C04b_Attachment 3_SOI_12444026Q0085.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
LAKE SINCLAIR DUMP STATION REPAIR Federal contract opportunity
Solicitation number
12444026Q0085
Issued by
Department of Agriculture Forest Service

About this file

This is a Statement of Objectives (SOO) and pricing template for the Lake Sinclair Dump Station Repair project, Solicitation Number 12444026Q0085, issued by the Department of Agriculture Forest Service. The project scope involves repairing a damaged septic drain line at an RV dump station through concrete cutting and removal, excavation, jackhammering, pipe removal and replacement, backfilling, and concrete installation with site stabilization measures.

The base bid items include mobilization (calculated at 20% of subtotal), soil erosion and site stabilization (400 SY), excavation (1 LS), new line/piping and fittings replacement (20 LF), concrete sawing (0.5 LF), concrete removal (1.2 CY), jackhammer work (1 day), backfilling (1 CY), pipe removal (20 LF), restricted area signage (1 LS), and concrete installation (1.2 CY). Optional items consist of replacing 2 barrier wooden logs, 6 wooden pole logs, and 2 wooden signposts with existing signs installed on new posts. The pricing template structure includes unit prices for each line item, with contractor overhead and profit applied at 20% of the subtotal. The template provides separate grand total calculations for base items only and for base items combined with optional items. All unit prices and cost fields are currently blank, indicating this is a blank template awaiting contractor pricing submission.

View the file

Other files for this federal contract opportunity

Other files attached to LAKE SINCLAIR DUMP STATION REPAIR, newest first.
File Type Posted
C04g_Lake Sinclair Questions and Responses 5-28-26.docx DOCX document
C04_12444026Q0085_0001_S.pdf PDF
C04_12444026Q0085_s.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

LK Sinclair Dump Station Repair - Base Bid Items
No.ItemUnitsEst. QtyUnit PriceCost
1Mobilization (Base Only) (20% of Subtotal [w/o mobilization])$ - 0
2Soil Erosion and Site StabilizationSY400$ - 0
3ExcavationLS1$ - 0
4New line/piping and proper fittings replacementLF20$ - 0
5Concrete SawingLF0.5$ - 0
6Concrete RemovalCY1.2$ - 0
7JackhammerDay1$ - 0
8BackfillingCY1$ - 0
9Pipe RemovalLF20$ - 0
10Restricted Area SignageLS1$ - 0
11Concrete InstallationCY1.2$ - 0
LK Sinclair Dump Station Repair - Optional Bid Items
No.ItemUnitsEst. QtyUnit PriceCost
1Replacing barrier wooden logsEA2$ - 0
2Replacing wooden pole logsEA6$ - 0
3Replacing wooden signpostsEA2$ - 0
For Base Items Only
Subtotal (w/o mobilization)$ - 0
Subtotal$ - 0
Contractor Overhead and Profit (20% of Subtotal)$ - 0
Grand Total$ - 0
For Base and Optional Items
Subtotal (w/o mobilization)$ - 0
Subtotal$ - 0
Contractor Overhead and Profit (20% of Subtotal)$ - 0
Grand Total$ - 0

File details come from the government source that posted it. Updated .