This document is a Design Analysis for a federal construction project involving the redesign of Building 4 at Moore Field in Edinburg, Texas, under USDA APHIS contract 12805B23D0001, Task Order 1232SA25F03843. The project, prepared by The Johnson-McAdams Firm, P.A., is dated August 31, 2026, and focuses on converting an existing experimental dip vat facility into a practical, higher-capacity cattle-processing facility for USDA ARS operations supporting the Cattle Fever Tick Research Laboratory mission.
The 95% design proposes to modernize Building 4 through expanded cattle pens, improved circulation, an enlarged open-sided canopy with straight-column rigid frames and 8-inch purlins at approximately 5-foot on-center spacing, water service, LED lighting, and convenience power. The project scope includes eleven pens ranging from approximately 200 to 533 square feet, a rotunda/holding area, 42-inch circulation paths, 6-inch reinforced concrete walkways, overhead PEX water distribution serving wall hydrants and float valves, and a 100A 120/208V 3-phase electrical panelboard with vapor-tight LED fixtures controlled by astronomical time clock. The Base Bid utilizes red-oxide-coated fencing and gates with safety-yellow alkyd paint bollards, with galvanizing carried as Additive Alternate No. 2. The current Base Bid estimate totals $1,031,810 (103.2% of the $1,000,000 Estimated Construction Cost), exceeding the PRD ceiling of $900,000 by $131,810 and requiring value engineering before final issuance. The design establishes a programmed ECC limit of $1,000,000 with requirements that the Base Bid remain within 90 percent of ECC and all additives remain within overall programmed construction funding. Critical design considerations include protection of the active USDA ARS biosecurity installation during construction, maintenance of existing roads and utilities, construction sequencing that minimizes operational disruption, and field verification of dimensions, grades, and utility locations before procurement.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN ANALYSIS
EDINBURG-KERRVILLE BLDG 4
DIP VAT REDESIGN – A-E
PREDESIGNAND DESIGN
SERVICES
PN: T.B.D.
MOORE FIELD EDINBURG, TX
Prepared For:
U.S. Department Of Agriculture
USDA APHIS
5601 Sunnyside Avenue
RM 3-2102
Beltsville, Maryland 20705
Contract No.
12805B23D0001
Task Order No.
1232SA25F03843
Prepared By:
The Johnson-McAdams Firm, P.A.
Greenwood, Mississippi
Friday, August 31, 2026 i
TABLE OF CONTENTS
Executive Summary
1.0 Project Overview
2.0 Basis of Analysis
3.0 Project Requirements and Functional Intent
4.0 Existing Conditions and Site Constraints
5.0 Proposed Design Summary
6.0 Key Design Criteria
7.0 Discipline Review
7.1 Civil / Site / Concrete
7.2 Structural
7.3 Architectural / Operational Layout
7.4 Roofing
7.5 Plumbing
7.6 Electrical
8.0 Budget and Phasing Considerations
8.1 Cost Estimate Review
8.2 Phasing
8.3 Estimate Basis and Markups
Edinburg-Kerrville BLDG 4 Dip Vat Redesign - Design Analysis
Executive Summary
The proposed 95% redesign modernizes Building 4 and activates the existing dip vat and drip pad through expanded cattle pens, improved circulation, a larger open-sided canopy, water service, lighting, convenience power, and durable concrete access. The current design uses straight-column rigid frames, 8-inch purlins at approximately 5 feet on center, roof-plane bracing only, and exposed-fastener metal roof panels over 1/4-inch foil-faced reflective insulation. The Base Bid uses red-oxide-coated fencing and gates with bollards finished in safety-yellow alkyd paint; galvanizing is carried as Additive Alternate
No. 2. The operational concept remains responsive to the PRD, but the current cost estimate exceeds both the PRD Base Bid ceiling and total programmed construction funding and therefore requires value engineering before final issuance.
1.0 Project Overview
The Edinburg-Kerrville BLDG 4 Dip Vat Redesign project is intended to convert an existing experimental vat area that is currently not in use into a practical, higher-capacity cattle-processing facility for USDA ARS operations at Moore Field in Edinburg, Texas.
The Project Requirements Document states that Building 4 contains an experimental vat that was never used and an animal pen arrangement that is too small to process the number of cattle the research barn can hold. The redesign therefore focuses on making the existing dip vat and drip pad operational by enlarging the penning system, improving circulation, and providing the support systems necessary for daily use once the facility is returned to service.
The attached 95% design package reflects this intent through a covered penning layout, interior and exterior gates, maintenance access, a loading arrangement, water service, lighting, and convenience power.
