CUSTER GALLATIN NATIONAL FOREST - Lead Based Paint Removal & Painting
Solicitation number
1240LU25Q0051
Issued by

About this file

This is a Solicitation, Offer, and Award (Standard Form 1442) for a lead-based paint removal and painting project issued by the USDA Forest Service for the Custer Gallatin National Forest. The contract is for removing lead-based paint and repainting exterior surfaces of four buildings located at Meyers Creek Station and West Bridger Cabin in Montana, with a total project scope of approximately 6,635 square feet across four buildings.

The project is set aside 100% for small businesses, with a NAICS code of 238320 (Commercial and Institutional Building Construction) and a small business size standard of $19,000,000. The estimated contract value is between $100,000 and $250,000, with work anticipated to begin in July 2026 and be completed within 60 calendar days. Contractors must provide performance and payment bonds at 100% of the original contract price if the contract exceeds $150,000. The solicitation requires both a price proposal and a technical proposal, which will be evaluated based on past performance, experience, and price using a best value approach.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1153015

USDA-FS CSA INTERMOUNTAIN 9

324 25TH ST

OGDEN UT 84401-2310

40LU

PPS, Intermountain Zone, CSA 9

Alisha Knaub or alisha.knaub@usda.gov 415 South Front Street Townsend, MT 59644

ALISHA KNAUB 406-438-2981

GAOA

08/19/2025

1240LU25Q0051

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

CUSTER GALLATIN NATIONAL FOREST

GAOA Cabin Building Lead Based Paint Removal & Painting

The intent of the contract is to provide for the completion of the work described below. The precise details of performing the work are not stipulated, except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

The work shall consist of removing lead-based paint on existing buildings; preparing the exterior of the buildings for new paint; furnishing and applying new paint on the exterior.

The North American Industry Classification System (NAICS) code for this work is

238320, Commercial and Institutional Building Construction with a small business size standard of $19,000,000. This requirement is set aside 100% for small business participation.

Performance and Payment Bonds: Both required at 100% of original contract price if

Continued ...

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 60 calendar days and complete it within ________________ ________________ calendar days after receiving

Section C

_______________________ 09/09/2025

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA-FS CSA INTERMOUNTAIN 9

324 25TH ST

OGDEN UT 84401-2310

40LU

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 39

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

1240LU25Q0051

contract value in excess of $150,000, due 10 days after award. Only payment protections required for contracts exceeding $35,000 but not exceeding

$150,000, irrevocable letter of credit or payment bond allowed per FAR 52.228-13, due within 10 days of contract award.

Bid Bond/Offer Guarantee (FAR 52.228-1): 20% required if quote/offer in excess of

$150,000.

Email quotes as response to this solicitation are authorized and can be sent to alisha.knaub@usda.gov. Use address in Box 8 for mailed proposals.

Delivery: 08/31/2026

Delivery Location Code: 0355

USDA FOREST SERVICE

BILLINGS OFFICE

5001 SOUTHGATE DR STE 2

BILLINGS MT 59101 US

0001 FY25 Lead Based Paint Removal & Painting-Meyers

Creek and West Bridger Creek Cabins

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

1240LU25Q0051

GAOA Lead Based Paint Removal & Painting

Beartooth/Yellowstone RD, Custer Gallatin NF

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 SITE VISIT

C.5 PERIOD OF PERFORMANCE

C.4 TECHNICAL SPECIFICATIONS

PART I - GENERAL

PART II - PRODUCTS

PART III - EXECUTION

PART IV – PAYMENT

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

H.2 OTHER REQUIREMENTS

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF

OFFERORS OR RESPONDENTS

K.1 PROVISIONS

K.2 OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

L.1 PROVISIONS

L.2 QUOTE PREPARATION INSTRUCTIONS:

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 QUOTE EVALUATION

M.2 TECHNICAL EVALUATION FACTORS

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

FY25 GAOA Cabins Building Lead Based Paint Removal & Painting 1BF & 1ES

Building #2400 Meyers Creek Barn 1ES Building # 1502 Meyers Creek Garage/Shop 1ES Building #1007 Meyers Creek White House 1BF Building #1009 West Bridger Creek Cabin 1BF

