LI0002 WOMBLE RANGER OFFICE REPAIRS Schedule B BID SHEET Amendment 0004.pdf
PDF 513 KB Posted
- Solicitation number
- 12445126B0005
About this file
This is a Solicitation for the Womble Ranger Office Repairs project located at 1523 Hwy 270E, Mt Ida, AR 71957. Solicitation No: 12445126B0005 requires one award to be made, with contractors required to submit pricing for all line items. The project encompasses comprehensive structural and exterior repairs to the ranger office facility.
The scope of work includes: removal and replacement of 51 joist hangers on the West wood deck and East pedestrian bridge; removal and replacement of 5 balusters on the East pedestrian bridge; removal and replacement of approximately 57 square feet of shiplap siding and 12 square feet of fascia board; removal and replacement of approximately 17 linear feet of exterior door jamb and beam trim; installation of 170 linear feet of metal flashing to cover rafters and beams; replacement of the pergola beam with a treated LVL beam; clamping and screwing together 13 double wood rafter members on the pergola; painting of approximately 788 square feet of siding, fascia, beam, and trim; removal and replacement of 13 pergola rafters as required by deterioration evaluation; and reinstallation of the door awning. All work requires contractors to provide materials, labor, and equipment. The contractor shall perform work between 8:00 AM and 4:30 PM Monday through Friday, excluding Federal Holidays, unless other arrangements are made with the Contracting Officer Representative (COR). Specific locations and designations for work items will be provided by the COR during execution.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No: 12445126B0005 Project Name: WOMBLE RANGER OFFICE REPAIRS
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
WOMBLE RANGER OFFICE REPAIRS
LI002 PACKAGE Schedule B BID SHEET
B.1 SCHEDULE OF ITEMS
Item Supplies/Services Qty Unit of Issue
Unit Price Total Price
0001 Provide materials, all labor, and all equipment to replace the pergola beam at the Womble Ranger Office according to the specifications.
1 EA $
0001AA Provide materials, all labor, and all equipment to remove existing quantity 5 balusters and replace them at the Womble Ranger Office according to the specifications.
5 EA $ $
0001AB Provide materials, all labor, and all equipment to remove and replace quantity 51 joist hangers at the Womble Ranger Office according to the specifications.
51 EA $ $
0002 Provide materials, all labor, and all equipment to remove and replace approximately 57 square feet of siding at the Womble Ranger Office according to the specifications.
57 SF $
0002AA Provide materials, all labor, and all equipment to remove and replace approximately 12 square feet of fascia at the Womble Ranger Office according to the specifications.
12 SF $ $
000201 Provide materials, all labor, and all equipment to remove and replace approximately 17 linear feet of exterior door jamb and beam trim at the Womble Ranger Office according to the specifications.
17 LF $
0003 Provide materials, all labor, and all equipment to install 170 linear feet of flashing to cover rafters and beam at the Womble Ranger Office according to the specifications.
170 LF $
Solicitation No: 12445126B0005 Project Name: WOMBLE RANGER OFFICE REPAIRS 1001 Provide materials, all labor, and all equipment to paint siding, fascia, beam, and trim at the Womble Ranger Office according to the specifications.
788 SF $ $
1002 Provide materials, all labor, and all equipment to remove and replace pergola rafters as required by evaluation of deterioration at the Womble Ranger Office according to the specifications.
13 EA $ $
2001 Provide materials, all labor, and all equipment to re-install the door awning at the Womble Ranger Office according to the specifications.
1 EA $ $
B.2 SCHEDULE NOTES
a) One award will be made from this solicitation, contractors must submit pricing for all items.
Total:_________________________________________________________________
DIVISION 01 00 00 GENERAL REQUIREMENTS
01 10 00 – SUMMARY OF WORK
The project is located at 1523 Hwy 270E, Mt Ida, AR 71957 at the Womble Ranger Office. The contractor shall provide all labor, tools, equipment, and materials to perform the work listed below per the specification.
