This file is a Questions and Answers (Q&A) matrix documenting bidder inquiries and government responses for USDA Forest Service RFQ 12445127Q0005, issued as a small business set-aside for fiber optic installation at Womble Work Center in Mt. Ida, Arkansas. The Q&A clarifies scope, specifications, site conditions, labor requirements, and contractual terms across 91 documented inquiries submitted between October 23 and October 29, 2026.
The project requires installation of approximately 1,300 linear feet of single-mode (OS2) 8-strand fiber optic cable connecting the Ranger Office and Work Center network closets, with roughly 1,250–1,300 feet total distance (150 feet in office, 850 feet between buildings, 250 feet in work center). The route crosses approximately 200 feet of parking lot requiring washed rock backfill and asphalt patching (hot mix, cold patch, or concrete acceptable). Contractors may use either open-cut trenching or horizontal directional boring; one traffic-rated pull box is required, with additional pull boxes as needed for fiber pulling. Existing utilities (water, sewer, communications within 100–200 feet of buildings) must be located by the contractor; solid rock should not be encountered, but if discovered will be treated as a differing site condition with government-provided solutions. Fiber must be pre-terminated with LC connectors or field-terminated with fusion-spliced pigtails; all connection equipment is government-furnished and ready to receive the installed fiber. Testing must demonstrate fiber performance at network-supported speeds. The period of performance is 60 calendar days from Notice to Proceed (with weather delays considered upon review), and performance and payment bonds are not required. Labor standards include Davis-Bacon prevailing wage (Wage Determination AR20260047); contractors may submit conformance requests for fiber optic technician classifications not listed in the wage determination. Insurance requirements include Workers Compensation with Employer's Liability minimum $100,000, General Liability minimum $500,000 per occurrence, and Automobile Liability minimum $200,000 per person/$500,000 per occurrence. Buy American and Section 889 compliance apply to fiber and equipment. Evaluation is lowest-price technically acceptable (FAR 9.4); the independent government estimate range ($25,000–$100,000) cannot be disclosed. Site visits are available (one scheduled for November 12, 2026 at 10:00 AM); visits are optional but COR coordination is required for site access. Quotes must be submitted via email to Cynthia.granderson@usda.gov on the provided Schedule B pricing template in Microsoft Word, Excel, or Adobe PDF format; it is the offeror's responsibility to confirm receipt from the Contract Specialist.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 12445127Q0005_Amd_0004.pdf | ||
| 12445127Q0005 Amd 00003.pdf | ||
| Wage Determination.pdf | ||
| 12445127Q0005 Amd 00002.pdf | ||
| 12445127Q0005 Amd 00001.pdf | ||
| C04_Solicitation Package_12445127Q0005.pdf | ||
| Wage Determination.pdf | ||
| 12445127Q0005.pdf | ||
| A04_SOW_12445127Q0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMENTS MATRIX FOR USDA-FS ISSUANCES:
RFQ 12445127Q0005 Womble Work Center Fiber Optic Installation
| # |
| Class |
| Component and POC Name, Phone, and E-mail |
| Page |
| Para |
| Comment Type (C/S) |
| Comments, Justification, and Originator Justification for Resolution |
| A/R/P |
Emailed 10/23/2026
Bidder Comment: SAM.gov lists the response date as Monday, November 23, 2026, 9:00 AM CT, while SF-1442 Item 13a and the continuation schedule state October 29, 2026, 0900 CT. Please confirm the governing due date and, if changed, issue an amendment.
Resolution: See Amendment 0001
Emailed 10/23/2026
Bidder Comment: The question deadline is listed as 10/27/2026. Please confirm the time and time zone, and whether it will be extended if the quote due date is November 23.
Emailed 10/23/2026
Bidder Comment: The SF-1442 states award will be a firm-fixed-price BPA Call performed under 'the contractor's respective BPA.' Is this
RFQ open to all small businesses registered in SAM, or limited to existing Forest Service BPA holders? If a BPA is required, will the Government issue one to a non-holder upon award, or award a standalone purchase order?
Emailed 10//23/2026
Bidder Comment: The SOW refers to 'specifications and drawings' and areas 'shown on the plans,' but no drawings were posted. Please provide a site plan showing the conduit route, approximate linear footage, pull box locations, and building entry points.
Resolution: Site plan created.