B.1 SCHEDULE OF ITEMS

Pay Item Description Method of

Measure Pay Unit

Estimated Quantity Unit Price Total Price

1 Mobilization LSQ LS All * * * * * $_________

Building #2400 Meyers Creek Barn

2 LBP Removal Square Feet SF 1700 $________ $_________

3 Exterior Wall Painting Square Feet SF 1700 $________ $_________

Building # 1502 Meyers Creek Garage/Shop

4 LBP Removal Square Feet SF 2285 $________ $_________

5 Exterior Wall Painting Square Feet SF 2285 $________ $_________

Building #1007 Meyers Creek White House

6 LBP Removal Square Feet SF 1650 $________ $_________

7 Exterior Wall Painting Square Feet SF 1650 $________ $_________

Building #1009 West Bridger Creek Cabin

8 LBP Removal Square Feet SF 1000 $________ $_________

9 Exterior Wall Painting Square Feet SF 1000 $________ $_________

TOTAL PRICE: $_________

Price Quotation Furnished By:

Name: ______________________________ Phone: _________________________________ Address:____________________________ UEI #: _______________________________ _____________________________ E-mail: ________________________________

B.2 SCHEDULE NOTES

a) One award will be made from this solicitation, contractors must submit pricing for all items. Only unit prices to the nearest $0.01 will be accepted. Where extended unit prices do not agree with totals or subtotals shown by the quoter, the unit price governs.

b) The quantities provided are for quoting purposes only. The Contractor shall be responsible for verifying all building measurements to determine necessary quantities of materials to be furnished.

c) Performance and Payment Bonds: Both required at 100% of original contract price if contract value in excess of $150,000, due 10 days after award. Only payment protections required for contracts exceeding $35,000 but not exceeding $150,000, irrevocable letter of credit or payment bond allowed per FAR 52.228-13, due within 10 days of contract award

d) Bid Bond/Offer Guarantee (FAR 52.228-1): 20% required if quote/offer in excess of $150,000.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

The intent of the contract is to provide for the completion of the work described below. The precise details of performing the work are not stipulated, except as considered essential for the successful completion of the work. Furnish all labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

The work shall consist of removing lead-based paint on existing buildings; preparing the exterior of the buildings for new paint; furnishing and applying new paint on the exterior.

Meyers Creek Paint: House, Barn, and Shed

Lead- All three buildings test positive for lead. The house has undergone lead remediation, but the wooden siding still tests positive for lead.

Detail- All three buildings consistent: white siding, green trim, rafter tails, underside of eave and gable rake.

House- 26.5’x32.5’, front porch 15.5’x7’, back porch 16’x8.5’; 10’ under eave, 16’ under gable peak. 1650ft²; 4” lap siding

Barn- 18.5’x32.5’; 15’ under eave, 24’ under gable peak. 1700ft²; 5” drop siding

Shed- 30.5’x56.5’; 10.5’ under eaves, 18’ under gable peak. 2285ft²; 6” drop siding

West Bridger Paint: Cabin

Lead- The cabin no longer has the original lead-based paint, but the wooden siding still tests positive for lead, and some remnants of the original paint remain.

Detail- White siding, green trim, soffit, and fascia.

House- 15.5’x32.5’, no more than 10’ under eave. Porch enclosed by 29” half-wall, 8’x15’.

1000ft² plus porch details 4” lap siding(?)

7” enclosed soffit, 4” fascia

ITEM 1, Mobilization: Work shall consist of preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies, and incidentals to the project site;

and for other work and operations that must be performed, or costs incurred prior to beginning work on the various items on the project site.

ITEM 2, Lead Based Paint Removal: Removal of all Lead Based Paint on the buildings as specified and comply with all local, state and federal regulations.

ITEM 3, Exterior Preperation and Painting : Work shall consist of the contractor stripping all exterior paint from siding prior to painting or as indicated by CO. Preparation to include but not limited to: cleaning and repairing damaged siding, trim and doors, protecting windows doors utilities, soffitt and any other external items located on siding. The contractor shall paint all external siding as well as trim with Sherwin Williams Duration paint or approved equal. Color and Sheen to be approved by CO.