2.0 Basis of Analysis
This design analysis is based on the following documents reviewed for this task:
Document Date Primary Use
FY 25 PRD Edinburg-Kerrville BLDG 4 Dip Vat Redesign 08/26/2025 Project purpose, budget, submittal requirements, and program criteria
95% Dip Vat Drawings 04/20/2026 Facility layout, discipline drawings, alternates, and project-specific details
Project Specifications 2026 issue set Technical requirements, submittals, materials, finishes, and execution criteria
3.0 Project Requirements and Functional Intent
The PRD establishes a clear operational goal: maximize the efficiency of the existing dipping vat and drip pad so the facility can process more cattle and better support the
Cattle Fever Tick Research Laboratory mission. The required features include larger pens, exterior gates for skid-steer access, gates between pens, alleys to and from the vat, access to a cattle chute from any pen, water in each pen, lighting, 120-volt receptacles, and a loading pen for trailer operations.
The 95% overall plan responds directly to the PRD by organizing the Base Bid cattle-handling system around the existing vat, with associated feed troughs, water trough locations, wall-hydrant drops, maintenance gates, internal movement gates, a holding/rotunda area, and improved circulation. Additive Alternate No. 1 provides the additional pen work identified on the drawings and must remain clearly separated from the complete and operational Base Bid.
4.0 Existing Conditions and Site Constraints
The project is located within an active USDA ARS livestock research installation operating under biosecurity controls. While the existing Building 4 dip vat facility is currently not in use, the specifications still require the contractor to protect surrounding research operations, animal movement, and site access throughout construction. The existing dip vat and drip pad are specifically identified as integral facilities to be protected, except where contract modifications are shown.
The site is also constrained by the need to keep existing roads, pens, gates, and utilities functional during construction. Field verification of dimensions, grades, and utility locations is required before procurement or installation. This is especially important because the work interfaces with an existing vat, existing structural framing, and existing utility infrastructure.
Construction sequencing is therefore a major design consideration. The specifications require phasing that maintains Government operations, limits disruption, and coordinates utility extensions, pen construction, and electrical and water tie-ins to minimize downtime and temporary conditions.
5.0 Proposed Design Summary
The overall design concept is a practical, open agricultural handling structure built around the existing vat. The drawing set indicates eleven pens with areas ranging from approximately 200 square feet to 533 square feet, plus a rotunda/holding area, 42-inch circulation path, trailer loading relationship, and dedicated maintenance gates. The canopy and framing layout create a controlled environment for moving cattle through the dip process while still allowing service access and washdown operations.
Architecturally and operationally, the project is driven more by animal handling efficiency, durability, and maintainability than by conventional occupied-building criteria.
That design approach is appropriate for the facility type and consistent with the PRD.
6.0 Key Design Criteria
Item Current Basis Observation
Programmed ECC $1,000,000 Base bid is to remain within 90 percent of the
ECC, with additives held within the overall programmed limit.
Pen Count 11 pens Pen areas shown on the overall plan range from approximately 200 SF to 533 SF.
Roof Slope 2:12 Consistent between the drawings and the metal building specifications.
Eave Height 8' - 5 1/2" Specified in the metal building system requirements.
Walkway Construction 6-inch concrete over 6-inch Reinforced with 4x4-W4xW4 welded wire aggregate base mesh and heavy broom finish perpendicular to travel.
Water Service Connect to existing 1-inch line Overhead PEX distribution serves wall hydrants and float valves in the pens.
Electrical Service 100A, 120/208V, 3-phase, 4-wire, NEMA 3R panel Connected load is modest and consistent with lighting plus convenience receptacles.
Foundation Bearing 1,000 psf allowable bearing Conservative basis; verify against final delegated-design reactions and any geotechnical information obtained later.
Wind / Risk Criteria - drawings 134 mph ultimate, Risk Category I Shown in structural general notes on S001.
PEMB Framing Straight columns; roof-plane bracing only
Final member sizes and bracing remain subject to delegated engineering.
Purlins 8-inch depth at approximately 5 feet O.C.
Cost and layout basis; confirm strength, uplift, bridging, and existing interfaces.
Roof Assembly Exposed-fastener panels over 1/4-inch foil-faced insulation
Reflective/condensation-control assembly; not equivalent to a 2-inch insulated panel.
Base Bid Steel Finish Red-oxide coating; safety-yellow alkyd on bollards
Specifications must remove mandatory galvanizing from Base Bid fencing, gates, and bollards.
Additive Alternate No. 2 Galvanized fencing, gates, and bollards
Coordinate drawings, specifications, bid schedule, and premium for all accepted alternate steel.
7.0 Discipline Review
7.1 Civil / Site / Concrete
The civil/site scope is limited but important because the project must operate in a wet, livestock-heavy environment. The walkway layout indicates 6-inch concrete reinforced with
4x4-W4xW4 welded wire mesh over 6 inches of crushed aggregate base, finished with a heavy broom texture perpendicular to the path of travel. This is a practical assembly for washdown conditions, hoof traffic, and routine facility maintenance.
