Abstract of Bids 250714.xls
XLS spreadsheet 60 KB Posted
- Attached to
- GAOA SUF Forest Road 152 South Brule River Bridge Replacement Federal contract opportunity
- Solicitation number
- 12445525B0004
- Issued by
- Department of Agriculture Forest Service
About this file
The document is a Bid Abstract for a bridge replacement project by the US Forest Service in Cook County, Minnesota. The solicitation (12445525B0004) seeks a contractor to replace the Forest Road 152 South Brule River Bridge using a Firm-Fixed Price Contract. Five vendors submitted bids, with total bid amounts ranging from $390,441 (Gustav & Rudy HUOT) to $3,769,929.69 (Nordic Group). The project involves multiple construction activities including excavation, roadway finishing, erosion control, timber pile installation, bridge superstructure work, and traffic control, with 36 distinct line items covering various construction elements.
Key requirements include mandatory SAM registration, with the project located in Superior National Forest. The bid abstract details unit prices for each construction item across five bidders, showing significant variance in pricing strategies. Vendors include Day Services LLC, Gustav & Rudy HUOT, CS Nordic Group, Winberg, and an unnamed fifth bidder. The government estimate and detailed breakdown provide insight into the complex bridge replacement project, which involves substantial earthwork, structural components, and environmental mitigation measures. The solicitation indicates one contract will be awarded following Federal Acquisition Regulation (FAR) Part 14 sealed bidding procedures.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12445525B0004 Amendment 0001 250707.pdf | ||
| Att. 2 Plans 250523.pdf | ||
| Att. 4 Supplemental Specs 250220.pdf | ||
| Att. 5 Project Map 250523.pdf | ||
| Att. 6 NEPA 250523.pdf | ||
| Att. 7 Wage Determination - MN20240231 250502.pdf | ||
| IFB Solicitation 12445525B0004 250529.pdf | ||
| Att. 1 Schedule of Items 250529.docx | DOCX document | |
| Att. 3 SOW 250523.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| BID ABSTRACT | |||||||||||||||
| ISSUING OFFICE: | R9 CSA 13 | I certify that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. | |||||||||||||
| Address | |||||||||||||||
| change schedule of items and gov't est unit price | |||||||||||||||
| Signature: | Date: | 7/14/25 | |||||||||||||
| SOLICITATION NO.: | 12445525B0004 | ||||||||||||||
| PROJECT: | GAOA SUF Forest Road 152 South Brule River Bridge Replacement | OFFEROR NO. 1 | OFFEROR NO. 2 | OFFEROR NO. 3 | OFFEROR NO. 4 | OFFEROR NO. 5 | |||||||||
| Vendor Name: | Day Services LLC | Gustav & Rudy | HUOT CS | Nordic Group | Winberg | ||||||||||
| Vendor City/State: | |||||||||||||||
| Amendments Acknowledged: | Yes | Yes | Yes | No | Yes | ||||||||||
| Acceptance Time | |||||||||||||||
| DUNS # | |||||||||||||||
| Business Size | |||||||||||||||
| Bid Guarantee: | No | Yes | Yes | Yes | Yes | ||||||||||
| Government Estimate | |||||||||||||||
| ITEM | EST. | UNIT | EST. | UNIT | UNIT | UNIT | UNIT | UNIT | |||||||
| NO. | DESCRIPTION | QTY. | UNIT | PRICE | AMOUNT | PRICE | AMOUNT | PRICE | AMOUNT | PRICE | AMOUNT | PRICE | AMOUNT | PRICE | AMOUNT |
| 1 | REMOVE EXISTING STRUCTURE - 20301 | 1 | LS | $0.00 | $55,000.00 | $0.00 | $50,000.00 | $0.00 | $208,140.00 | $0.00 | $11,500.00 | $0.00 | $30,000.00 | $0.00 | $95,200.00 |
