This is a Questions and Answers document for Solicitation 12639525Q0022 for janitorial services at USDA APHIS PPQ CHRP's Palm Bay Work Unit facility. The document clarifies that the contract is for one location only, with facility details including 14 windows of varying sizes (three 2'x3', four 8'x3', two 8'x4', and an entrance glass wall with door), with cleaning required up to 8' height.

The document reveals there is an incumbent contractor under Contract No. 12639524C0027 with a one-year contract value of $10,188. Other key clarifications include: only one contractor will be awarded the contract, no performance bond is required, and service frequency details are specified in section 2.6 of the Performance Work Statement. The facility is approximately 8,000 sq ft with one floor, two bathrooms, six office rooms, and one conference room. Questions must be submitted in writing to Kim Yen Tu, with no phone inquiries accepted.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 12639525Q0022: Questions and Answers

Question: How many Windows and what are the general sizes?

Answer: 14 Windows. 3 Small like 2’x3’. 4 large 8’x3’, 2 large 8’x4’. Entrance is basically a wall of glass with a glass door. Facility would only expect the floor to about 8’ to be cleaned. These are all general guessed on dimensions

Question: Could we verify the total number of locations included in this contract? Is it possible to increase?

Answer: Sorry for the confusion. This contract is for one location as stated in the performance work statement.

Question: Is there an incumbent contractor? Can you provide information.

Answer: Contract No. 12639524C0027 One year contract for $10,188

Question: Are the frequency of services 2 days per week or 5 days per week? Or what is the specific frequency of services?

Answer: Please read through section 2.6 Duties/Tasks on the PERFORMANCE WORK STATEMENT. It goes over the required services and the frequency required.

Question: Will the contract be awarded to 1 or several contractors?

Answer: Only one contractor will be awarded

Question: Can the location be visited at any time?

Answer: Please read the solicitation instructions about site visits.

Question: Is a performance Bond required?

Answer: No