FAR 52.228 1. The original cashier’s check must be physically delivered to the Government at the location provided by the Contracting Officer prior to the quote due date; offerors shall email the Contracting Officer to obtain the mailing address.

Failure to provide the original cashier’s check in accordance with these instructions will render the quote non responsive.

The four (4) documents detailed within “Quote Submission Requirements” shall be submitted as separate Adobe PDF documents. It is the quoter’s responsibility to ensure delivery of all required documents by the date and time set for receipt of offers.

Contact the Contracting Officer by e-mail if you do not understand any part of these instructions.

FAR Overhaul Provisions

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Nov 2025) 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (Sep 2024) 52.204-7 System for Award Management—Registration (Nov 2025) 52.217-5 Evaluation of Options (Nov 2025) 52.225-10 Notice of Buy American Requirement - Construction Materials (May 2014) 52.233-2 Service of Protest (Sep 2025) 52.222-5 Construction Wage Requirements, Secondary Site of the Work (Nov 2025)

52.228-1 Bid Guarantee (Sep 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20% percent of the bid price or $1,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

Page | 19

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of provision)

AGAR Provisions 452.203-70 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Certification (Dec 2025)

(a) By submission of its offer, the offeror certifies that:

(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution.

(2) Neither it nor any proposed subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution.

(b) If the offeror participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, by submission of its offer, the offeror certifies that it is compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The offeror affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the offeror will not be eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .