9. Statement of Work Addendum.pdf
PDF 112 KB Posted
- Attached to
- ARA, Groveland RS Facility Repairs Federal contract opportunity
- Solicitation number
- 127EAW26Q0030
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for bat exclusion and bird netting services at the ARA Groveland RS Facility within Stanislaus National Forest. The work is incidental to exterior painting (pay item 008-099113) and requires replacement of existing bat exclusion and bird netting in perimeter eaves, utility chase venting, and other areas where netting currently exists. Preliminary estimates indicate 1,000 square feet of bird exclusion netting and 300 square feet of bat exclusion netting are required, with the contractor responsible for verifying actual quantities. The contractor must provide all equipment, material, labor, and logistics to accomplish removal of existing netting, perform exterior painting per section 099113, and install replacement netting. Re-use of existing material is prohibited without written contracting officer (C.O.) approval.
Product specifications require UV-stabilized, knotted polyethylene netting that is flame-resistant (270°F melting point), rot-proof, non-conductive, and stable in subzero temperatures. Bat netting must be 1/6 inch mesh size while bird netting must be 3/4 inch mesh size. Fastening materials include 5/8 inch galvanized staples, 1 inch thick wooden lath, and galvanized or stainless-steel metal screws with minimum 1 inch embedment depth. All products require submittal to the C.O. for approval prior to installation per Section 013000 Administrative Requirements. Installation must follow manufacturer's instructions. The document also includes three resolved RFIs clarifying that equivalent roofing products are acceptable, hazardous materials abatement is excluded from scope, and local building permits are waived for this federal facility with all work complying with applicable federal regulations and project specifications.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment A00001 -127EAW26Q0030 - ARA Groveland RS Facility.pdf | ||
| 1. Solicitation Terms and Conditions - ARA, Groveland RS Facility Repairs.pdf | ||
| 2. Statement of Work and Specifications.pdf | ||
| 3. Schedule Of Items.docx | DOCX document | |
| 4. Davis-Bacon Act WD - CA20260018.pdf | ||
| 7. Contract Administration Data.pdf | ||
| 5. Fire Plan.pdf | ||
| 6. Plans and Drawings.pdf | ||
| 8. RFI Form.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARA, Groveland RS Facility Repairs Stanislaus National Forest
Additional guidance is provided below for incorporation into the solicitation requirements.
1 | P a g e
Bat Exclusion/ Bird netting SOW PART 1 Scope Incidental to pay item 008- 099113 Exterior Painting, it is required that existing bat exclusion netting and bird netting be replaced under perimeter eves, utility chase venting, and any other area where netting already exists. Preliminary estimates for required bird exclusion netting are 1000 sqft. Preliminary estimates for bat exclusion netting are estimated at 300 sqft. It is the Contractor’s responsibility to verify all quantities.
Work includes removal of netting, painting the exterior in accordance with section 099113 Exterior Painting, and then placing exclusion netting back where netting previously existed. The contractor shall provide all equipment, material, labor, and logistics to accomplish the task. Re-use of existing material is prohibited without written permission from the C.O.
Part 2 Products Provide Submittals in accordance with Section 013000 Administrative Requirements to the C.O. for approval prior to placement of required products.
Netting- Material: U.V. stabilized knotted polyethylene net. Flame resistant (270°F melting point). Rot-proof, non-conductive and stable in subzero temperatures.
Sizes: Bat Netting 1/6”; Bird Netting 3/4”
Fasteners- 5/8’ Galvanized Staples.
Miscellaneous- Wooden Lath 1” thick. Galvanized or Stainless-steel metal screws. Length to embed fasteners a minimum of 1”
Part 3 Execution Place netting in accordance with manufacturer’s instructions.
RFI #1 – Can you confirm whether there is a required basis of design roofing system (manufacturer/model), or if equivalent products are acceptable?
Response: Equivalent roofing system products are acceptable, provided they meet the project’s performance requirements and specifications and are accepted by the Forest.
RFI #2 – Can you confirm if any hazardous materials surveys have been completed and whether abatement is included in the project scope?
Response: Abatement activities are excluded from the project scope.
RFI #3 – Please confirm whether local building permits are required for this federal facility, or if they are waived.
Response: Because the project is located on a federal facility, local building permits and associated approvals are not required. All work shall comply with applicable federal regulations and project specifications.