| 2 | COMMON EXCAVATION - 20407 | 60 | CY | $50.00 | $3,000.00 | $70.00 | $4,200.00 | $352.00 | $21,120.00 | $115.00 | $6,900.00 | $40.00 | $2,400.00 | $224.00 | $13,440.00 |
| 3 | EXCAVATION FOR STRUCTURES BRIDGES - 20801 | 1 | LS | $0.00 | $40,000.00 | $0.00 | $12,000.00 | $0.00 | $76,315.00 | $0.00 | $17,250.00 | $0.00 | $10,000.00 | $0.00 | $80,640.00 |
| 4 | BORROW – 20901 | 1994 | CY | $10.00 | $19,940.00 | $15.00 | $29,910.00 | $98.45 | $196,309.30 | $23.00 | $45,862.00 | $60.00 | $119,640.00 | $67.20 | $133,996.80 |
| 5 | FINISHING ROADWAY - 30901 | 1 | EA | $0.00 | $5,000.00 | $0.00 | $2,500.00 | $0.00 | $132,048.00 | $0.00 | $11,500.00 | $0.00 | $20,000.00 | $0.00 | $10,528.00 |
| 6 | TACK COAT - 70200 | 50 | GAL | $24.00 | $1,200.00 | $25.00 | $1,250.00 | $23.50 | $1,175.00 | $115.00 | $5,750.00 | $80.00 | $4,000.00 | $14.56 | $728.00 |
| 7 | MOBILIZATION – 15101 | 1 | EA | $0.00 | $175,000.00 | $0.00 | $90,000.00 | $0.00 | $293,226.00 | $0.00 | $317,301.84 | $0.00 | $250,000.00 | $0.00 | $560,000.00 |
| 8 | WATER – 72501 | 5 | MGAL | $1,000.00 | $5,000.00 | $500.00 | $2,500.00 | $528.00 | $2,640.00 | $1,150.00 | $5,750.00 | $30.00 | $150.00 | $1,120.00 | $5,600.00 |
| 9 | SALVAGED TOPSOIL - 71301 | 1846 | SY | $8.00 | $14,768.00 | $3.00 | $5,538.00 | $31.80 | $58,702.80 | $12.08 | $22,299.68 | $20.00 | $36,920.00 | $44.80 | $82,700.80 |
| 10 | SILT FENCE – 71316 | 949 | LF | $5.00 | $4,745.00 | $5.00 | $4,745.00 | $16.45 | $15,611.05 | $17.25 | $16,370.25 | $7.00 | $6,643.00 | $8.96 | $8,503.04 |
| 11 | EROSION MAT ERO-GUARD EG-2X(NN) - 71317 | 1846 | SY | $5.00 | $9,230.00 | $3.50 | $6,461.00 | $76.50 | $141,219.00 | $10.35 | $19,106.10 | $7.00 | $12,922.00 | $8.96 | $16,540.16 |
| 12 | TURBIDITY BARRIERS - 71321 | 109 | SY | $35.00 | $3,815.00 | $15.00 | $1,635.00 | $119.00 | $12,971.00 | $143.75 | $15,668.75 | $35.00 | $3,815.00 | $33.60 | $3,662.40 |
| 13 | FERTILIZER - 71303 | 1.26 | CWT | $250.00 | $315.00 | $700.00 | $882.00 | $58,704.00 | $73,967.04 | $3,680.00 | $4,636.80 | $2,000.00 | $2,520.00 | $560.00 | $705.60 |
| 14 | SEEDING MIXTURE NO. 36-311 – 62501 | 52 | LB | $38.00 | $1,976.00 | $6.00 | $312.00 | $176.00 | $9,152.00 | $172.50 | $8,970.00 | $60.00 | $3,120.00 | $56.00 | $2,912.00 |
| 15 | EROSION CONTROL (TYPE 2.B) AND SEDIMENT CONTROL – 15713 | 1 | LS | $13,000.00 | $13,000.00 | $6,000.00 | $6,000.00 | $0.00 | $49,034.00 | $0.00 | $17,250.00 | $0.00 | $8,000.00 | $0.00 | $28,000.00 |
| 16 | BASE AGGREGATE (MNDOT CLASS 1) -25101 | 14 | CY | $95.00 | $1,330.00 | $100.00 | $1,400.00 | $1,928.00 | $26,992.00 | $86.25 | $1,207.50 | $100.00 | $1,400.00 | $336.00 | $4,704.00 |
| 17 | BASE AGGREGATE (MNDOT CLASS 5) - 30207 | 148 | CY | $95.00 | $14,060.00 | $60.00 | $8,880.00 | $622.00 | $92,056.00 | $86.25 | $12,765.00 | $85.00 | $12,580.00 | $112.00 | $16,576.00 |
| 18 | ASPHALT PAVING SURFACE – 30902 | 124 | TON | $245.00 | $30,380.00 | $180.00 | $22,320.00 | $260.00 | $32,240.00 | $534.75 | $66,309.00 | $275.00 | $34,100.00 | $516.88 | $64,093.12 |
| 19 | TIMBER WEAVERING SURFACE (TIMBER SUPERSTRUCTURE ONLY) - 55701 | 1.9 | MBM | $15,861.00 | $30,135.90 | $4,800.00 | $9,120.00 | $49,535.00 | $94,116.50 | $12,368.25 | $23,499.68 | $25,000.00 | $47,500.00 | $17,165.12 | $32,613.73 |