C.2 PROJECT LOCATION

This project is located at Meyers Creek Station of the Custer Gallatin National Forest in Nye, Montana and West Bridger Cabin locates south of Big Timber, MT

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

Between $100,000 and $250,000

C.4 SITE VISIT

No formal site visit of the project will be conducted. Prospective quoters wishing to visit the site on their own may obtain direction information by contacting Sam Archambault at the Billings Office, Custer Gallatin National Forest, Billings, Montana, telephone (406) 255-1423.

C.5 PERIOD OF PERFORMANCE

It is estimated that work can begin in July 2026. Contract to be completed in 60 calendar days.

Contractor shall give 60 days notice prior to start due to buildings listed on the government reservation program and used by the public.

C.6 FACILITIES

The contractor may use the water and restrooms on-site with CO approval. The contractor may also use on-site electrical service for operation of small power tools with CO approval.

C.7 TECHNICAL SPECIFICATIONS

The following CSI formatted specifications are part of this solicitation and any resulting contract.

Section Description 01000 Mobilization 01025 Measurement and Payment 01400 Quality Control and Quantity Measurement 02094 Work Involving Lead Based Paint 07000 Building Maintenance

SECTION 01000

MOBILIZATION

PART I: GENERAL

1.1 SUMMARY

A. Section Includes: Preparatory work and operations, including those necessary to the movement of personnel, equipment, supplies and incidentals to the project site; and for other work and operations which must be performed, or costs incurred prior to beginning work on the various items on the project site. This specification does not include moves between project sites.

PART II: PRODUCTS

(There are no applicable requirements.)

PART III: EXECUTION

(There are no applicable requirements.)

PART IV: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT:

A. Units: Progress payments will be made as follows:

1. When 5% of the original Contract amount is earned from other bid items, 50% of the amount bid for mobilization or 5% of the original Contract amount, whichever is lesser, will be paid.

2. When 10% of the original Contract amount is earned from other bid items, 100% of the amount bid for mobilization or 10% of the original Contract amount, whichever is lesser, will be paid.

3. Upon completion of work for the project, payment of the amount bid for mobilization in excess of 10% of the original Contract amount will be paid.

4. The total sum of all payments shall not exceed the original Contract amount bid for mobilization, regardless of the fact that the Contractor may have shut down the work on the project or moved equipment away from the project and then back again.

4.2 BASIS OF PAYMENT:

Payment: No direct payment for moves between project sites will be made. The Contractor shall include consideration for moves between project sites in the bid price for other items of the Contract. Prices and payment will be full compensation for the work described in this section. Payment will be made under:

Pay Item Pay Unit

(01000) Mobilization. . . . . . . . . . . . . . . . . Lump Sum

END OF SECTION

SECTION 01025

MEASUREMENT AND PAYMENT

PART I - GENERAL

1.1 Measurement and Payment - Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.

When more than one class, size, or thickness is specified in the SCHEDULE OF ITEMS for any pay item, suffixes will be added to the item number to differentiate between items to be bid.

1.2 Determination of Quantities - The following methods of measurement are used to determine contract quantities for payment.

For individual construction items, longitudinal and lateral measurements for area computations will be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, geotextiles, netting, erosion control blankets, and sodding will be along slope lines.

Structures will be measured according to neat lines SHOWN ON THE DRAWINGS or as altered by the COR in writing to fit field conditions.

For standard manufactured items, such as fence, wire, plates, rolled shapes, pipe conduits, etc., identified by gauge, weight, section dimensions, etc., such identification shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances will be accepted.

1.3 Units of Measurement - Payment will be by units defined and determined according to

U.S. Standard measure as follows:

A. Acre – Make longitudinal and transverse measurements for area computations horizontally.

B. Cubic Yard - A measurement computed by one of the following methods:

1. Excavation, Embankment, or Borrow - The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

2. Material in Place or Stockpile - The measurement computed with dimensions of the in-place material.

3. Material in the Delivery Vehicle - The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

C. Cubic Yard Mile - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material 1 mile.

D. Each - One complete unit, which may consist of one or more parts.

E. Gallon – The quantity may be measured by any of the following methods:

1. Measured volume container.

2. Metered volume. Use an approved metering system

3. Commercially packaged volumes.

F. Hour – Measurement will be for the actual number of hours ordered and performed by the Contractor.

G. Linear Foot – Measure from end to end, parallel to the base or foundation being measured, or horizontal.

H. MFBM - One thousand board feet measure based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job.

I. Mile – Measure horizontal along the centerline of each roadway, approach road, or ramp.

J. Pound – If sacked or packaged material is furnished, the net weight as packed by the manufacturer may be used.

K. Square Foot - Measure on a plane parallel to the surface being measured or horizontal.

L. Square Yard – Measure on a plane parallel to the surface being measured or horizontal.

M. Station - One hundred linear feet measured horizontally.

N. Station Yard - A combination of linear and volumetric measurement meaning the movement of a cubic yard of material one station.

