DOCUMENT TYPE: Questions and Answers (Amendment 0001) for a USDA Forest Service janitorial services solicitation.
This amendment provides clarification on Solicitation 12444527Q0007 for facility cleaning services at Eleven Point Ranger Station, Mark Twain National Forest. The facility comprises approximately 10,000 square feet across a main floor and basement level, with cleaning scope encompassing restrooms, breakroom/conference room, kitchen, computer room, and other areas detailed in the Performance Work Statement and attached office map. Required services include sweeping, dust mopping, damp mopping, wet mopping, vacuuming, and scrubbing as necessary to meet performance standards, plus cleaning of interior glass and mirrors and washing/disinfecting trash containers at least twice annually. Periodic tasks such as floor stripping, waxing, carpet extraction, and exterior window cleaning are not required. The facility is the direct predecessor to Purchase Order 12444522P0040. Subcontracting is permitted provided it complies with applicable Federal Acquisition Regulation and Agriculture Acquisition Regulation requirements, with the prime contractor remaining fully responsible for performance including subcontractor acts and omissions. All contractor and subcontractor personnel require compliance with Government identity-verification, access-control, key-control, and facility-security requirements before facility access. The question deadline is November 4, 2026, at 4:00 p.m. Eastern Time, and the quotation deadline is extended to November 13, 2026, at 10:00 a.m. Eastern Time.
Quotations must include pricing for the base year and all four option years plus required technical-capability and past-performance information, and may be submitted in the quoter's custom format provided all solicitation requirements are met and not omitted or altered. Insurance evidence and a complete Quality Control Plan are not required with quotations but must be provided post-award. The applicable wage rate for the Janitor classification is $15.90 per hour plus $5.42 per hour Health and Welfare fringe benefit under Department of Labor Wage Determination No. 2015-5101, Revision 31, with separate compliance required for Executive Order 13706 paid sick leave. Payment requests must be submitted electronically monthly in arrears through the Department of Treasury's Invoice Processing Platform (IPP.gov); paper and email invoices will not be accepted. Individual site visits may be coordinated by contacting Francis Moll at francis.moll@usda.gov, though site visits are not required.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USDA Forest Service CSA East 6 1720 Peachtree St NW, Ste 876S Atlanta, GA 30309
Contracting Division
Solicitation Number: 12444527Q0007 Facility: Eleven Point Ranger Station, Mark Twain National Forest Amendment: 0001
The questions and answers below provide clarification of the solicitation. They do not change the solicitation unless expressly incorporated by formal amendment. If any answer conflicts with the solicitation, the formal solicitation amendment controls. Quoters remain responsible for reviewing the complete solicitation, all attachments, and all amendments. Quoters must acknowledge the amendment and submit quotations by the deadline stated in the amendment.
Facility Specifications & Cleaning Scope
Question:
Please confirm the total building area and split between carpeted and hard-surface flooring.
Answer:
The facility consists of a main floor and a basement level, with a combined area of approximately 10,000 square feet. The solicitation does not provide a separate square-footage breakdown for carpeted and hard-surface flooring. Quoters are responsible for determining the labor, equipment, and materials necessary to perform the PWS requirements.
Question: How many restrooms, breakrooms, and specialized areas are within the cleaning scope?
Answer:
The solicitation does not provide a numerical count of restrooms or separately identify every room by cleaning category. The cleaning scope includes the restrooms, breakroom/conference room, kitchen area, computer room, and other areas identified in the PWS and Attachment C, Office Map. Restrooms and applicable cleaning requirements are addressed in PWS §§ 1.14 and 1.1A.20.
Quoters should review the PWS and Attachment C when preparing their quotations.
Question:
Are periodic floor-care tasks, such as stripping/waxing VCT or carpet deep-shampoo extraction, or exterior window cleaning required?
Answer:
The PWS does not specifically require floor stripping, waxing, carpet extraction, or exterior window cleaning. The required floor services include sweeping, dust mopping, damp mopping, wet mopping, vacuuming, and scrubbing as necessary to meet the applicable performance standards. The PWS also requires cleaning of interior glass and mirrors. The expressly identified periodic service is washing and disinfecting trash containers at least twice annually.
Subcontracting and Performance Arrangements
Is subcontracting permitted for the on-site janitorial work under this acquisition?
Answer:
The solicitation does not expressly prohibit subcontracting. Any subcontracting must comply with the solicitation, applicable FAR and AGAR requirements, and the resulting order. The prime contractor remains responsible for all contract performance, including the acts and omissions of subcontractors, compliance with the PWS and QCP, labor requirements, facility-access requirements, and protection of Government property.
Can a subcontractor’s supervisor perform recurring on-site quality-control inspections and sign checklists?