| 20 | MARKING LINE EPOXY 4-INCH - 71815 | 912 | LF | $15.00 | $13,680.00 | $3.50 | $3,192.00 | $35.00 | $31,920.00 | $11.50 | $10,488.00 | $20.00 | $18,240.00 | $19.60 | $17,875.20 |
| 21 | HEAVY RIPRAP (MNDOT CLASS III) - 70502 | 123 | CY | $150.00 | $18,450.00 | $85.00 | $10,455.00 | $1,090.00 | $134,070.00 | $115.00 | $14,145.00 | $200.00 | $24,600.00 | $280.00 | $34,440.00 |
| 22 | REMOVING SING TYPE II – 71800 | 2 | EA | $100.00 | $200.00 | $300.00 | $600.00 | $176.00 | $352.00 | $143.75 | $287.50 | $1,000.00 | $2,000.00 | $1,120.00 | $2,240.00 |
| 23 | POSTS WOOD 4X6-INCH X 12 FT – 71805 | 4 | EA | $100.00 | $400.00 | $200.00 | $800.00 | $13,008.00 | $52,032.00 | $287.50 | $1,150.00 | $700.00 | $2,800.00 | $1,680.00 | $6,720.00 |
| 24 | OBJECT MARKER SIGNAGE - 63307 | 6 | SF | $400.00 | $2,400.00 | $60.00 | $360.00 | $64.50 | $387.00 | $57.50 | $345.00 | $300.00 | $1,800.00 | $1,176.00 | $7,056.00 |
| 25 | FIELD OFFICE (FOR CONTRACTOR) - 15101 | 1 | EA | $10,000.00 | $10,000.00 | $0.00 | $8,000.00 | $0.00 | $8,600.00 | $0.00 | $11,500.00 | $0.00 | $15,000.00 | $560.00 | $26,880.00 |
| 26 | TRAFFIC CONTROL BARRICADES TYPE III – 63505 | 48 | LF | $80.00 | $3,840.00 | $20.00 | $960.00 | $118.00 | $5,664.00 | $115.00 | $5,520.00 | $75.00 | $3,600.00 | $72.80 | $8,736.00 |
| 27 | TRAFFIC CONTROL SIGNS – 63504 | 120 | SF | $31.00 | $3,720.00 | $15.00 | $1,800.00 | $82.50 | $9,900.00 | $0.00 | $2,875.20 | $50.00 | $6,000.00 | $0.00 | $28,000.00 |
| 28 | TRAFFIC CONTROL – 63501 | 1 | EA | $6,500.00 | $6,500.00 | $0.00 | $8,500.00 | $0.00 | $82,184.00 | $0.00 | $5,750.00 | $0.00 | $10,000.00 | $0.00 | $22,400.00 |
| 29 | CONSTRUCTION STAKING - 15201 | 1 | LS | $12,000.00 | $12,000.00 | $0.00 | $4,000.00 | $0.00 | $41,092.00 | $0.00 | $11,500.00 | $0.00 | $25,000.00 | $425.60 | $136,192.00 |
| 30 | TIMBER PILE 9.9-INCH TIP DIA (includes pile driving) – 55101 | 320 | LF | $170.00 | $54,443.00 | $0.00 | $32,000.00 | $412.00 | $131,840.00 | $427.08 | $136,665.60 | $250.00 | $80,000.00 | $0.00 | $228,480.00 |
| 31 | TREATED LUMBER AND TIMBER - 71603 | 1 | LS | $336,050.00 | $336,050.00 | $0.00 | $7,000.00 | $0.00 | $259,400.00 | $0.00 | $76,417.50 | $0.00 | $100,000.00 | $5,152.00 | $633,696.00 |
| 32 | SPIKE GLULAM LAMINATED TIMBER PANEL BRIDGE SUPERSTRUCTURE - 71604 | 123 | CY | $130.00 | $15,990.00 | $0.00 | $14,760.00 | $0.00 | $361,005.00 | $0.00 | $306,314.28 | $2,000.00 | $246,000.00 | $70.00 | $12,880.00 |
| 33 | GEOTEXTILE FABRIC – 71401 | 184 | SY | $10.00 | $1,840.00 | $0.00 | $736.00 | $35.00 | $11.00 | $9.78 | $1,799.52 | $15.00 | $2,760.00 | $134.40 | $8,736.00 |
| 34 | DRAIN TILE PIPE 6-INCH - 60505 | 65 | LF | $50.00 | $3,250.00 | $0.00 | $975.00 | $99.80 | $6,487.00 | $20.13 | $1,308.45 | $70.00 | $4,550.00 | $100.80 | $49,694.40 |
| 35 | STRUCTURE BACKFILL – 20901 | 493 | CY | $50.00 | $24,650.00 | $0.00 | $24,650.00 | $177.00 | $87,261.00 | $86.25 | $42,521.25 | $85.00 | $41,905.00 | $0.00 | $318,080.00 |
| 36 | TEMPORARY BYPASS - 20801 | 1 | LS | $225,000.00 | $225,000.00 | $0.00 | $12,000.00 | $0.00 | $1,020,690.00 | $0.00 | $230,000.00 | $0.00 | $170,000.00 | $0.00 | $0.00 |
| Total | $1,160,307.90 | $390,441.00 | $3,769,929.69 | $1,488,483.90 | $1,359,965.00 | $2,703,249.25 | |||||||||
| TOTAL | Bid | $1,520,000.00 | $450,000.00 | $3,776,358.69 | $1,488,483.90 | $1,359,965.00 | $2,742,449.25 |