This document is an Amendment of Solicitation and a Questions and Answers response for USDA Forest Service solicitation 12445226Q0029 issued by the CSA East 12 office in Atlanta, Georgia. Amendment 0001, effective July 28, 2026, extends the Period of Performance from 180 days to 240 days and incorporates questions and answers received by the due date. The contracting officer is Penny R. Zortman.

The questions and answers address three key clarifications for the Cooter Creek project (solicitation 12445226Q0026): (1) regarding Item 210 Stream Protection, dewatering may be necessary to perform work, protect improvements, or protect water quality; (2) regarding Item 240 Contract Time and Schedule, the correct contract period is 240 days, as updated by Amendment 01; and (3) regarding Item 260 Permitting, no permits are required for this project, clarifying that the contractor has no permitting obligations. All other terms and conditions of the original solicitation remain unchanged and in full force and effect.

View the file

Other files for this federal contract opportunity

Other files attached to GAOA Cooter Creek Rd Bridge Replacement (SC), newest first.
File Type Posted
A6 - WD Hwy SC Charleston County.pdf PDF
A2 - SOW Cooter Creek Bridge.pdf PDF
A3 - SOI Cooter Creek.pdf PDF
A1 - RFQ Terms and Conditions 12445226Q0029.pdf PDF
A4 - Cooter Creek Plans.pdf PDF
RFQ 12445226Q0029 GAOA Cooter Creek.pdf PDF
A5 - FSSS Bridge Replacements.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12445226Q0029 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ATLANTA GA 30309-2449

STE 876S

1720 PEACHTREE ST NW

USDA-FS CSA EAST 12

07/28/20260001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/09/2026

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment 0001 is for questions and answers received by the due date and time and to extend the POP from 180 days to 240.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

PENNY R. ZORTMAN

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Questions 12445226Q0026 Cooter Creek

1. Item – 210 – STREAM PROPECTION – can you clarify what you mean about dewatering of the site will need to be considered? (is this in a flood zone? or floods all the time?)

- For work at this site, dewatering may be needed to perform the work, protect improvements, or protect water quality.

2. Item – 240 – CONTRACT TIME and SCHEDULE – This says 240 days and front solicitation sheet has 180 days; can you clarify which is correct?

- Amendment 01 will be updating the Period of Performance from 180 days to 240.

3. Item – 260 – PERMITTING - who takes care for obtaining all permits?

- No permits are required for this project.