Attachment-05 127EAV26Q0022 Quemado Lake Well Repair QA.docx

DOCX document 19 KB Posted

Attached to
Quemado Lake Well Repair Gila National Forest
Solicitation number
127EAV26Q0022
Issued by

About this file

This is a Questions and Answers/Additional Information document supporting a solicitation for well pump system repair and access route maintenance at Quemado Lake Recreation Site on the Gila National Forest. The document provides detailed scope clarification in response to contractor inquiries and specifies the exact deliverables and performance requirements for the project.

The scope of work requires contractors to remove and replace failed well pump system components with specified equipment: one 1.5 horsepower, 5 gallons-per-minute Goulds submersible pump and motor assembly; one 1.5 horsepower control box compatible with the installed pump motor; and one PumpTec Plus pump protection device or approved equivalent. Installation tasks include removal and proper disposal of existing failed components in accordance with New Mexico Environment Department (NMED) standards, installation per manufacturer specifications, electrical connections and grounding integration, startup and functional testing, and documentation of installed equipment with test results provided to the Contracting Officer's Representative. Additionally, contractors must perform minor maintenance on approximately 250–300 linear feet of existing unsurfaced access route by clearing vegetation and obstructions, regrading the dirt surface to remove impediments, and restoring natural drainage—work limited strictly to the existing corridor footprint. All work must comply with federal, state, and local codes; National Electrical Code standards for electrical work; OSHA safety requirements; and NMED standards. Deliverables include a fully operational well pump system, passable dirt access route, as-built documentation with component details and test results, and final inspection and acceptance documentation signed by the COR.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

127EAV26Q0022 Quemado Lake Well Repair Questions and Answers/Additional Information on Scope of Work

1. Is there a more detailed scope of work?

2. Is there a quote or analysis of the issues with the well either from the Forest Service or from another vendor?

3. Is there a well log or details regarding the well construction including pump type?

Parts needed include:

- 1.5hp 5gpm Gould’s pump and motor

- 1.5hp control box

- Pump tec Plus

For a more detailed scope see below:

2. Scope of Work

The Contractor shall furnish all labor, materials, equipment, tools, supervision, transportation, and incidentals necessary to complete the work described herein.

2.1 Well Pump System Replacement

The Contractor shall remove and replace failed well pump system components and ensure the system is fully operational upon completion.

Required components (or approved equal):

· One (1) 1.5 horsepower, 5 gallons-per-minute (GPM) Goulds submersible pump and motor assembly.

· One (1) 1.5 horsepower control box compatible with the installed pump motor.

· One (1) PumpTec Plus pump protection device, or equivalent, to provide dry-run and overload protection.

Tasks include:

· Removal and proper disposal of the existing failed pump, motor, control box, wiring, and associated components in accordance with NMED standards.

· Installation of the new pump, motor, control box, and PumpTec Plus device in accordance with manufacturer specifications and NMED standards.

· Electrical connections, grounding, and integration with the existing power supply system.

· Startup, functional testing, and verification of proper flow and system operation.

· Documentation of installed equipment, including model numbers and test results, provided to the Contracting Officer’s Representative (COR).

2.2 Dirt Access Route Maintenance

Approximately 250-300 linear feet of existing unsurfaced access route requires minor maintenance to allow vehicle access to the well site. This work is intended solely to restore basic passable conditions and does not constitute road construction or improvement.

The Contractor shall:

· Clear minor vegetation and obstructions within the existing disturbed travel corridor as needed for vehicle passage.

· Regrade and smooth the existing dirt surface using on-site material to remove ruts, washouts, or irregularities that impede access.

· Restore natural surface drainage to prevent standing water or concentrated erosion within the existing travel way.

· Limit disturbance strictly to the existing roadway footprint and avoid new ground disturbance outside the established corridor.

3. Deliverables

The Contractor shall provide:

· A fully installed and operational well pump system meeting the specified requirements and NMED standards.

· A passable dirt access route for the specified 250-300-foot segment.

· As-built documentation of installed components and test results.

· Final inspection and acceptance documentation signed by the COR.

4. Performance Requirements

· All work shall comply with applicable federal, state, and local codes and regulations.

· Electrical work shall comply with the National Electrical Code (NEC).

· Workmanship shall meet standard industry practices for well installation and low-volume access route maintenance.

· The pump system shall be tested to verify proper operation and protection device functionality.

5. Safety and Environmental Compliance

The Contractor shall:

· Comply with all OSHA safety requirements.

· Comply with all NMED standards.

· Minimize disturbance outside the well site and existing access route.

· Implement basic erosion control as necessary to prevent sediment movement from disturbed areas.

· Dispose of removed materials in accordance with applicable regulations.