Q and A_12445526B0007.xlsx
XLSX spreadsheet 36 KB Posted
- Solicitation number
- 12445526B0007
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Questions and Answers document for IFB 12445526B0007, the Monongahela National Forest FR76 Embankment Stabilization Project. The Q&A addresses eight contractor inquiries received between May 12-14, 2026, regarding project execution and technical specifications.
Key clarifications include: the Forest Service will post the site visit attendee list; simultaneous work at both project sites is permitted with prior schedule approval; stream diversion must utilize culverts in existing channels without destabilizing banks, with continuous pumping required once started; H-pile splices must be located in the bottom third of piles with maximum two splices per pile, each at least 10 feet long; pile wall distances require surveying under item 15201 but can be estimated from plan sheets; upper roadside work at site 2 is limited to requirements specified in project plans; drilling material not incorporated into the project must be removed from Forest Property; and woody debris in the stream channel at site 1 may be cut and placed within the stream channel and wasted within construction limits, with exact placement subject to Contracting Officer Representative approval.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Opening_12445526B0007.docx | DOCX document | |
| SIGN IN SHEET_PRE-BID_12445526B0007.pdf | ||
| Q and A_12445526B0007.xlsx | XLSX spreadsheet | |
| Amd_0002_12445526B0007.pdf | ||
| Amd_0001_12445526B0007.pdf | ||
| HOW TO FOLLOW PROJECTS ON SAM FOR EMAIL ALERTS.pdf | ||
| Att 03_FP-14 Standard Specifications.pdf | ||
| Att 01_SCHEDULE OF ITEMS FR 76 EMBANKMENT REPAIR PROJECT (ERFO).xlsx | XLSX spreadsheet | |
| Sol_12445526B0007.pdf | ||
| Att 05_Wage Rates.pdf | ||
| Att 02_SOW - FR 76 Embankment Stabilization.docx | DOCX document | |
| Att 04_Embankment Stabilization Project_Drawings.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| IFB | 12445526B0007 | |||
| Title | FR76 EMBANKMENT STABILIZATION PROJECT | |||
| File Last Updated | 2026-05-14 | |||
| Question | ||||
| Number | Date | |||
| Received | Question | FS Response | ||
| 1 | 2026-05-12 | Will you be posting the site visit attendee list? | Yes | |
| 2 | 2026-05-14 | Can both work sites be worked at the same time? | Yes, though the work schedule will have to be approved prior to start of work, it would be possible for work to proceed at both sites simultaneously. | |
| 3 | 2026-05-14 | For stream diversion, can the stream bank be excavated and a culvert be utilized to move the water? | No, A culvert can be utilized in the existing stream channel. However, the stream bank cannot be destablilized by excavation. A culvert could be used for a portion of the dewatering and a pump around system utilized for the remainder as needed. However once pumping starts it is to be continuous until instream work is completed, to avoid repeated flushing of material into the stream channel. | |
| 4 | 2026-05-14 | Can you please clarify the requirement for splicing in the bottom sections of the H-piles? | As per plan notes, all splices (welds) shall be in the bottom 1/3 of the pile. No more than two splices are allowed per pile, and all splices must be at least 10 feet long. | |
| 5 | 2026-05-14 | How far away from the road are the pile walls? | Pile wall locations will have to be surveyed under item 15201 "Construction Survey and Staking". For estimation purposed, the distance can be scaled from the project plan sheets. | |
| 6 | 2026-05-14 | Is there any work required on the upper side of the roadway at site 2? | Required work on the cutbank side of the slide will only be as required and specified in the project plans. | |
| 7 | 2026-05-14 | Will the material from the drilling operation have to be removed from the project site? | Some material may be utilized to dress in the slopes. However, all material not incorporated into the project will have to be removed from Forest Property. | |
| 8 | 2026-05-14 | Does woody material, currently in the stream channel at site 1, need to be removed from the project site? | No, woody debris within the stream channel can be cut and placed within the stream channel and wasted within the construction limits. Exact placement will be approved by the COR when stream work is being completed. |