This document is a pre-bid meeting memorandum from the U.S. Forest Service, Ouachita National Forest, documenting a site visit and discussion held on February 18, 2026, at 0800 hours at the Womble District Ranger Office. The meeting was conducted by Will McFadden, PE, Facilities Program Manager, and attended by six bidders representing construction and plumbing companies: Five Hats LLC, Surfco, AAA Construction, Byway Plumbing, Mr Handyman, and 13:12 Restoration. The site visit covered three project locations: the District Office building, the work center (featuring water valves to be replaced), and the Seed Orchard roof.
The memorandum identifies seven items requiring addendum modifications to the solicitation: removal of joist hangers from a rebuilt walkway at the office; addition of drip edge to seed orchard roof specifications; inclusion of Cedar Lake plans (which were not provided in the original solicitation); modification of door trim specifications from 14 linear feet to 17 linear feet with terminology change from "beam" to "head trim"; provision of a site/utility plan showing existing utilities as designed rather than as-built conditions; correction of one cubic yard of concrete to one cubic yard of flowable fill; and clarification regarding the Cedar Lake project scope, which was described verbally during the meeting due to missing plans in the solicitation documents.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| LI0001 MOUNT IDA SEED ORCHARD ROOF SPECS Amendment 0004.pdf | ||
| LI0004 Womble Work Center Valve Replacement Plans Amendment 0004.pdf | ||
| LI0003 Cedar Lake 2025 Sanitary Sewer System Schedule B Bid Schedule Amendment 0004.pdf | ||
| LI0002 WOMBLE RANGER OFFICE REPAIRS Schedule B BID SHEET Amendment 0004.pdf | ||
| 12445126B0005 Amendment 0004.pdf | ||
| 12445126B0005 Amendment 0003.pdf | ||
| Attachment 004 Cedar Lake Shady Lane Septic Split Plans.pdf | ||
| 12445126B0005 Amendment 0002.pdf | ||
| 12445126B0005.pdf | ||
| 12445126B0005 Amendment 0001.pdf | ||
| 12445126B0005.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Logo Department Name Agency Organization Organization Address Information
United States Department of Agriculture
Forest Service
Ouachita National Forest P. O. Box 1270 Hot Springs, AR 71902 501-321-5202
FAX: 501-321-5353
Caring for the Land and Serving People
February 18, 2026
Re: Womble and Cedar Lake pre-bid meeting
The meeting was convened at 0800 hours on Wednesday, February 18, 2026 at the Womble District Ranger Office. We walked around the District Office, walked to the work center to look at the water valves and then drove to the Seed Orchard to look at the office roof. The list of attendees are:
Brady Knight – Five Hats LLC Chris Foster – Surfco Brad Lumon – AAA Construction James Carter – Byway Plumbing Eric Garcia – Mr Handyman Scott Tucker – 13:12 Restoration
I made a short run-through of the list of items to be repaired at the Office building. We then walked around the building looking at each item on the list. We walked to the work center to look at the valves to be replaced and where to shut off the water at the meter. We then drove to the seed orchard to look at the roof.
While at the seed orchard, we discussed the Cedar Lake portion of the project. I described the project since the plans were not included in the solicitation. The meeting concluded at 1000 hours.
Items that will require an addendum:
The district rebuilt a walkway at the office and the joist hangers from that walkway will need to be removed.
The seed orchard roof specifications do not include drip edge. This will need to be added.
The Cedar Lake plans need to be added.
The door trim at the office will need to be changed from 14 lf to 17 lf and “beam” changed to “head trim.”
Site/utility plan showing the existing utilities as they were designed, not as-builts.
1 cubic yard of concrete should be 1 cubic yard of flowable fill.
Will McFadden, PE Facilities Program Manager
Forest Service Ouachita National Forest, SO p: 501-321-5369 f: 501-321-5353 william.mcfadden@usda.gov
100 Reserve St Hot Springs, AR 71902 www.fs.usda.gov
Caring for the land and serving people
File details come from the government source that posted it. Updated .