Questions and Answers for NRS Electrical Panels.docx

DOCX document 13 KB Posted

Attached to
NRS Rhinelander, WI Replace 2 Electrical Panels 600 AMP and 100 AMP with surge protection
Solicitation number
12445523Q0107
Issued by

View the file

Other files

File Type Posted
photo4.jpg JPG image
230714 SF 30 Amendment 0003.pdf PDF
photo1.jpg JPG image
photo0.jpg JPG image
photo2.jpg JPG image
photo3.jpg JPG image
230707 SF 30 Amendment 0002.pdf PDF
SF 30 (11_2016).pdf PDF
J2 SOW Electrical Panel replacement.pdf PDF
J1 DBA Wage Determination.pdf PDF
Sol_12445523Q0107.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers for NRS Electrical Panels Are we just providing surge protection for the 600 amp panel since the 100 amp panel is fed from it or both panels?

Only one surge protection is needed.

Question about what does the Buy American Act mean for a contractor?

Unless an exception applies, U.S. government agencies are required to purchase U.S. made products if the BAA applies to the procurement. A U.S. made product is (1) an unmanufactured end product mined or produced in the United States; or (2) an end product manufactured in the United States, if the cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. For DoD procurements, the requirement in (2) above would include the cost of components from the United States or a Qualifying Country.

The term component is defined as an article, material, or supply incorporated directly into an end product. A component is either entirely foreign or entirely domestic. A component is domestic only if it is manufactured in the United States. A foreign made component may become domestic if it undergoes substantial remanufacturing in the United States. The cost of components includes transportation costs, but do not include packaging costs, the cost of combining the components into the end product, or the cost of testing after manufacturing.

This applies to construction materials and products as well.