Questions and Answers.docx

DOCX document 12 KB Posted

Attached to
Floor Replacement
Solicitation number
12505B21Q0017
Issued by

View the file

Other files

File Type Posted
Statement of Work.docx DOCX document
SCA Wage Rates.pdf PDF
MB-401 Drawing.pdf PDF
12505B21Q0017.pdf PDF
Statement of Work.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question: Could you please tell me if the Combined Synopsis/Solicitation posted as solicitation number 12505B21Q0017 will be a follow-on requirement to any work performed currently or in the past, or will this be a new requirement?

If possible, can you please provide the most recent contract or task order number?

Answer: This work is a new requirement.

Question: What are the existing floor coverings in the project area? The Scope of Work indicates removal of carpet. Is carpet the only floor covering in the project area, or is there existing vinyl composite tiles as well?

Answer: Carpet is the only floor covering in the project area.