12445525R0003_Attachment_2_SOW_GMNF_FR278-0_24_Bridge_Superstructure_Replacement_1.docx

DOCX document 28 KB Posted

Attached to
GAOA Forest Road 278 Bridge Structure Replacemet GMNF Federal contract opportunity
Solicitation number
12445525R0003
Issued by
Department of Agriculture Forest Service

About this file

This document is a Statement of Work (SOW) for the Forest Road 278 Bridge Superstructure Replacement project in the Green Mountain National Forest. The contract involves removing the existing bridge superstructure and deck, and constructing a new bridge structure, including fabrication, erection, guardrail installation, and associated site work. The project is located in Woodford, Vermont, Bennington County, and is part of a solicitation issued by the Department of Agriculture Forest Service.

The project schedule specifies construction starting after June 1, 2025, with all in-stream work restricted to July 1 through September 30, 2025. The total project must be completed by October 31, 2025, with a critical requirement that the road and bridge cannot be closed for more than 2 months during the contract period. The solicitation number is 12445525R0003 and is categorized as a Special Notice opportunity under the Great American Outdoors Act (GAOA) for forest road infrastructure improvement.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FR278 Bridge Superstructure Replacement

SECTION C – DESCRIPTION/SPECIFCIATIONS/STATEMENT OF WORK

Scope of Contract The Forest Road 278 – 0.24 Bridge Superstructure Replacement Contract work shall include, but is not limited to, removal of existing bridge superstructure and deck; furnishing, fabricating, and erecting the bridge superstructure and deck; bridge and guardrail installation; and associated road and site work.

The Contractor shall furnish the necessary personnel, material, equipment, services, traffic control, and facilities (except as otherwise specified), to perform the Work in accordance with the Specifications in Attachment 4 Plans.

Project Schedule Construction shall start after June 1, 2025. All in-stream work shall be between July 1 and September 30, 2025. Final project completion shall be no later than October 31, 2025. The road and bridge shall not be closed for more than 2 months during the contract period performance.

Project Location FR278-0.24 bridge is located on the Green Mountain National Forest in Woodford, VT in Bennington County.