This is a Statement of Work for the installation of a stacked washer and dryer system at a USDA AMS Science & Technology Program greenhouse facility. The contractor must provide all labor, tools, equipment, materials, transportation, permits, and incidentals to complete the installation. The scope includes removal and disposal of an existing double-bowl utility sink and installation of a new single-bowl utility sink with hot and cold water supply and drain connections. The contractor must install complete service infrastructure for the stacked washer and dryer set, including a new dryer exhaust vent with exterior weatherproof cover and core-drilled vent hole, a 230VAC single-phase electrical circuit for the dryer originating from the existing electrical panel (not exceeding 30 feet run length) with required breaker, conduit, and outlet complying with the National Electrical Code, and a 2-inch plumbing drain washer box with PEX hot and cold supply lines. Additional work includes installation of a 120VAC single-phase 6-gallon tank-type water heater with all plumbing and electrical connections, cinder block wall demolition to access the existing drain line, and installation of the government-furnished Samsung frontload washer and dryer with required stacking attachment kit, leveling, and securing.

Deliverables include a fully installed and operational washer and dryer system, functional single-bowl sink with hot and cold water and drain, completed dryer venting system, completed electrical circuit with panel inspection, installed water heater with operational hot water supply, cleaned site with waste removal, and provided warranty information and documentation. The contractor must coordinate facility entry and any electrical panel access or water shutdowns with USDA personnel and ensure compliance with all applicable local, state, and federal codes. Work must be scheduled during normal business hours (Monday through Friday, 7 a.m. to 5 p.m.) or coordinated evenings and weekends with the designated point of contact, with completion timeframe to be negotiated after contract award while minimizing disruptions to facility operations. Acceptance is contingent upon verification of complete and functional installations, code compliance inspection, debris removal confirmation, and receipt of warranties and documentation.

View the file

Other files

File Type Posted
Site visit attendance.pdf PDF
RFIs and responses.docx DOCX document
Photos 1.pdf PDF
Photos 2.pdf PDF
12639526Q0143.docx DOCX document
Attachment 2_Federal Construction Wage Rates_Gaston County.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12639526Q0143, Attachment 1

US Department of Agriculture (USDA)

Statement of Work

Contents

Project3
General Information3
1.0Background3
2.0 Scope of Work3

3.0 Contractor Responsibilities

4.0 Government Furnished4
5.0 Deliverables / Schedule4
7.0 Site Access & Security4
Contractor shall coordinate entry to the greenhouse facility with the Resource Management Office. Visitors must follow all AMS site-entry procedures.4

Project Installation of Washer and Dryer in Greenhouse

General Information

1.0 Background

The AMS Science & Technology Program operates a greenhouse facility requiring the installation of a stacked washer and dryer to support laboratory and operational needs. The program already owns a Samsung front‑load washer and dryer set, which is compatible with stackable installation. A stacking kit needs to be supplied and installed as part of the project.

The installation area is located along an exterior wall in the greenhouse entryway. Existing plumbing must be reconfigured, and new electrical, ventilation, and structural modifications are required.

2.0 Scope of Work

The contractor will provide all labor, tools, equipment, materials, transportation, permits, and incidentals necessary to complete the following tasks:

2.1 Removal and Disposal

· Remove and properly dispose of the existing double‑bowl utility sink.

2.2 Installation of New Utility Sink

· Install one (1) single‑bowl utility sink.

· Install all required sink drain plumbing, including tie‑in to existing drain line.

· Install hot and cold supply water piping routed to new sink configuration.

2.3 Washer and Dryer Service Infrastructure

The contractor shall install all infrastructure required to support one (1) stacked washer and dryer set, including:

2.3.1 Dryer Venting

· Install new dryer exhaust vent piping from the unit location to the exterior wall.

· Install an exterior weatherproof vent cover.

· Core drill one vent hole to support the installation.

2.3.2 Electrical Work

· Install one (1) 230VAC, 1‑phase electrical circuit for the dryer.

· Circuit shall originate from the existing 230/110 VAC 3/0 electrical panel, not to exceed 30 ft in total run length.

· Provide and install:

· One (1) panel breaker

· Appropriate electrical metallic tubing (EMT) and/or liquidtight conduit (LQT)

· All required fittings

· Thermoplastic High Heat-resistant Nylon-coated wire (THHN)

· Dryer receptacle outlet

· All electrical work must comply with the National Electrical Code (NEC).

2.3.3 Plumbing for Washer

· Install a 2" plumbing drain washer box, tied into the existing sink drain line.

· Install ½" Crosslinked polyethylene (PEX) hot and cold supply lines routed to the washer box.

2.4 Water Heater Installation

· Install one (1) 120VAC, 1‑phase, 6‑gallon tank‑type water heater, including:

· All plumbing connections

· All electrical connections

· Any mounting hardware required

2.5 Structural Modifications

· Cinder block wall demolition will be required to reach and tie into the existing drain line.

2.6 Washer & Dryer Installation

· Install customer‑provided Samsung front‑load washer and dryer.

· Provide and install required stacking attachment kit.

· Ensure units are leveled, secured, and fully functional.

3.0 Contractor Responsibilities

The contractor will:

· Supply all materials unless noted as Government‑furnished (washer/dryer only).

· Coordinate any electrical panel access or water shutdowns with USDA personnel.

· Ensure compliance with all applicable local, state, and federal codes.

· Maintain a clean and safe work environment.

· Properly dispose of all construction debris.

· Provide warranty information for all fournished equipment.

4.0 Government Furnished

· One (1) Samsung front‑load washer

· One (1) Samsung front‑load dryer Both units are owned by the laboratory and must be installed as a stacked configuration.

5.0 Deliverables / Schedule

· Fully installed and operational washer and dryer system.

· Installed single‑bowl sink with functional hot/cold water and drain.

· Completed dryer venting system.

· Completed electrical circuit and inspected connection to panel.

· Installed water heater with operational hot water supply.

· Site cleaned and all waste removed.

Normal business hours are Monday through Friday, 7am to 5pm. If the contractor is available evenings or weekends, this will be coordinated with the designated point of contact.

6.0 Period of Performance

The contractor shall complete all work within the timeframe negotiated after contract award. Work must be scheduled to minimize disruptions to facility operations.

7.0 Site Access & Security

Contractor shall coordinate entry to the greenhouse facility with the Resource Management Office. Visitors must follow all AMS site-entry procedures.

8.0 Acceptance Criteria

AMS will accept the work upon:

· Verification that all installations are complete and functional.

· Inspection confirming compliance with code requirements.

· Confirmation that all debris has been removed.

· Receipt of warranties and documentation.