Emailed 10/23/2026
Bidder Comment: What is the approximate route length between the Ranger Office network closet and the Work Center network closet, including the length of any parking-lot/asphalt crossing?
Resolution: 1300 ft – about 150 feet in the office, 850 feet between buildings and 250 feet in the work center plus 50 feet extra.
Emailed 10/23/2026
Bidder Comment: How many pull boxes are required, and at what maximum spacing? Please specify minimum pull box size and lid rating
(traffic-rated in the parking lot?).
Resolution: One traffic rated pull box. Other pull boxes as needed to pull fiber based on the contractors ability to pull the fiber. It will be about 850 feet outdoors between the buildings.
Emailed 10/23/2026
Bidder Comment: . Is open-cut trenching required, or is horizontal directional boring an acceptable alternative (especially under the parking lot and drives)?
Resolution: Horizontal boring is preferred but trenching is acceptable.
Emailed 10/23/2026
Bidder Comment: Are there known existing underground utilities (power, water, septic, propane, communications) along the route? Will the Government provide utility maps or locate non-Arkansas-One-Call private utilities on Forest Service property?
Resolution: There are water, sewer and communications lines within about 100 feet of the office and 200 feet of the workcenter. In the wooded area there will not be any other utility conflicts.
Emailed 10/23/2026
Bidder Comment: Is rock anticipated? If unforeseen rock is encountered at less than 18 inches, how will that be handled (differing site condition)?
Resolution: There might be too much rock to use a trenching machine but an excavator shouldn’t have any rock issues.
Emailed 10/23/2026
Bidder Comment: Wage Determination AR20260047 (Heavy) contains no electrician or telecommunications technician classification.
Should we submit a conformance request (SF-1444) post-award, or will the Government provide an additional WD (e.g., Building)?
Resolution: See Amendment 0002
Emailed 10/23/2026
Bidder Comment: Please confirm the correct CO email (cynthia.granderson@usda.gov vs. cynthia_granderson@usda.gov) and the maximum email attachment size.
Resolution: cynthia.granderson@usda.gov
Emailed 10/23/2026
Bidder Comment: The notice references FAR Part 12 and the SF-1449, but the posted form is the SF-1442. Which form must be completed and signed? Item 13a calls for 'original and 1 copies' - is a single emailed PDF acceptable?
Emailed 10/23/2026
Bidder Comment: Period of performance is listed as 11/02/2026-01/04/2027 and also 10 days after NTP / 60 calendar days. If award slips, will the completion date be adjusted? Are weather/seeding-season delays excusable?
Resolution: Completion date will be adjusted. Weather days will be considered after review of your current work progress.
Emailed 10/23/2026
Bidder Comment: Please specify fiber type: single-mode (OS2) or multimode (OM3/OM4), loose-tube gel-free, armored or non-armored, and jacket rating for indoor transition (OSP cable typically must transition to riser/plenum within 50 ft of building entry).
Resolution: Specifications updated.
Emailed 10/23/2026
Bidder Comment: Is the fiber to be factory pre-terminated with LC connectors and pulling eye, or may we field-terminate/fusion-splice LC pigtails?
Resolution: Pre-terminated is not required.
Emailed 10/23/2026
Bidder Comment: Does the contractor furnish rack-mount or wall-mount fiber enclosures/patch panels, couplers, and patch cords in each closet, or only the terminated cable?
Resolution: Equipment is already located at each end to plug the fiber into.
Emailed 10/23/2026
Bidder Comment: Is the contractor responsible for media converters, switches, or network equipment, or any cutover of the existing copper circuit and radio system?
Resolution: No, the equipment to connect is already installed.
Emailed 10/23/2026
Bidder Comment: What testing is required (OTDR bidirectional, insertion loss/power meter Tier 1 per TIA-568) and in what report format?
Resolution: Must prove that the fiber works at the speeds the network can support.
Emailed 10/23/2026
Bidder Comment: Is tracer wire, locate balls, and/or warning tape required? Pull string/mule tape in conduit? Any spare conduit?
Resolution: If the fiber chosen does not have a locate conductor, provide one outside the conduit in the trench.
Emailed 10/23/2026
Bidder Comment: Are building wall penetrations, interior conduit/innerduct, and firestopping included? Are buildings occupied/any historic or asbestos concerns at penetration points?
