This is Amendment 0001 to solicitation 12445127B0002, issued by USDA Forest Service CSA East 11 on November 2, 2026, with an effective date of November 9, 2026. The solicitation pertains to HVAC installation at the Halfmoon Ranch House in Arizona. The amendment period of performance runs from December 15, 2026 to February 15, 2027. The amendment incorporates responses to 14 bidder comments received through November 6, 2026, documented in an attached Comments Matrix.
Key technical requirements include installation of three 1-ton R410A single-stage outdoor condensers and three 1-ton indoor wall-mounted units with a minimum 20 SEER rating; equal or better substitutes meeting 20 SEER are acceptable subject to Forest Service approval, including R-32 or R-454B systems, but retrofitting existing R-410A systems to use alternative coolants is not acceptable. Work shall be completed within 60 calendar days after Notice to Proceed. Payment and Performance bonds are required only if the bid exceeds $35,000. The site visit is scheduled for 10:00 a.m. to 11:00 a.m. local time on November 10, 2026, at Halfmoon Ranch House, conducted by Lauren Atkinson (lauren.atkinson@usda.gov). Attendance is not required; photos will be taken during the walkthrough. This is a new requirement with no incumbent contractor. All solicitation documents are available on SAM.gov under solicitation number 12445127B0002.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C04 12445127B0002 Complete Package.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x) x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ATLANTA GA 30309-2449
STE 876S
1720 PEACHTREE ST NW
USDA-FS CSA EAST 11
11/09/2026
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
12445127B0002
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
11/02/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
CHARLES C. COTTON
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment incorporates the following:
Amendment provides responses to comments received through 11-06-2026.
Period of Performance: 12/15/2026 to 02/15/2027
Attachments:
12445127B0002 Comments Matrix 11-06-2027
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
x 1 aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight aldoyle Highlight
COMMENTS MATRIX FOR USDA-FS ISSUANCES: 12445127B0002 AZ Halfmoon Ranch House HVAC Installation
(Please read instructions on back before completing form.)
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/ R/ P
SD FORM 818, JAN 09 PREVIOUS EDITION IS OBSOLETE
11-02-2027 email question
Bidder Comment: The organized site visit is listed for Tuesday, November 10, 2026, at Halfmoon Ranch House, but no start time is provided. Please confirm the start time and any meeting location at the gate.
Resolution: Site visit will be 10 A.M.-11A.M., local time. Lauren Atkinson lauren.atkinson@usda.gov will be conducting the site visit.
email question
Bidder Comment: Equipment size and efficiency: Specification 15740, Section 1.1 calls for three (3) 1-ton R410A single-stage outdoor condensers and three (3) 1-ton indoor wall-mounted units with a minimum 20 SEER rating. Section 2.1 lists the Daikin RXC24AXVJU outdoor unit (18 SEER) and FTXC24AXVJU indoor unit, which are 24,000 BTU (2-ton) models.
Please confirm which unit size, minimum SEER rating, and refrigerant type bidders should price.
Resolution: We will look into this and provide a full response after the site visit on Tuesday.
Bidder Comment: Completion time: The SF-1442 (Item 11) states work shall begin within 10 calendar days and be completed within 60 calendar days after Notice to Proceed.
Specification 01010, Section 1.4 states all work shall be completed within 60 days of award.
Please confirm which completion period governs.
Resolution: Work shall be completed within 60 calendar days after Notice to Proceed.
Bidder Comment: We won’t be able to attend the scheduled site visit. Is attendance required to submit a bid? If not, would an alternate visit or photos and a video walkthrough be available to help us evaluate the installation?
Resolution: Attendance is not required. Photos will be taken during the walkthrough.
11-03-2027 Bidder Comment: We would like to know if this is a brand-new contract OR if there is (was) an incumbent performing these services.
Resolution: This is a new requirement.
6 11-03-2027
Bidder Comment: The specifications refer to the building as both the Shaw House and the Half Moon Ranch House. Please confirm these are the same building and indicate the intended locations of the three indoor units, if known.
Resolution: The name “Shaw House” is a typo and should be replaced with Half Moon Ranch House.
7 11-03-2027
Bidder Comment: Can the Government confirm the size and available capacity of the existing electrical service at the house to support three new dedicated circuits?
Resolution: A Forest Service technician will be present to show the components of the electrical system. We will look into this and provide a full response after the site visit on mailto:lauren.atkinson@usda.gov
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
Tuesday.
8 11-03-2027 Bidder Comment: Section 15740 §1.1 specifies the Daikin RXC24AXVJU. Will an equal or better substitute meeting 20 SEER be accepted under §1.6?
Resolution: Equal or better substitutes are acceptable, subject to Forest Service approval.
9 11-04-2027
Bidder Comment: Are floor plans, equipment locations, or mechanical equipment schedules available? If not, are bidders expected to gather the necessary dimensions, installation locations, routing, and existing electrical information during the November 10 site visit?
