RFIs and Responses.docx
DOCX document 15 KB Posted
- Attached to
- Replace Siding, Moore Air Base, TX Federal contract opportunity
- Solicitation number
- 12639525Q0169
About this file
The document is an RFI (Request for Information) file containing site visit questions and responses for Solicitation 12639525Q0169, a USDA-Animal and Plant Health Inspection Service construction project to replace siding at Building 6418 on Moore Air Base in Edinburg, Texas. The project involves removing existing metal corrugated siding and replacing it with Hebel wall panels, specifically for the Mexican Fruit Fly Rearing Facility. The solicitation is exclusively set aside for service-disabled veteran-owned small businesses under NAICS code 238170, with a small business size standard of $19 million and an estimated project value between $500,000 and $1 million.
The RFI reveals specific site details through a Q&A format, including confirmation that no as-built drawings or construction photos are available for the building addition. The contractor is instructed to include new moisture barrier in the quote if the existing barrier is in disrepair, and stucco is recommended as the most cost-effective finish when using the Hebel system. The contracting officer for this opportunity is Jim Roloff, who can be contacted at james.g.roloff@usda.gov for any questions about the solicitation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFIs and Responses 2.docx | DOCX document | |
| Project site visit attendance.pdf | ||
| Atch 2_Federal Construction Wage Rates_Hidalgo County.pdf | ||
| Atch 1_SOW_ B6418 Insulation Installation.docx | DOCX document | |
| 12639525Q0169.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Visit Questions, Solicitation 12639525Q0169 Replace Siding Bldg 6418
1. Are there any as bult drawings available for the building addition?
None that pertain to the outside of the building or the addition.
2. Are there any construction photos available of the addition?
No
3. What will finished wall be (stucco most cost-effective).
Stucco if the Hebel system is used.
4. If air and moisture barrier is in disrepair it will need to be replaced as these products require it. Would you like new moisture barrier included in cost or would you rather handle that as it is found to be in disrepair?
Yes, include with your quote.