• Remove quantity 51 joist hangers or the remnants of such on the West wood deck and East pedestrian bridge as per the COR designation. Provide and install quantity 51 joist hangers to replace the quantity 51 that were removed.
• Reinstall quantity one inside corner bracket on the East pedestrian bridge.
• Remove quantity 5 balusters from the East pedestrian bridge. Provide and install quantity 5 replacement balusters matching the profile of the balusters that were removed from the East pedestrian bridge. Paint the newly installed balusters per the specifications defined below.
• Reinstall quantity one awning over the front door under of the structure under the pergola. The awning will be supplied by the US Forest Service and the hardware to install such awning will be supplied by the contractor.
• Remove approximately 57sf of existing shiplap siding. Provide and install approximately 57sf of shiplap siding matching the profile of the siding that was removed. Designation of locations of such siding shall be provided by the COR. Paint the newly installed siding per the specifications below.
• Remove approximately 12sf of fascia board. Provide and install approximatel12sf of fascia board matching the profile of the fascia board that was removed. Designation of location of such fascia board shall be provided by the COR. Paint the newly installed siding per the specifications below.
• Remove approximately 14lf 17LF of existing jamb trim for both jambs and above the door for the West entrance doorway on exterior of building structure. Provide and install approximately 14lf 17LF of jamb trim and above the door trim matching the profile of the siding that was removed.
Designation of locations of such jamb trim shall be provided by the COR. Paint the newly installed jamb door trim per the specifications below.
• Paint approximately 527sf of shiplap siding and fascia. Designation of locations of such siding and fascia shall be provided by the COR. Paint the siding and fascia per the specifications below.
• Remove existing beam and filler pieces. Rafters installed on the existing beam must be structurally supported to remove the existing beam or they shall be removed and re-installed after the new beam installation. Supply and install a replacement treated LVL beam supporting the rafters on the pergola attached to the front of the building structure. Such beam to be a treated beam matching existing structure features including filler pieces next to rafters. Such beam shall be designed to carry the load that the current beam supports with current design features for rafter support and design as a simply supported beam. Paint filler pieces and the replacement beam per the specifications below.
• Clamp double wood members making up each pergola rafter together and screw them to one another to remove separation and prevent future separation. Total rafter quantity is 13 with each containing a double wood member.
• Paint quantity 13 rafters on the pergola on the front of the structure per the specifications below.
• Remove metal flashing covers from the quantity 13 rafters on the pergola on the front of the building structure. Remove the metal flashing covers over the filler pieces above the beam that are located on top of the beam and between the rafters on the pergola on the front of the building. Install new metal flashing over the rafters with one continuous metal flashing piece. Replace the flashing over the filler pieces with one continuous metal piece per filler piece. Metal flashing installation shall be completed after the beam is replaced, new filler pieces installed, and beam/rafters/filler pieces repainted. Caulk joints in areas at the end of metal flashing over the filler pieces.
01 31 13 – PROJECT COORDINATION
The contractor shall perform work in a manner that will protect the safety of public and employees. The contractor shall perform the work between the hours of 8:00 AM and 4:30 PM Monday through Friday excluding Federal Holidays unless arrangements have been made with the COR.
WilliamMcFadden Cross-Out
WilliamMcFadden Cross-Out
WilliamMcFadden Cross-Out
WilliamMcFadden Cross-Out
| fill_9: |
| fill_10: |
| fill_14: |
| fill_15: |
| fill_19: |
| fill_20: |
| fill_24: |
| fill_25: |
| fill_29: |
| fill_30: |
| fill_34: |
| fill_35: |
| fill_39: |
| fill_40: |
| fill_4: |
| fill_5: |
| fill_9_2: |
| fill_10_2: |
| fill_14_2: |
| fill_15_2: |
File details come from the government source that posted it. Updated .