Hoosier National Forest Springs Valley Dam Improvement
Solicitation number
12445522Q0102
Issued by

View the file

Other files

File Type Posted
220614 Q and A as of June 13.docx DOCX document
220613 LIST OF ATTENDEES.pdf PDF
J4 PROJECT PHOTOS.pdf PDF
J5 PROJECT EXHIBIT.pdf PDF
J2 PROJECT SPECS.pdf PDF
J1 PROJECT DESCRIPTION.pdf PDF
12445522Q0102 Solicitation.pdf PDF
J3 PROJECT MAPS.pdf PDF
J6 DAVIS BACON WD IN20220006 ORANGE COUNTY.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12445522Q0102 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ATLANTA GA 30309-2449

STE 876S

1720 PEACHTREE ST NW

USDA-FS CSA EAST 13

GAOA06/14/20220001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/18/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Contractor must be registered in Sam.gov to submit an offer on this project.

Enter UEI number__________________________________

Please complete this package and return by the response date via email to cassandra.potts@usda.gov

ENTER PRICING ON SCHEDULE OF ITEMS OF THIS SOLICITATION PACKAGE.

The purpose of this Amendment is to incorporate questions and answers into the requirement from the pre bid meeting held June 13, 2022.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

JONATHAN D. GELLINGS

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12445522Q0102/0001

There are no other changes to terms and conditions.

Period of Performance: 07/18/2022 to 12/31/2022

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Questions and Answers for the Hoosier National Forest Springs Valley Dam Improvement Project as of June 13, 2022.

Solicitation 12445522Q0102

1. The width of the access road running along the side of the dam. The access road ranges from 10’ to 12’.

2. A contractor asked about access below the rip rap for placing it. I stated the lake is currently down for other work, but the plan is not leave it down for this work the original thought was to access the rip rap from the top side.

3. The thickness of the proposed rip rap. The maximum thickness would be 24” +/-.

4. The guardrails along the road are an option to removes couple sections for bringing in the rip rap material. The contractor will be allowed to remove a couple sections including the post. It will be his responsibility for replacing the sections removed and restoring the area around it.

5. I mention the trees and brush along the existing area could be removed by a separate contract.

But I also stated it is the contract for the contractor to remove it and they were given options on the removal. Based on the timing the separate contract will not be able to remove the material based on the timeframe of the contract.