Resolution: Some photos of the site are available at this site:
https://www.recreation.gov/camping/campgrounds/233177
10 11-04-2027
Bidder Comment: Will R-32 or R-454B equipment be accepted as equal to the R-410A stated?
Resolution: Yes, systems designed to use these coolants will be considered equal or better substitutes and acceptable, retrofitting a R-410A system to use R-32 or R454B is not acceptable.
11 11-04-2027 Bidder Comment: Please confirm that payment and performance bonds apply only if the bid exceeds $35,000.
Resolution: Payment and Performance bonds are only required if the bid exceeds $35,000.00
12 11-04-2027 Bidder Comment: Do 52.219-14 and 52.222-54 apply? Their boxes are unchecked.
Resolution: No, this acquisition is below the simplified acquisition threshold (SAT) and will not be a multiple-year contract or is not a contract with options to renew.
13 11-04-2027
Bidder Comment: Are there any registration requirements or items we should bring to the site visit?
Resolution: A sign-in sheet will be used during the sight visit. No prior registration will be required.
14 11-03-2027
Bidder Comment: We would appreciate the opportunity to review the complete project plans, specifications, and bid sheet.
Resolution: All documents are attached to the SAM.gov posting. Please search “12445127B0002” to access the most up to date version of the posting.
https://www.recreation.gov/camping/campgrounds/233177
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
INSTRUCTIONS FOR COMPLETING SD FORM 818
COORDINATING OSD COMPONENT: Use this form to provide consolidated critical and substantive comments to the OSD Component that originated the issuance. Complete the classification header and footer, columns 1 through 5, and the first two entries in column 6. REVIEW THE COMMENTS, RESOLVE ANY CONFLICTING VIEWS, AND CONFIRM THAT THE COMPLETED MATRIX ACCURATELY REPRESENTS YOUR COMPONENT’S POSITION. Upload the form to the DoD Directives Program Portal IN MICROSOFT WORD FORMAT, with a scanned copy of the sign SD Form 106, “DoD Directives Program Coordination Record,” or coordination memorandum.
ORIGINATING OSD COMPONENT: Use this form to consolidate comments from all coordinators and to record adjudication of the comments. (To add comments from an SD 818 submitted by a coordinator, use the “Copy” and “Paste” tools on the Microsoft Word Standard Toolbar.) When consolidating comments, place them in the order of the pages/paragraphs they apply to (e.g., all comments from all coordinators that apply to page 1, paragraph 1.a., should be grouped together as the initial entries; all comments that apply to page 1, paragraph 1.b., should be grouped together next, and so on). Complete column 7 and the third entry in column 6. Adjust the classification header and footer and columns 1 and 2 as appropriate.
CLASSIFICATION – Enter the highest classification of the comments. If all are unclassified, mark the header and footer accordingly and ignore the column.
COLUMN 1 – Enter the number of the comment. Enter comments in the order of the pages/paragraphs they apply to.
COLUMN 2 – Enter the classification of the comment. If all comments are unclassified, mark the header and footer accordingly and ignore the column.
COLUMN 3 – Enter the appropriate information.
COLUMN 4 – Enter the appropriate information.
COLUMN 5 – Enter the appropriate information.
COLUMN 6 – Enter the comment type. Place only one comment per row. Do NOT include administrative comments concerning non-substantive aspects of an issuance, such as dates of references, organizational symbols, and/or grammatical errors.
(C) CRITICAL: When a Component has one or more critical comments, that Component’s coordination shall reflect a nonconcur. THE JUSTIFICATION FOR CRITICAL COMMENTS
MUST IDENTIFY:
– Violations of the law or contradictions of Executive Branch policy or of policy established in DoD issuances. The GC, DoD, or his or her representative shall identify legal objections as critical comments.
– Unnecessary risks to safety, life, limb, or DoD materiel; waste or abuse of DoD appropriations; or imposition of an unreasonable burden on a Component’s resources.
(S) SUBSTANTIVE: Substantive comments are made when a section in the issuance appears to be or is potentially unnecessary, incorrect, misleading, confusing, or inconsistent with other sections, or when a Component disagrees with the proposed responsibilities, requirements, and/or procedures. A substantive comment is usually not sufficient justification for a Component to nonconcur on an issuance. Several substantive comments when taken together may be grounds for a nonconcurrence.
COLUMN 7 – COORDINATING COMPONENT: Enter the comment in the area provided. Enter your justification for the comment and your requested or recommended changes in the area provided.
YOU MUST PROVIDE CONVINCING SUPPORT FOR CRITICAL COMMENTS IN THE JUSTIFICATION.
– ORIGINATING COMPONENT: Enter your justification for disposition of the comment in the area provided. Include any related communications with the coordinating Component. You must provide convincing support for rejecting critical comments.
COLUMN 8 – Enter whether you accepted (A), rejected (R), or partially accepted (P) the comment. Your justification for disposition of the comment in column 6 must be consistent with this entry.
| SF 30.pdf |
| 12445127B0002 Comments Matrix 11-06-2027.pdf |