Answer:
Yes. A subcontractor’s supervisor may perform contractor quality-control inspections and sign applicable checklists if authorized by the prime contractor and permitted under the Government’s facility-access requirements. The supervisor must perform those duties in accordance with the contractor’s QCP. The signature documents contractor quality-control activity and does not constitute Government inspection, acceptance, or approval of the services. The prime contractor remains responsible for the subcontractor’s performance.
Personnel Access, Background Checks, and Building Security
What specific background checks, badging, or workforce-integrity credentials are required for after-hours facility access under AGAR 452.204-71?
Answer:
All contractor and authorized subcontractor personnel requiring access must comply with applicable Government identity-verification, access-control, key-control, and facility-security requirements before entering the facility or receiving keys or other access devices. The prime contractor is responsible for ensuring compliance by its personnel and subcontractors.
What is the process and typical lead time for obtaining building keys and alarm codes?
Answer:
After award, the Contracting Officer or COR will coordinate facility access, including any required keys, access devices, or alarm procedures, with the successful contractor. The solicitation does not establish a guaranteed lead time for issuing keys or alarm information. Access devices and alarm information will be provided only to authorized personnel who satisfy applicable Government requirements. The contractor must safeguard all keys and immediately report lost keys in accordance with PWS § 1.6.
Are subcontractor personnel authorized to access the facility under PWS § 1.6?
Answer:
Authorized subcontractor personnel may access the facility when they are performing work under the order, are authorized by the prime contractor, and satisfy all applicable Government facility-access and security requirements. The prime contractor remains responsible for ensuring that subcontractor personnel comply with PWS § 1.6, including restrictions on unauthorized persons, key control, building security, and protection of Government property. Family members, visitors, and other unauthorized persons are not permitted in the facility during performance.
Predecessor Contract
Is Purchase Order 12444522P0040 the direct predecessor contract for this facility?
Answer:
Yes, Purchase Order 12444522P0040 is the direct predecessor contract for this facility.
Insurance and Performance Bonding
What specific insurance types and minimum policy limits are required of the contractor for this order?
Answer:
The contractor remains responsible for obtaining and maintaining insurance required by applicable Federal, State, or local law and the resulting order.
Must insurance evidence be submitted with the quotation or only upon contract award?
Answer:
The solicitation does not require insurance evidence as a quotation submission deliverable. The successful contractor must obtain and maintain any insurance required by the resulting order and applicable law and must provide evidence of coverage if required by this agency.
Quotation Submission Deliverables and Evaluation
Does submission of a completed Experience Questionnaire, Form FS-6300-27, satisfy the Technical Capability narrative requirement?
Answer:
Attachment E is identified as an optional submission. It can be used to document a contractor’s technical capability, provided it gives the information requested as found in the solicitation. Some contractors prefer to use the questionnaire, others prefer to document their technical capability as a separate document. So long as the essential elements as found in the solicitation are given, the information will be accepted.
Is a quotation in the offeror’s custom format acceptable?
Answer:
Yes, provided the quotation is clear, complete, timely, and includes all information required by the solicitation. At a minimum, the quotation must include pricing for the base year and all four option years, the required technical-capability information, and the required past-performance information. A custom format must not omit or alter any solicitation requirement.
Will references for similar work performed by a proposed subcontractor be evaluated under past performance?
Answer:
Quoters may identify relevant subcontractor experience and references. The Government will evaluate the information consistent with the solicitation’s stated evaluation procedures and may consider the relevance and extent of the proposed subcontractor’s role. Submission of subcontractor experience does not relieve the prime contractor of responsibility for successful contract performance.
The Government does not guarantee that subcontractor past performance will receive the same consideration as the prime contractor’s past performance.
Are there any issued amendments or extensions to the submission deadline of November 9, 2026, at 10:00 a.m. Eastern Time?
Answer:
As of the date of this amendment, the question deadline is November 4, 2026, at 4:00 p.m. Eastern Time, and the quotation deadline is extended to November 13, 2026, at 10:00 a.m. Eastern Time, unless changed by a subsequently issued solicitation amendment. Quoters are responsible for reviewing SAM.gov for the complete and current solicitation and all amendments.
Wage Rates and Executive Orders
Which Health and Welfare fringe-benefit rate applies given the inclusion of FAR 52.222-62 concerning Executive Order 13706 paid sick leave?
Answer:
Based on the Wage Determination included in this solicitation and the inclusion of FAR 52.222- 62, the applicable Health and Welfare rate for covered contract performance is $5.42 per hour.
The applicable monetary wage for the Janitor classification is $15.90 per hour.