The specifications also emphasize maintaining existing drainage paths and preventing sediment, debris, concrete washout, and other contaminants from entering the vats, pads, drains, troughs, and adjacent livestock areas. Although the PRD marks erosion and stormwater items as not applying to the project scope, the narrative still describes erosion and runoff protection measures that should be carried forward as construction-phase controls.
7.2 Structural
The structural concept is a shallow-foundation system supporting an expanded pre-engineered metal building canopy. The revised basis uses straight columns, 8-inch purlins at approximately 5 feet on center, and permanent cross-bracing in the roof plane only.
Structural notes establish a preliminary 1,000 psf allowable soil bearing pressure and frame reactions for bidding. If final PEMB reactions differ by more than 10 percent, the contractor must resize affected footings under the delegated design requirements.
The specifications require delegated design by a Texas-licensed professional engineer and signed and sealed calculations and shop drawings for the complete metal building system, including verification of the existing structure, new straight-column frames, purlin extensions, roof-plane bracing, connections, and foundations. The 8-inch purlin depth and nominal 5-foot spacing are cost-estimate criteria and must be confirmed by the PEMB engineer for final wind, uplift, diaphragm, and stability demands.
7.3 Architectural / Operational Layout
The architectural package supports the cattle-handling mission with a straightforward pipe-rail and gate layout. The enlarged plans show reverse swing gates, sliding gates, maintenance gates, rail infill at existing openings, and full-height blackout panels at the rotunda area. The overall plan also shows the holding area, truck/trailer relationship, and a new level concrete access surface above the existing vat access.
From an operational standpoint, the layout satisfies the PRD requirement for moving cattle between pens, to the vat, and back to pens while preserving outside access for equipment. The use of multiple gate types is deliberate and supports flexible movement control.
The A/E has had a full-scale working model of the reverse swing gate constructed and will schedule a time to bring it to the facility to demonstrate its use. The gate was developed to reduce the number of gates required and to aid in the safe movement of cattle for both the cattle and facility personnel. The gate can be opened from either gate post and creates a gentle angle to move cattle through the system, eliminating sharp ninety-degree turns.
7.4 Roofing
The revised roof basis is a standard exposed-fastener metal roof panel system installed over approximately 1/4-inch-thick foil-faced Prodex Total 5M Plus reflective insulation.
The thin reflective insulation is a cost-conscious agricultural-canopy assembly intended primarily to reduce radiant heat gain and condensation potential.
7.5 Plumbing
The work includes extending the existing potable water distribution system from the existing PVC water main to provide domestic cold-water service throughout the cattle handling chute. Existing domestic water piping will be demolished as required to install a new full-port isolation valve that will permit shutoff and complete drainage of the modified portion of the water distribution system for maintenance and seasonal winterization. The
PEX water distribution piping will be connected to the existing PVC water piping using approved transition fittings installed in accordance with the manufacturer's recommendations.
An insulated, weatherproof, cast-in-place concrete valve access box with the access cover flush with the finished floor will be provided to allow access to the new isolation valve while protecting the valve from environmental exposure and physical damage. Piping supports, fittings, and accessories will be selected for the agricultural environment and installed to accommodate existing site conditions while minimizing disruption to the existing facility. Following completion of the work, all disturbed surfaces and utilities will be restored to match existing conditions.
The domestic water distribution system will be routed overhead within the cattle handling area and will provide service to automatic livestock waterers and wall-mounted wall hydrants. Wall hydrants will be provided at locations indicated on the drawings to support cleaning, washdown, and routine maintenance operations within the facility.
Freeze-resistant, self-draining wall hydrants with integral vacuum breakers will be provided to protect the potable water system from back siphonage and to minimize the potential for freeze damage during cold weather.
Automatic livestock waterers will be supplied through high-flow, float-operated fill valves with integral manual lock-off capability to maintain the required water level within each owner-provided water trough to allow for isolation of the waterers without individual valving. Float valves will be constructed of corrosion-resistant materials suitable for continuous livestock service and installed within a protective chamber or enclosure to reduce the potential for damage from animals and routine operations. Waterer installation and float valve configuration will be coordinated with the selected equipment manufacturer and installed in accordance with the manufacturer's requirements.
The design utilizes the existing domestic water supply and does not significantly increase the facility domestic water demand. Existing available water pressure is expected to be adequate to serve the proposed plumbing fixtures without requiring additional booster pumping or storage. The modified plumbing system will be designed and installed in accordance with the International Plumbing Code (IPC), USDA Agricultural Research
Service design requirements, and all applicable federal, state, and local codes and standards.
