This is a Performance Work Statement for hazardous waste removal services at the USDA/ARS Tifton research facility in Georgia.

The contractor is required to perform one scheduled removal of hazardous, universal, and selected non-hazardous waste materials from the USDA/ARS Tifton location at 2747 Davis Road, Tifton, Georgia 31794, with disposal to be completed by April 1, 2027. The contractor must furnish all trained labor, materials, safety equipment, chemical stabilization services, containers meeting Department of Transportation specifications, transportation, licenses, permits, and supervision (including a high-hazard chemist if required). The scope includes lab packing, profiling, manifesting, stabilizing, removing, and transporting all waste to a federally approved disposal site. The contractor must sort waste by hazardous properties, wear appropriate protective clothing, properly label all containers, complete Uniform Hazardous Waste Manifests (EPA Form 8700-22), submit manifests to the EPA eManifest system, and provide Certificates of Disposal within three months of waste receipt at the disposal facility. The contractor is responsible for any errors in packing, labeling, or shipping and must monitor and remove any materials or by-products generated during performance. The facility maintains Very Small Quantity Generator status under RCRA and requires compliance with Title 40, CFR Parts 260-268. Contractor staff must coordinate with the USDA/ARS Hazardous Waste Coordinator for pickups Monday-Friday, 7:30 AM to 4:00 PM, excluding federal holidays, and must have personnel trained in Hazardous Waste Operations and Emergency Response procedures. The contractor must be registered in the System for Award Management (SAM) and provide a DUNS number with the bid. All travel expenses must be included in the contract bid. The inventory of materials to be removed includes flammable liquids, Class 9 waste, toxic materials, oxidizers, corrosives, solids, and other hazardous materials in quantities ranging from one to eight containers.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Performance Work Statement

2026 Hazardous Waste Removals for:

USDA/ARS Tifton

2747 Davis Road

Tifton, GA 31794

Contents Project General Information

1.0 Scope of Work

2.0 Background

Contractor Requirements

3.0 Technical Requirements / Tasks

4.0 Government Furnished

5.0 Deliverables / Schedule

6.0 Travel

7.0 Contractor’s Key Personnel

8.0 Security Requirements

9.0 Data Rights ............................................................................................................ Error! Bookmark not defined.

10.0 Section 508 – Electronic and Information Technology Standards ...................... Error! Bookmark not defined.

Project:

One scheduled removal of hazardous, universal, and selected non-hazardous waste from U.S. USDA/ARS Tifton Georgia location.

General Information

1.0 Scope of Work:

The Contractor shall properly lab pack, profile, manifest, stabilize, remove, and transport all hazardous, non-hazardous, and universal waste materials listed on the provided inventories from USDA/ARS Tifton Georgia location to a federally approved hazardous waste or universal waste disposal site.

Place of Performance: USDA/ARS Tifton, 2747 Davis Road Tifton, Georgia 31794

Period of Performance: Disposal to be completed by April 1st, 2027.

2.0 Background

As a research facility, the USDA/ARS Tifton Location produces a varying amount of hazardous waste and maintains a Very Small Quantity Generator (SQG) status as defined by the Resource Conservation and Recovery Act (RCRA) of 1976. The USDA/ARS Tifton location must remain in compliance with all federal and state hazardous waste regulations described in Title 40, Code of Federal Regulations Parts 260-268 and requires contractor assistance to perform a one-time cleanout of lab facilities hazardous waste.

The Agricultural Research Service (ARS) recognizes its responsibilities to ensure that its facilities comply with existing regulations imposed upon entities which generate, transport, store, treat, and dispose of hazardous chemical wastes. The Agency has a need to contract for hazardous, non-hazardous, and universal waste disposal services, from the private sector. The Agency acknowledges that the field of hazardous waste disposal is a dynamic and ever-changing industry which is significantly impacted upon by Federal, State, and Local regulations and by the influx of new technological developments. It is, therefore, mandatory that the successful Contractor demonstrate a high level of competence and technical expertise comparable to that obtained through extensive experience and aggressive compliance with appropriate hazardous waste management regulations as well as complying with Federal procurement regulations. The contractor must comply with all applicable Federal, State, and Local regulations governing the handling, characterizing, stabilizing, packaging, labeling storing, transportation, and disposal of hazardous waste chemicals and other nonregulated materials.

Contractor Requirements

3.0 Technical Requirements / Tasks

The contractor shall furnish all properly trained labor, materials, safety equipment, stabilization of chemicals, containers, transportation, licenses, special permits, and supervision (including a high-hazard chemist if required) to properly remove and dispose of any Hazardous, Non-Hazardous, and Universal waste and their containers from the USDA/ARS, Tifton Georgia 2747 Davis Road 31794 Hazardous Waste Marshaling Area. The contracted company provides all shipping containers (meeting Department of Transportation shipping specifications), stickers, packing material, and transport manifests. Quotes must indicate the price for the lab pack of all items including cost of appropriate personnel to stabilize any chemicals, including high hazard chemicals, for transport.