Resolution: There are no historic or asbestos concerns at this site. There are building wall penetrations. There is interior conduit to install in the office crawl space.
Emailed 10/23/2026
Bidder Comment: Required slack/service loops at pull boxes and closets?
Resolution: Slack will be looped at one or both ends in the closets.
Emailed 10/23/2026
Bidder Comment: Please provide the fertilizer table values that appear incomplete in Section 32 92 00 (Nitrogen/Potassium lbs/acre).
Resolution: Fertilizer may not be needed this time of year.
Emailed 10/23/2026
Bidder Comment: Asphalt patching: please specify approved patch material (hot mix vs cold patch) and any saw-cut requirements.
Resolution: Hot mix, cold patch or concrete are approved materials.
Emailed 10/23/2026
Bidder Comment: May excavated spoils/debris be disposed on Forest Service property, or must all be hauled off-site?
Resolution: There are areas it can be disposed on site.
Emailed 10/23/2026
Bidder Comment: Is a staging/laydown area and access to water/power available on site?
Resolution: Yes to all.
Emailed 10/23/2026
Bidder Comment: Please confirm that performance and payment bonds are not required (SF-1442 Item 12a appears marked NO) and that no bid guarantee is required (Item 13b).
Resolution: No
Emailed 10/23/2026
Bidder Comment: What insurance minimums apply (FAR 52.228-5 / 28.307-2 limits)?
Resolution: Workers Compensation and Employer's Liability Employer's liability coverage of at least $100,000 must be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
General Liability. The Contractor must have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.
Automobile Liability. The Contractor must have automobile liability insurance written on a comprehensive form of policy. The policy must provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States must provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
Emailed 10/23/2026
Bidder Comment: Will the full clause list (FAR 52.212-4/5 or 52.236 series) be provided? Please confirm Section K reps & certs can be satisfied by SAM registration.
Resolution: No, the full clause will not be provided. No, Section K reps & certs can not be satisfied by SAM registration.
Emailed 10/23/2026
Bidder Comment: What is the evaluation basis beyond lowest price - are technical submittals, past performance, or licenses (Arkansas Contractors Licensing Board, Arkansas electrical/low-voltage license) required with the quote or at award?
Resolution: Lowest Price Technical Acceptable per FAR 9.4.
Emailed 10/23/2026
Bidder Comment: Is there an Independent Government Estimate range beyond the $25,000-$100,000 magnitude that can be shared?
Resolution: No, the magnitude can’t be shared.
Emailed 10/23/2026
Bidder Comment: Are there Forest Service security/badging, background check, or Buy American/Section 889 requirements for the fiber and equipment?
Resolution: Yes, Buy American/Section 889 requirements for the fiber and equipment
Emailed 10/23/2026
Bidder Comment: Payment: invoicing via IPP? Any partial payments for materials delivered?
Emailed 10/23/2026
Bidder Comment: Is a site visit arranged with the COR available, or only self-guided? Is there a POC on site (Womble RD) to provide building access to the network closets?
Resolution: A site visit is scheduled for November 12th at 1000. A site POC will be identified after project award.
Emailed 10/24/2026
Bidder Comment: Please provide the approximate trench/conduit length from the Ranger Office to the Work Center, the number of pull boxes required, the length of the parking lot crossing, and any site plan or drawing showing the route Resolution: Pull boxes as the installer needs for pulling the fiber.
Emailed 10/26/2026
Bidder Comment: Is there a site drawing showing the proposed fiber route, approximate footage, and pull-box locations?
Resolution: Yes
Emailed 10/26/2026
Bidder Comment: What is the approximate distance from the Ranger Office network closet to the Work Center network closet? The specification does not state a length and no drawing is included, and Section 27 10 00 Part 3 directs the contractor to verify dimensions in the field.
Resolution: 1250 feet.
Emailed 10/26/2026
Bidder Comment: Is rock known or expected along the route between the two buildings? If rock is encountered, will the Government consider it a differing site condition, or is it the contractor's risk?
Resolution: Solid rock should not be encountered. If encountered, it is not at the contractor’s risk. A solution will be found or modification will be made. The routing is flexible.
Emailed 10/26/2026
Bidder Comment: Approximately how many linear feet of the route crosses the Work Center parking lot and requires the washed rock backfill and two inch asphalt patch described in Section 31 05 16?