O. Thousand Gallons Mile - A combination of linear and volumetric measurement meaning the movement of 1,000 gallons of material 1 mile.

P. Ton - Short ton consisting of 2,000 pounds.

Q. Ton Mile - A combination of linear and weight measurement meaning the movement of 1 ton of material 1 mile.

1.4 Methods of Measurement - One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:

A. Contract Quantities (CQ) AND Design Quantities (DQ) - These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:

1. As a result of changes in the work authorized by the Contracting Officer.

2. As a result of the Contracting Officer determining that errors exist in the original design data used to determine designed quantities that cause a pay item to change by more than 15 percent.

3. As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design data used to determine design quantities that cause a pay item total to change by more than 15%. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

B. Staked Quantities (SQ) - These quantities are determined from staked measurements prior to construction.

C. Actual Quantities (AQ) - These quantities are determined from measurements of completed work.

D. Vehicle Quantities (VQ) - These quantities are measured or weighed in hauling vehicles.

E. Lump Sum Quantities (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.

PART II - PRODUCTS (Not Applicable)

PART III - EXECUTION (Not Applicable)

SECTION 01400

QUALITY CONTROL AND QUANTITY MEASUREMENT

PART I - GENERAL

1.1 Scope - This work shall consist of providing quality control in conformance with the Inspection of Construction provisions of this contract to ensure compliance with the drawings, specifications, and provisions of the contract, and measuring the quantities of completed work in conformance with the provisions of the applicable specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of this specification.

1.2 Measurement and Payment - No separate payment will be made for the work included under this section. Payment for this work is considered incidental to other items of work.

PART II - PRODUCTS (Not Applicable)

PART III – EXECUTION (Not Applicable)

SECTION 02094

WORK INVOLVING LEAD-BASED PAINT (LBP)

PART 1 - GENERAL

1.01 DESCRIPTION OF WORK:

Work under this section includes those engineering controls which are necessary for surface preparation of materials to be resurfaced, or demolition/removal of materials, that are coated with lead base paint (LBP). This is a notification that the work under this contract will bring the Contractor into contact with LBP materials that will require worker protection.

1.02 NOTICE OF HAZARD:

A. The Government has determined that work under this contract will involve exposure to lead-based paint (LBP). Paint to be removed on this project has been analyzed and found to contain lead.

B. Exposure to airborne lead contaminants is a recognized hazard to human health. The

Contractor shall assume that all painted surfaces on which work is required are coated with LBP.

1.03 SUBMITTALS:

A. Health and Safety Plan:

1. The Contractor shall provide a Health and Safety Plan for review and acceptance by the Contracting Officer. No work will commence until acceptance of the plan by the Contracting Officer.

2. The Health and Safety Plan will address, but not be limited to, the health-related standards and protective measures proposed to be utilized by the Contractor during work involving exposure to airborne lead contaminants.

3. The Health and Safety Plan will also identify the engineering and work practice controls proposed to be implemented by the Contractor. Such controls will be identified to assure the Government that there will be no release to the environment of lead contamination for which liability may be imposed on the Government.

1.04 WORKER PROTECTION:

OSHA requirements for worker protection shall be followed in accordance with 29 CFR 1926.62, Lead Exposure in Construction.

1.05 WASTE ANALYSIS AND MANAGEMENT:

A. The Contractor will be responsible for representative sampling and analysis of waste generated during this project. If the Contractor determines that the waste is hazardous in accordance with Appendix II of 40 CFR 261, then the responsibility for its management rests with the Contractor. If it is determines that the waste is non-hazardous, then the Contractor shall retain responsibility for managing the waste.

B. Unless directed otherwise by the Contracting Officer with respect to a particular waste, the Contractor shall assume that any waste containing lead-based paint is hazardous.

C. The Contractor shall segregate dust and small debris which may contain lead-based paint.

Such waste shall be double bagged, secured with tape, and labeled with required labels.