The Contractor shall monitor, maintain, and remove any materials, waste (by-products), etc., generated because of work performed in accordance with this contract. All such activities must be performed in accordance with applicable Federal, State, and local regulations. The Government will not be liable to the Contractor for the cleanup of spills or any accidental releases to the environment caused through the fault of the Contractor or their Subcontractor.

The contractor must be registered in System for Award Management, (SAM), prior to submitting a bid.

Registration can be obtained through www.sam.gov. Please provide a DUNS number when the bid is submitted.

Pickup Procedures: Contractor personnel shall determine if each waste listed is identified to meet transportation and disposal requirements. Once onsite work begins, transport shall be completed within three Federal workdays. The Contractor's personnel shall wear all protective clothing and equipment necessary to handle and move waste safely. The Contractor shall sort waste by hazardous properties, pack, label, and transport the waste materials to a disposal site approved by the receiving State and EPA, in DOT-approved shipping vehicles in accordance with applicable Federal and State regulations for such shipments. Each container for shipment shall be labeled clearly.

Manifest Preparation and Shipping Data: The Contractor shall provide all data required for waste transportation, treatment, or disposal, and for completion of annual hazardous waste generator reports if required by the regulatory agency or jurisdiction. Uniform Hazardous Waste Manifests (EPA Form 8700-22 or latest revision thereof) shall be properly completed by the Contractor for each waste and shall list each transportation container including any nonhazardous waste or hazardous materials shipped. All manifest information shall be neatly printed or typed and minimally contain that information required by applicable Federal, State, and local hazardous chemical waste regulations.

Waste manifests shall be submitted to Hazardous Waste Coordinator HWC) for review and signatures during routine operating hours and prior to the shipment of waste off-site. The manifest shall be signed by the Contractor's transporter in the presence of the USDA Tifton HWC. Correction of errors in packing, labeling, or shipping shall be the responsibility of the Contractor. Costs associated with these errors shall also be the responsibility of the Contractor. All manifests shall also be submitted to the EPA eManifest system.

Certificates of Disposal: The Certificates of Disposal shall be forwarded to the HWC within three (3) months of the date the waste was received at the disposal facility. The Certificate of Disposal shall: list each container received at the treatment or disposal facility; document the date and method of treatment or disposal and include the appropriate EPA Treatment Code Number if available; and list the http://www.sam.gov/ name and location of the treatment/disposal facility. The Government recognizes that Certificates of Disposal may take up to twelve (12) months to be received due to the lack of incineration capacity. The Contractor is expected to make every effort to provide certificates as quickly as possible, and shall report to the HWC, on a quarterly basis, the status of pending certificates of disposals. If waste is disposed of in a secured chemical landfill facility, the Certificate of Disposal shall also indicate the location within the landfill where the waste container was buried through the use of cell numbers, coordinates, or other appropriate identifiers. All certificates shall also be submitted to the EPA eManifest system.

4.0 Government Furnished

Inventory of all materials to be removed from the USDA/ARS Tifton Georgia Research Laboratory:

5.0 Schedule

Item No. Task Objective Due 1 Removal of all hazardous, universal and non-hazardous material

Empty Hazardous Waste Storage shed in the USDA Tifton Hazardous Waste Marshalling Area

Any workday prior to April 1st, 2027

6.0 Travel

Any travel expenses incurred by Contractor must be included in contract bid.

7.0 Contractor’s Key Personnel

The contractor shall supply qualified staff for the safe removal of all listed wastes. Personnel shall be trained in Hazardous Waste Operations and Emergency Response procedures should a spill occur.

8.0 Security Requirements and Work Schedule

Contractor staff will be required to coordinate with USDA /ARS Hazardous Waste Coordinator on pick-up times and schedules, Monday-Friday (7:30am to 4:00pm are anticipated) excluding federal holidays.

Contractor will be given full, unobstructed access to the Hazardous Waste Marshalling Area

Project:
General Information
1.0 Scope of Work:
2.0 Background
Contractor Requirements
3.0 Technical Requirements / Tasks
The contractor shall furnish all properly trained labor, materials, safety equipment, stabilization of chemicals, containers, transportation, licenses, special permits, and supervision (including a high-hazard chemist if required) to properly remove a...
The Contractor shall monitor, maintain, and remove any materials, waste (by-products), etc., generated because of work performed in accordance with this contract. All such activities must be performed in accordance with applicable Federal, State, and ...
The contractor must be registered in System for Award Management, (SAM), prior to submitting a bid. Registration can be obtained through www.sam.gov. Please provide a DUNS number when the bid is submitted.
4.0 Government Furnished
5.0 Schedule
6.0 Travel
7.0 Contractor’s Key Personnel
8.0 Security Requirements and Work Schedule