Resolution: 200 feet
Emailed 10/26/2026
Bidder Comment: Are there existing underground utilities along the proposed route, and will the Government provide locates or as-built information before excavation begins?
Resolution: There are utilities that the contractor must locate.
Emailed 10/26/2026
Bidder Comment: Will the Government accept a single 8-strand outdoor cable terminated directly to LC connectors at both ends, or is a splice enclosure and pigtail arrangement preferred at either closet?
Resolution: Either.
Emailed 10/26/2026
Bidder Comment: Is a site plan available showing the intended 1,300-foot route, building entry points, existing utilities, and pavement crossings? Please confirm whether 1,300 feet is an estimated quantity or a fixed bid quantity.
Resolution: Yes.
Emailed 10/26/2026
Bidder Comment: Is a site plan available showing the intended 1,300-foot route, building entry points, existing utilities, and pavement crossings? Please confirm whether 1,300 feet is an estimated quantity or a fixed bid quantity.
Emailed 10/26/2026
Bidder Comment: Please confirm whether the 8-strand fiber should be single-mode or multimode, the required LC connector type, and any required manufacturer or cable specifications.
Resolution: Single mode.
Emailed 10/26/2026
Bidder Comment: How many pull boxes are required, and what sizes and load ratings apply? Please also confirm the required conduit type and schedule, including any additional requirements beneath pavement.
Resolution: One traffic rated, the others as the contractor needs for pulling the fiber.
Emailed 10/26/2026
Bidder Comment: Does the contractor’s scope include fiber enclosures, patch panels, adapters, patch cords, splicing, and connections at both network closets? Please confirm the required testing, test reports, labeling, and acceptance criteria. Will the Government furnish and configure the active network equipment?
Resolution: All equipment is present on each end to connect to the fiber once installed.
Emailed 10/26/2026
Bidder Comment: Is there a site plan or drawing available showing the proposed fiber route between the Ranger Office and Work Center?
Emailed 10/26/2026
Bidder Comment: Is there a site plan or drawing available showing the proposed fiber route between the Ranger Office and Work Center?
Emailed 10/26/2026
Bidder Comment: What is the approximate linear footage of conduit and fiber optic cable required?
Resolution: 1300 ft
Emailed 10/26/2026
Bidder Comment: Has a specific installation route been established, or will the contractor be responsible for determining the route?
Resolution: The contractor has some flexibility in determining the route.
Emailed 10/26/2026
Bidder Comment: Is directional boring an acceptable installation method, or is open-cut trenching required?
Resolution: Directional boring is acceptable.
Emailed 10/26/2026
Bidder Comment: Are there any anticipated asphalt, concrete, or roadway crossings?
Resolution: About 200 feet of parking lot.
Emailed 10/26/2026
Bidder Comment: How many pull boxes are required, and are there specific size or spacing requirements?
Resolution: One traffic rated box and as needed to pull the fiber.
Emailed 10/26/2026
Bidder Comment: Is the specified 8-strand outdoor fiber required to be single-mode or multimode?
Emailed 10/26/2026
Bidder Comment: Will the contractor be responsible for fiber termination at both network closets, including any necessary enclosures or patch panels?
Resolution: No, the equipment is ready to connect to the fiber.
Emailed 10/26/2026
Bidder Comment: Will fiber testing and certification be required upon completion?
Resolution: The fiber will have to perform at the network supported speed.
Emailed 10/26/2026
Bidder Comment: We noticed the solicitation is classified under NAICS 238210, Electrical Contractors and Other Wiring Installation Contractors. NEA Construction holds an Arkansas contractor's license covering telecommunications and underground utility installation. Given the scope of work, is a separate electrical contractor's license required, or would our existing telecommunications classification satisfy the project's licensing requirements?
Resolution: No additional license is needed unless it is required per the state, Emailed 10/26/2026
Bidder Comment: Is a site visit available or scheduled for prospective contractors?
Emailed 10/26/2026
Bidder Comment: What is the anticipated project start date and required completion timeframe?
Resolution: Start time is immediately after notice to proceed and 60 days to complete the project.
Emailed 10/26/2026
Bidder Comment: Should contractors submit a single lump-sum quote, or is there a preferred pricing breakdown?
Resolution: Quote should be submitted on the Schedule B provided
Emailed 10/26/2026
Bidder Comment: Are there any bid, performance, or payment bonding requirements for this project?
