Questions and Answers.docx
DOCX document 12 KB Posted
- Attached to
- Floor Replacement Federal contract opportunity
- Solicitation number
- 12505B21Q0017
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Statement of Work.docx | DOCX document | |
| SCA Wage Rates.pdf | ||
| 12505B21Q0017.pdf | ||
| Statement of Work.docx | DOCX document | |
| MB-401 Drawing.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question: Could you please tell me if the Combined Synopsis/Solicitation posted as solicitation number 12505B21Q0017 will be a follow-on requirement to any work performed currently or in the past, or will this be a new requirement?
If possible, can you please provide the most recent contract or task order number?
Answer: This work is a new requirement.
Question: What are the existing floor coverings in the project area? The Scope of Work indicates removal of carpet. Is carpet the only floor covering in the project area, or is there existing vinyl composite tiles as well?
Answer: Carpet is the only floor covering in the project area.