This is a Solicitation Addendum One document issued by the State of Nebraska, Nebraska Game & Parks Commission, revising the schedule of events for a tree clearing service contract at Merritt Reservoir Wildlife Management Area. The solicitation (Number 124151 O3) seeks comprehensive tree removal services across approximately 216.6 acres in Cherry County, Nebraska, including eastern red cedar, Rocky Mountain juniper, and scattered ponderosa pine. The revised procurement schedule establishes key deadlines: Intent to Attend Solicitation Conference submission by January 16, 2026, at 5:00 p.m. Central Time; written questions due by January 28, 2026, at 5:00 p.m. Central Time; and electronic solicitation responses required via ShareFile by February 10, 2026, at 3:00 p.m. Central Time. The mandatory solicitation conference is scheduled for January 21, 2026, from 10:00 a.m. to 3:00 p.m. at 88079 State Highway 97, Valentine, Nebraska. The state anticipates posting an Intent to Award by February 20, 2026, with contract finalization by March 4, 2026, and final award by March 5, 2026. The contract term runs from execution through June 30, 2027, with potential extension by mutual agreement.
Work must be divided into units of at least 50 acres, with 50 percent completion required in the first year and 50 percent in the second year. Contractors must be capable of removing materials through mulching and cutting/piling methods, with opportunities to negotiate reduced per-acre rates in exchange for removing and utilizing merchantable timber. Work is restricted to dry or frozen ground conditions and limited by specific timeframes to avoid interference with campground operations and the Nebraska Star Party. Bidders must comply with standard state contractual requirements, including registration with the Nebraska Secretary of State, and maintain insurance coverage of $2,000,000 Commercial General Liability, statutory Workers' Compensation, and $1,000,000 Commercial Automobile Liability. No advance payments are permitted, and the contract is subject to legislative appropriation of funds. Prospective bidders are responsible for monitoring the State Purchasing Bureau website for all addenda and amendments, with electronic submission via ShareFile being mandatory and no exceptions made for technology issues.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION ADDENDUM ONE
REVISED SCHEDULE OF EVENTS, SHARED LINKS
SOLICITATION NUMBER: 124151 O3
Tree Clearing at Merritt Reservoir Wildlife Management Area Opening Date: February 10, 2026, 3:00 p.m. Central Time Addendum Effective Date: January 12, 2025.
Revised Schedule of Events
The State expects to adhere to the tentative procurement schedule shown below. It should be noted, however, that some dates are approximate and subject to change. It is the responsibility of bidders to check the State Purchasing Bureau website for all addenda or amendments.
| Activity |
| Date/Time |
| 1 |
| Last day to submit “Intent to Attend Solicitation Conference” |
ShareFile link for uploading Intent to Attend Solicitation Conference: https://nebraska.sharefile.com/r-r2c592bb977bf4294af73185b0d71e0c9
January 16, 5:00 p.m.
Central Time
| 1. |
| Last day to submit written questions after Solicitation Conference |
ShareFile link for uploading questions: https://nebraska.sharefile.com/r-rb72848a9ed2b4651a59a0953b7f23fdd January 28, 2026.
5:00 p.m. Central Time.
| 1. |
| Electronic Solicitation Opening – Online Via Webex |
IT IS THE BIDDER’S RESPONSIBILTY TO UPLOAD ELECTRONIC FILES BY OPENING DATE AND TIME. EXCEPTIONS WILL NOT BE MADE FOR TECHNOLOGY ISSUES.
ShareFile Electronic Solicitation Submission Link: https://nebraska.sharefile.com/r-raf7359eddb4d4b5e9667a95ae555caea Join Webex Meeting https://sonvideo.webex.com/sonvideo/j.php?MTID=m7631e63d5ea7bc1b44c7a7ccffa0855e
February 10, 2026.
2:00 p.m. Central Time
February 10, 2026.
3:00 p.m. Central Time
This addendum will be incorporated into the solicitation.
SPB Form 27 Last Revised 4-17-2025