C04b_Attachment 3_SOI_12444026Q0085.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- LAKE SINCLAIR DUMP STATION REPAIR Federal contract opportunity
- Solicitation number
- 12444026Q0085
- Issued by
- Department of Agriculture Forest Service
About this file
This is a Statement of Objectives (SOO) and pricing template for the Lake Sinclair Dump Station Repair project, Solicitation Number 12444026Q0085, issued by the Department of Agriculture Forest Service. The project scope involves repairing a damaged septic drain line at an RV dump station through concrete cutting and removal, excavation, jackhammering, pipe removal and replacement, backfilling, and concrete installation with site stabilization measures.
The base bid items include mobilization (calculated at 20% of subtotal), soil erosion and site stabilization (400 SY), excavation (1 LS), new line/piping and fittings replacement (20 LF), concrete sawing (0.5 LF), concrete removal (1.2 CY), jackhammer work (1 day), backfilling (1 CY), pipe removal (20 LF), restricted area signage (1 LS), and concrete installation (1.2 CY). Optional items consist of replacing 2 barrier wooden logs, 6 wooden pole logs, and 2 wooden signposts with existing signs installed on new posts. The pricing template structure includes unit prices for each line item, with contractor overhead and profit applied at 20% of the subtotal. The template provides separate grand total calculations for base items only and for base items combined with optional items. All unit prices and cost fields are currently blank, indicating this is a blank template awaiting contractor pricing submission.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C04g_Lake Sinclair Questions and Responses 5-28-26.docx | DOCX document | |
| C04_12444026Q0085_0001_S.pdf | ||
| C04_12444026Q0085_s.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| LK Sinclair Dump Station Repair - Base Bid Items | |||||
| No. | Item | Units | Est. Qty | Unit Price | Cost |
| 1 | Mobilization (Base Only) (20% of Subtotal [w/o mobilization]) | $ - 0 | |||
| 2 | Soil Erosion and Site Stabilization | SY | 400 | $ - 0 | |
| 3 | Excavation | LS | 1 | $ - 0 | |
| 4 | New line/piping and proper fittings replacement | LF | 20 | $ - 0 | |
| 5 | Concrete Sawing | LF | 0.5 | $ - 0 | |
| 6 | Concrete Removal | CY | 1.2 | $ - 0 | |
| 7 | Jackhammer | Day | 1 | $ - 0 | |
| 8 | Backfilling | CY | 1 | $ - 0 | |
| 9 | Pipe Removal | LF | 20 | $ - 0 | |
| 10 | Restricted Area Signage | LS | 1 | $ - 0 | |
| 11 | Concrete Installation | CY | 1.2 | $ - 0 | |
| LK Sinclair Dump Station Repair - Optional Bid Items | |||||
| No. | Item | Units | Est. Qty | Unit Price | Cost |
| 1 | Replacing barrier wooden logs | EA | 2 | $ - 0 | |
| 2 | Replacing wooden pole logs | EA | 6 | $ - 0 | |
| 3 | Replacing wooden signposts | EA | 2 | $ - 0 | |
| For Base Items Only | |||||
| Subtotal (w/o mobilization) | $ - 0 | ||||
| Subtotal | $ - 0 | ||||
| Contractor Overhead and Profit (20% of Subtotal) | $ - 0 | ||||
| Grand Total | $ - 0 | ||||
| For Base and Optional Items | |||||
| Subtotal (w/o mobilization) | $ - 0 | ||||
| Subtotal | $ - 0 | ||||
| Contractor Overhead and Profit (20% of Subtotal) | $ - 0 | ||||
| Grand Total | $ - 0 |