Emailed 10/26/2026
Bidder Comment: Do you have any drawings for this project?
Emailed 10/26/2026
Bidder Comment: Conduit route: Is there a site plan or approximate length for the conduit run between the Ranger Office and the Work Center, including the length of the parking lot crossing? This would help offerors price consistently.
Emailed 10/26/2026
Bidder Comment: Please provide an exterior photo of the wall we would need to penetrate including a 10 ft section of the ground in front of the wall.
Resolution: It is grass/dirt and a concrete block wall.
Emailed 10/26/2026
Bidder Comment: Please include a photo of the network closet on each end where you would like the fiber to be terminated. If you have an existing network rack/cabinet within that closet please include a photo of it also. I am trying to confirm if you have enough space available to install a rack mounted fiber enclosure or if we need to look at a wall mount enclosure and also the distance to the switch uplink.”
Resolution: The racks and equipment are already present and ready to connect.
Emailed 10/26/2026
Bidder Comment: Drawings and route: the solicitation refers to drawings, but none are posted. Can you send the drawings or a site plan showing the required conduit route and pull box locations? Specifically, should the conduit follow Hwy 270 and Forbes Rd (about 1,600 ft) or run directly across Forest Service property between the buildings (about
900 ft), and is directional boring acceptable in place of open trenching?
Emailed 10/26/2026
Bidder Comment: The solicitation mentions a self-guided site visit. Could you please confirm whether the site visit is mandatory or optional?
Resolution: The Site Visit is not mandatory
Emailed 10/26/2026
Bidder Comment: Additionally, please advise whether prior approval or scheduling is required, and whom we should contact to arrange site access, including the network closets.
Resolution: The COR will coordinate that with the winning bidder. A site visit is scheduled.
Emailed 10/26/2026
Bidder Comment: The RFQ description states that the fiber needs to connect the Womble Work Center to the Ranger Office and gives one address (24 Forbes Rd). Can you clarify which building is located at 24 Forbes Rd and give the address of the other building? I attached a picture from google maps that shows a Caddo/Womble Ranger district which is roughly 1300’ away. Can you confirm if that is the other building and provide an address please?
Resolution: That sounds correct.
Emailed 10/26/2026
Bidder Comment: Please provide an exterior photo of the wall we would need to penetrate including a 10 ft section of the ground in front of the wall.
Resolution: The area in front is grass/dirt and a concrete block wall.
Emailed 10/26/2026
Bidder Comment: Please include a photo of the network closet on each end where you would like the fiber to be terminated. If you have an existing network rack/cabinet within that closet please include a photo of it also. I am trying to confirm if you have enough space available to install a rack mounted fiber enclosure or if we need to look at a wall mount enclosure and also the distance to the switch uplink.”
Resolution: All equipment is ready to connect to the fiber.
Emailed 10/26/2026
Bidder Comment: Can you provide a site map identifying the Ranger Office and Work Center buildings?
Emailed 10/26/2026
Bidder Comment: Is there an established underground conduit route, and if so, what is the approximate linear footage?
Resolution: Yes, about 900 feet underground.
Emailed 10/26/2026
Bidder Comment: Is there a local Forest Service representative who can assist with identifying the buildings during the self-guided site inspection?
Resolution: A site visit is scheduled.
Emailed 10/29/2026
Bidder Comment: Fiber type: Section 27 10 00 specifies 8-strand outdoor fiber with LC connectors but does not state single mode or multimode. Please confirm the required fiber type (for example, OS2 single mode or OM4 multimode). The approximately 1,300 ft run exceeds 10 Gb/s distance limits for OM3
Emailed 10/29/2026
Bidder Comment: Termination method: Is a factory pre-terminated assembly with pulling eye required, or are field fusion-spliced LC pigtails in fiber enclosures acceptable as an equal?
Resolution: Either is acceptable.
Emailed 10/29/2026
Bidder Comment: Termination hardware and electronics: Are fiber enclosures/patch panels in each network closet in the contractor's scope? Are media converters, switches, or SFP optics Government-furnished or excluded?
Resolution: No, the equipment is ready to connect the fiber.
Emailed 10/29/2026
Bidder Comment: Building entry: Please confirm the entry points at each building and the interior pathway from the exterior wall to each network closet. Will indoor/outdoor-rated cable be acceptable for the interior portion?
