C05_12444326Q0047_AMEND1.pdf
PDF 397 KB Posted
- Attached to
- Rochester SST Paint and Repairs Federal contract opportunity
- Solicitation number
- 12444326Q0047
- Issued by
- Department of Agriculture Forest Service
About this file
This is Amendment 1 to Solicitation 12444326Q0047, issued by USDA Forest Service CSA East 5 on July 30, 2026, for paint and repairs work at the Green Mountain National Forest Rochester Sanitary Sewage Treatment (SST) facilities.
The amendment incorporates a Questions and Answers document that clarifies solicitation requirements. Key clarifications include: Silver Lake Picnic Area coordinates (43.892548, -73.050514); mockups are not required as paint must match existing finishes; vent stack exhaust fans are to be installed on existing vent stacks to accelerate waste tank venting; concrete floor preparation and coating apply to all sites as specified in the solicitation table, with Moosalamoo Campground being the primary concrete floor site; and SAM representations and certifications suffice for submission. The work encompasses seven sites (Texas Falls Observation Site, Robert Frost, Moosalamoo Campground, Silver Lake Picnic Area, Silver Lake Campground, and Lefferts Pond) with a combined total of 12 buildings and 16 stalls requiring painting and solar exhaust fan installation. The Period of Performance runs from August 21, 2026 to October 1, 2026. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files for this federal contract opportunity
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12444326Q0047 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ATLANTA GA 30309-2449
STE 876S
1720 PEACHTREE ST NW
USDA-FS CSA EAST 5
07/30/20260001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/30/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
GREEN MOUNTAIN NATIONAL FOREST
ROCHESTER SST PAINT AND REPAIRS
AMENDMENT #1 - THIS AMENDMENT INCORPORATES THE ATTACHED "QUESTIONS AND ANSWERS" DOCUMENT.
ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED
Period of Performance: 08/21/2026 to 10/01/2026
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
CARRIE L. EDWARDS
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation Questions and Answers Rochester SST Paint and Repairs
12444326Q0047
Question 1: The site table in Attachment 1 lists Silver Lake Picnic Area (1 building, 1 stall) but the PROJECT IDENTIFICATION lists gives directions and coordinates for only five sites, and Silver Lake Picnic Area is not among them. Please provide the location or coordinates for the Silver Lake Picnic Area SST so it can be priced and reached.
Answer 1: The location for the Silver Lake picnic area is 43.892548, -73.050514
Question 2: Section 3000 requires a full-coat sample (mockup) for approval before each coating is applied to each surface type. Please confirm how many mockups are required and whether they may all be done at one site, and whether work may continue at the other sites while a mockup is awaiting approval. The sites are separated by road miles, so a hold for approval at each one would add return trips.
Answer 2: Mock ups will not be required. Paint is to match existing.
Question 3: Can you please clarify if the Vent Stack Fan Model FAN-1 should be installed on the roof of each stall or maybe on top of each stack visible on the solicitation plans?
Answer 3: The vent stack exhaust fan is to be installed on the stack to pull air up and out.
Question 4: Is the intention of the government to accelerate venting of the waste tanks (and install the new fans on existing vent stacks) or vent the restrooms (and install the new fans on the restroom roof or walls)? If the last one, can the vents be installed on the walls to ensure no water penetrates inside if installed on the roofs? The roofs are concrete with wood shake imitation which will make very hard to install proper and esthetical vent flashing. Please note that the specified Romtec Fan website states “The Solar Exhaust Fan for waterless, vault restrooms fits on top of the Romtec vent pipe to promote air flow and not inhibit ordinary natural flow. Promotes odor-free facilities.”
Suck vent pipe is the 12” vent pipe that vents the waste tank in those restrooms.
Answer 4: Yes, it is the intention of the Government to accelerate venting of the waste tanks and install the new fans on existing vent stacks.
Question 5: At the Summary of Work paragraph 1.1, second bullet is stated:
“Cleaning, scraping and sanding all concrete floors, walls and ceilings, followed by application of the specified paint system in accordance with manufacturer’s requirements.” However in the table following it, the only site where it is referenced an in bold “concrete floor” is at Moosalamoo Campground 6 stalls. Please clarify if the only concrete floors to be prepared and coated are the Moosalamoo Campground 6 stalls or all other sites’ restrooms as well?
Answer 5: Please follow the table provided in the solicitation (see below)
Question 6: Under the general notes, it states that we need to submit representations and certifications. Is there a certain section of the solicitation to fill out or will SAM reps and certs suffice?
Answer 6: SAM reps and certs will suffice.
| 2026-08-18T13:17:35-0400 | |
| CARRIE EDWARDS |