The contractor must also comply separately with the paid-sick-leave requirements of Executive Order 13706 and FAR 52.222-62, as applicable. The Health and Welfare amount may not be used as a credit toward the contractor’s separate paid-sick-leave obligation.
Is there an applicable predecessor collective-bargaining agreement governing wages for this requirement?
Answer:
The solicitation package does not identify a predecessor collective-bargaining agreement. The solicitation includes Department of Labor Wage Determination No. 2015-5101, Revision 31, including the listed wage and fringe-benefit requirements for the Janitor, Occupation Code 11150 classification. Quoters should base their quotations on the wage determination and other labor requirements included in the solicitation. If the Government determines that a predecessor collective-bargaining agreement applies under the Service Contract Labor Standards, the applicable wage and fringe-benefit requirements will be incorporated or otherwise addressed by formal solicitation amendment or contract action before performance begins.
Question:
Is a single-member LLC owner-operator exempt from the Service Contract Act for the owner’s own labor hours?
Answer:
The individual’s ownership status or business form, by itself, does not determine whether the Service Contract Labor Standards apply. Coverage depends on the individual’s actual status and duties under applicable law, including whether the individual is an employee performing covered service work and whether an exemption applies. A quoter should not assume that an owner-operator is exempt solely because the individual is a member of an LLC.
The contractor is responsible for complying with applicable wage, fringe-benefit, recordkeeping, and classification requirements. Questions requiring a definitive employee-status determination should be referred to the Contracting Officer, agency labor advisor, or the Department of Labor.
For more information related to the Department of Labor, please visit www.dol.gov
Quality-Control Plan
Question:
Must the complete Quality Control Plan accompany the quotation, or is it required post-award?
Answer:
The complete QCP is not required with the quotation. The successful contractor must develop, maintain, and provide the QCP to the Contracting Officer and COR after award in accordance with PWS § 1.10. The QCP must be submitted within the timeframe specified by the Contracting http://www.dol.gov/
Officer and before or at the start of performance, as directed. The contractor remains responsible for meeting all PWS requirements from the commencement of performance.
What is the required response and completion time for complaint-related re-performance under the “immediate” standard?
Answer:
The QASP states that re-performance, if needed, shall be performed immediately. The solicitation does not establish a specific number of hours for responding to or completing re-performance. The contractor must promptly address validated deficiencies and coordinate with the COR regarding the corrective action and completion.
Option Periods and FAR 52.217-8
Should the potential six-month extension under FAR 52.217-8 be priced separately within the quotation?
Answer:
No separate six-month CLIN is included in the Schedule of Items, and quoters should provide pricing only for the base year and the four stated option years.
Solicitation and AGAR Clerical Discrepancies
Page 6 lists AGAR 452.236-70 as “Electronic Submission of Payment Requests,” but the standard AGAR framework may use a different clause number. Which clause is controlling?
Answer:
The reference to AGAR 452.236-70, Electronic Submission of Payment Requests (Sep 2026), is corrected by this amendment. The applicable clause is FAR 52.232-33 (Payment by Electronic Funds Transfer—System for Award Management). The requirement for the contractor to submit payment requests electronically through the Department of the Treasury’s Invoice Processing Platform (IPP) remains unchanged. Invoices shall be submitted monthly in arrears through IPP.gov. Paper invoices and invoices submitted by ordinary email will not be accepted for payment.
This amendment corrects the clause number and title only; it does not change the electronic-invoicing requirement.
Which edition of AGAR 452.203-70 controls this requirement?
Answer:
The solicitation identifies AGAR 452.203-70, Unenforceable Supplier Terms (May 2026). The May 2026 edition controls as incorporated in the solicitation unless changed by formal solicitation amendment. A later AGAR edition does not automatically replace the edition identified in the solicitation. If the Contracting Officer determines that a later edition applies, the Government will identify and incorporate that edition by formal amendment. Quoters should rely on the solicitation and formally issued amendments.
Is an official site visit or pre-quotation walkthrough scheduled?
Answer:
No formal group site visit is scheduled. Individual site visits may be coordinated, subject to facility availability and Government approval. Interested quoters should contact Francis Moll at francis.moll@usda.gov to request a site visit. A site visit is not required unless the solicitation is amended to state otherwise. Site visits do not relieve quoters of responsibility for reviewing the solicitation, PWS, QASP, maps, and other attachments.
mailto:francis.moll@usda.gov
| Predecessor Contract |
| Insurance and Performance Bonding |
| Question: |
| Quotation Submission Deliverables and Evaluation |
| Question: |
| Answer: |
| Option Periods and FAR 52.217-8 |
| Solicitation and AGAR Clerical Discrepancies |
| Question: |
| Answer: |
| Question: |
| Answer: |
| Question: |
| Answer: |