Resolution: The office routing will be in the crawl space, the work center routing will follow the existing copper cable through brackets suspended from the ceiling.
Emailed 10/29/2026
Bidder Comment: Route and drawings: Are a site plan or route drawing, pull box quantities, and the length of the parking lot crossing available?
Emailed 10/29/2026
Bidder Comment: Period of performance: The solicitation lists 12/01/2026 to 02/01/2027, Amendment 0001 lists 11/02/2026 to 01/04/2027, and the clauses state 60 days after Notice to Proceed. Please confirm which governs.
Emailed 10/29/2026
Bidder Comment: Labor standards: Both FAR 52.222-6 (Construction Wage Rate Requirements, WD AR20260047) and FAR 52.222-41 (Service Contract Labor Standards) are included. Please confirm that only Davis-Bacon applies. Please also confirm that a conformance request will be accepted for a fiber optic technician classification, which is not listed in AR20260047.
Emailed 10/29/2026
Bidder Comment: Warranty: FAR 52.212-4 is amended to apply FAR 52.246-21, Warranty of Construction, but 52.246-21 is unchecked in the clause list. Please confirm the applicable warranty.
Emailed 10/29/2026
Bidder Comment: Subsurface conditions: If rock is encountered that cannot be trenched by conventional equipment to the 18-inch minimum depth, will this be treated as a changed condition under FAR 52.243-5?
Thank you for your assistance.
Resolution: Solid rock should not be encountered but if it is a solution will be found up to and including a contract modification.
Emailed 10/29/2026
Bidder Comment: Scope: Please provide the approximate trench/conduit length from the Ranger Office to the Work Center, the number of pull boxes required, the length of the parking lot crossing, and any site plan or drawing showing the route.
Resolution: Previously answered.
Emailed 10/29/2026
Bidder Comment: Fiber type: Section 27 10 00 specifies 8-strand outdoor fiber with LC connectors but does not state single mode or multimode. Please confirm the required fiber type (for example, OS2 single mode or OM4 multimode). The approximately 1,300 ft run exceeds 10 Gb/s distance limits for OM3.
Emailed 10/29/2026
Bidder Comment: Termination method: Is a factory pre-terminated assembly with pulling eye required, or are field fusion-spliced LC pigtails in fiber enclosures acceptable as an equal?
Emailed 10/29/2026
Bidder Comment: Termination hardware and electronics: Are fiber enclosures/patch panels in each network closet in the contractor's scope? Are media converters, switches, or SFP optics Government-furnished or excluded?
Emailed 10/29/2026
Bidder Comment: Building entry: Please confirm the entry points at each building and the interior pathway from the exterior wall to each network closet. Will indoor/outdoor-rated cable be acceptable for the interior portion?
Emailed 10/29/2026
Bidder Comment: Route and drawings: Are a site plan or route drawing, pull box quantities, and the length of the parking lot crossing available?
Emailed 10/29/2026
Bidder Comment: Period of performance: The solicitation lists 12/01/2026 to 02/01/2027, Amendment 0001 lists 11/02/2026 to 01/04/2027, and the clauses state 60 days after Notice to Proceed. Please confirm which governs.
Resolution: The contractor will have 60 days to complete the contract regardless of when its awarded.
Emailed 10/29/2026
Bidder Comment: Labor standards: Both FAR 52.222-6 (Construction Wage Rate Requirements, WD AR20260047) and FAR 52.222-41 (Service Contract Labor Standards) are included. Please confirm that only Davis-Bacon applies. Please also confirm that a conformance request will be accepted for a fiber optic technician classification, which is not listed in AR20260047.
Emailed 10/29/2026
Bidder Comment: Warranty: FAR 52.212-4 is amended to apply FAR 52.246-21, Warranty of Construction, but 52.246-21 is unchecked in the clause list. Please confirm the applicable warranty.
Resolution: Warranty period is 1 year from date of final inspection
Bidder Comment: Subsurface conditions: If rock is encountered that cannot be trenched by conventional equipment to the 18-inch minimum depth, will this be treated as a changed condition under FAR 52.243-5?
Resolution: This matter will be addressed provided the Contractor notifies the Contracting Officer immediately upon discovery of the condition.
PAGE
SD FORM 818, JAN 09
PREVIOUS EDITION IS OBSOLETE
File details come from the government source that posted it. Updated .