This Solicitation Addendum One document provides a revised schedule of events for Solicitation Number 124151 O3, issued by the Nebraska Game & Parks Commission for Tree Clearing services at Merritt Reservoir Wildlife Management Area. The project encompasses approximately 216.6 acres requiring removal of eastern red cedar, Rocky Mountain juniper, and scattered ponderosa pine through mulching and cutting/piling methods, with contractors required to divide work into units of at least 50 acres and complete 50 percent in the first year and 50 percent in the second year. Key dates include the deadline for submitting Intent to Attend Solicitation Conference on January 16, 2026, at 5:00 p.m. Central Time; the deadline for written questions on January 28, 2026, at 5:00 p.m. Central Time; electronic solicitation opening via Webex on February 10, 2026, at 2:00 p.m. Central Time; and the formal opening at 3:00 p.m. Central Time on the same date. A mandatory solicitation conference was held on January 21, 2026, at the project location (88079 State Highway 97, Valentine, NE). The contract term runs from execution through June 30, 2027, with potential extension by mutual agreement.
The addendum emphasizes that bidders are solely responsible for uploading electronic files by the opening date and time via ShareFile, with no exceptions made for technology issues. State responses to written questions are posted by February 4, 2026, with an Intent to Award scheduled for February 20, 2026, contract finalization by March 4, 2026, and award by March 5, 2026. Required insurance includes $2,000,000 Commercial General Liability, statutory Workers' Compensation, and $1,000,000 Commercial Automobile Liability. Work is restricted to dry or frozen ground conditions and limited by specific timeframes to avoid interference with campground operations. Bidders may negotiate reduced per-acre thinning rates in exchange for removing and utilizing merchantable timber. The project is subject to legislative appropriation of funds with no advance payments permitted, and all bidders must be registered with the Nebraska Secretary of State and comply with standard state contractual provisions including civil rights laws and Americans with Disabilities Act requirements.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION ADDENDUM ONE
REVISED SCHEDULE OF EVENTS, SHARED LINKS
SOLICITATION NUMBER: 124151 O3
Tree Clearing at Merritt Reservoir Wildlife Management Area Opening Date: February 10, 2026, 3:00 p.m. Central Time Addendum Effective Date: January 12, 2025.
Revised Schedule of Events
The State expects to adhere to the tentative procurement schedule shown below. It should be noted, however, that some dates are approximate and subject to change. It is the responsibility of bidders to check the State Purchasing Bureau website for all addenda or amendments.
| Activity |
| Date/Time |
| 1 |
| Last day to submit “Intent to Attend Solicitation Conference” |
ShareFile link for uploading Intent to Attend Solicitation Conference: https://nebraska.sharefile.com/r-r2c592bb977bf4294af73185b0d71e0c9
January 16, 5:00 p.m.
Central Time
| 1. |
| Last day to submit written questions after Solicitation Conference |
ShareFile link for uploading questions: https://nebraska.sharefile.com/r-rb72848a9ed2b4651a59a0953b7f23fdd January 28, 2026.
5:00 p.m. Central Time.
| 1. |
| Electronic Solicitation Opening – Online Via Webex |
IT IS THE BIDDER’S RESPONSIBILTY TO UPLOAD ELECTRONIC FILES BY OPENING DATE AND TIME. EXCEPTIONS WILL NOT BE MADE FOR TECHNOLOGY ISSUES.
ShareFile Electronic Solicitation Submission Link: https://nebraska.sharefile.com/r-raf7359eddb4d4b5e9667a95ae555caea Join Webex Meeting https://sonvideo.webex.com/sonvideo/j.php?MTID=m7631e63d5ea7bc1b44c7a7ccffa0855e
February 10, 2026.
2:00 p.m. Central Time
February 10, 2026.
3:00 p.m. Central Time
This addendum will be incorporated into the solicitation.
SPB Form 27 Last Revised 4-17-2025