7.6 Electrical
The electrical demolition scope includes demolishing all electrical on the building. All circuits fed from panel BLDG 4 must be demolished. All light fixtures and receptacles must be demolished. Panel BLDG 4 must be demolished, but the conduit and conductors are to be preserved and protected for reuse. The contractor must field verify that the existing conduit and conductors feeding BLDG 4 are undamaged and properly supported and report any deficiencies to the engineer.
Provide and install a new 100A, 120/208V, 3-phase, 4-wire, NEMA 3R panelboard with a type 2 SPD. The new panelboard must be fed from DP utilizing the existing breaker, conduit, and conductors. DP is an existing outdoor distribution panelboard. The panelboard must be grounded with 2 (3/4” diameter X 10’ long) copper clad ground rods separated by a minimum of 10 ft. The cattle fencing and building steel bust be bonded and grounded to a main building busbar.
Provide new vapor-tight LED luminaires throughout the structure to achieve uniform illumination with a maximum average-to-minimum ration of 2:1 and a maximum illumination level of 4 foot-candles. Fixtures must have a correlated color temperature of 3000k to support low-stress nighttime conditions for livestock. The contractor shall provide Unistrut framing as required to support fixture mounting across structural beams. Lighting must be controlled by an astronomical time clock with 0-10V dimming capability and manual off/on.
Provide new receptacles with weatherproof covers fed from GFCI breakers. One receptacle must be at each end of the dip vat. Provide additional receptacles mounted at
90 inches AFF on columns to accommodate user provided circulation fans as required.
8.0 Budget and Phasing Considerations
8.1 Cost Estimate Review
The PRD establishes an Estimated Construction Cost (ECC) limit of $1,000,000 for FY
26, limits the Base Bid to 90 percent of ECC, and requires the Base Bid plus all additives to remain within ECC. The revised estimate totals $1,031,810 for the Base Bid, $48,855 for
Additive Alternate No. 1, and $22,182 for Additive Alternate No. 2. The Base Bid alone is
$131,810 above the strict $900,000 PRD ceiling and $31,810 above the full ECC.
Review Item Amount Percent of ECC Funding
Programmed ECC / Available Funding $1,000,000 100.0% PRD Base Bid Ceiling (90% of ECC) $900,000 90.0% Current Base Bid – red oxide / yellow bollards $1,031,810 103.2% Additive Alternate No. 1 $48,855 4.9% Additive Alternate No. 2 – galvanized finish $22,182 2.2% Base Bid + both additives $1,102,847 110.3% Required Base Bid reduction to PRD ceiling $131,810 13.2% of ECC
The Base Bid represents 103.2 percent of ECC and 114.6 percent of the PRD Base Bid ceiling. Base Bid plus both listed alternates totals $1,102,847, or $102,847 above ECC.
Additive Alternate No. 1 represents approximately 4.9 percent of ECC and Additive
Alternate No. 2 approximately 2.2 percent; together they represent 7.1 percent. If the Base
Bid is reduced to $900,000, the two listed alternates would produce a combined total of approximately $971,037, within the overall ECC. Accordingly, the design is not presently within funding and requires at least $131,810 of Base Bid reduction, with an internal target of $850,000 to $875,000 recommended for bid-market headroom.
Detailed Cost Estimate:A detailed cost estimate is delivered under separate cover and is incorporated into this cost review by reference.
8.2 Phasing
Phasing is also central to the design because the Government will continue to operate the surrounding research facility during construction. The specifications require coordination of disruptive activities, temporary barriers and fencing, end-of-day hazard control, and advance notice for utility interruptions and major operations. These requirements are consistent with the biosecurity nature of the site and should be reflected clearly in the final construction documents.
8.3 Estimate Basis and Markups
The revised estimate applies 8 percent general conditions to direct cost, 7 percent contractor overhead to cost including general conditions, 5 percent profit to cost including overhead, and 1.5 percent bond/insurance to cost including profit.
The principal Base Bid direct-cost drivers are cattle railing and gates at approximately $317,975, structural steel/PEMB at $130,000, general direct costs at $86,700, concrete at $80,443, electrical at $69,603, and roofing at $56,938.
| Cover |
| Revised_Design_Analysis_v7_With_Cover_and_TOC (2) |
| Executive Summary |
| 1.0 Project Overview |
| 2.0 Basis of Analysis |
| 3.0 Project Requirements and Functional Intent |
| 4.0 Existing Conditions and Site Constraints |
| 5.0 Proposed Design Summary |
| 6.0 Key Design Criteria |
| 7.0 Discipline Review |
| 7.1 Civil / Site / Concrete |
| 7.2 Structural |
| 7.3 Architectural / Operational Layout |
| 7.4 Roofing |
| 7.5 Plumbing |
| 7.6 Electrical |
| 8.0 Budget and Phasing Considerations |
| 8.1 Cost Estimate Review |
| 8.2 Phasing |
| 8.3 Estimate Basis and Markups |