D. Paint debris shall not be placed on unprotected ground and shall be shielded adequately to prevent dispersion by wind or rainwater.

E. Larger hazardous waste items which cannot be bagged shall be wrapped in plastic, secured with tape, labeled, and set aside for Government approval of disposal method.

F. Properly wrapped, secured, and labeled hazardous waste will be placed in containers provided by the Contractor.

G. Non-hazardous waste will be placed in containers provided by the Contractor.

PART 2 - PRODUCTS

2.01 MATERIALS:

A. Disposal bags and sheeting: Provide 6 mil thick plastic disposal bags and sheeting for wrapping hazardous waste.

B. Disposal bins: The Contractor shall provide disposal bins for collection of non-hazardous waste prior to disposal by Contractor. The Contractor will provide disposal bins for collection of hazardous waste prior to disposal. All bins shall be secured when not in use to prevent deposit of unauthorized waste and debris.

C. Trisodium phosphate: Industry standard to mix with water for washing solutions on site.

PART 3 - EXECUTION

3.01 SITE PREPARATION:

A. The Contractor shall prepare the site in accordance with the Health and Safety Plan accepted by the Contracting Officer and meet all Federal and State requirements.

B. The Contractor is responsible for establishing and maintaining control measures sufficient to preclude any adverse effects to workers, Forest Service personnel and dependents, the public, and the environment.

A.02 REPAIR

A. The Contractor shall conduct all repair work in accordance with the Health and Safety Plan accepted by the Contracting Officer.

B. All waste will be handled in accordance with the provisions of this section and the directions of the Contracting Officer.

C. Cover the ground with plastic sheeting or other disposable impermeable material extending 10 feet beyond the perimeter of surfaces undergoing renovation or a sufficient distance to collect falling paint debris, whichever is greater. If the renovation will affect surfaces within 10 feet of the property line, then vertical containment or equivalent extra precautions must be erected to prevent contamination of adjacent buildings and property.

D. Close all doors and windows within 20 feet of the renovation. On multi-story buildings, close all doors and windows within 20 feet of the renovation on the same floor as the renovation, and close all doors and windows on all floors below that are the same horizontal distance from the renovation.

E. Ensure that doors within the work area that will be used while the job is being performed are covered with plastic sheeting or other impermeable material in a manner that allows workers to pass through while confining dust and debris to the work area.

F. In certain situations, the renovation firm must take additional precautions in containing the work area to ensure that dust and debris from the renovation does not contaminate other buildings or other areas of the property or migrate to adjacent properties.

G. When working on the 2nd story or above, you should extend the sheeting farther out and to each side where paint is being disturbed.

H. It is also a good idea to use vertical containment if work is close to a sidewalk, street, or property boundary, or the building is more than three stories high.

I. Avoid working in high winds if possible. EPA’s rule does not address wind speed, but when the wind is strong enough to move dust and debris, precautions need to be taken to keep the work area contained. That may mean creating a wind screen of plastic at the edge of the ground-cover plastic to keep dust and debris from migrating. Ultimately, you are responsible for preventing dust and debris from leaving the work area, so take appropriate precautions when wind is a factor or consider rescheduling the renovation for a less windy day.

3.03 CLEANUP:

A. Daily cleanup shall be in accordance with the Health and Safety Plan accepted by the Contracting Officer. Any environmental cleanup caused by Contractor's failure to comply with the provisions of law, of this contract, or the accepted Health and Safety Plan shall be at Contractor's sole expense.

B. Do not allow any paint debris to enter industrial waste, storm drain or sanitary sewer lines.

3.04 INSPECTION:

Contractor shall cooperate and coordinate all work with the Contracting Officer's inspection requirements. Inspection will center on compliance with the Health and Safety Plan accepted by the Contracting Officer.

3.05 CLEARANCE:

A. Contractor shall notify Contracting Officer of readiness for final inspection.

B. The visual inspection will occur no earlier than 24 hours after completion of the entire construction work.

C. Any visible debris will result in the Contractor recleaning the area at no additional cost to the Government.

D. Testing shall be completed by the contractor to ensure a negative result prior to painting.

SECTION 07000

BUILDING MAINTENANCE

EXTERIOR WALL PAINTING

PART I - GENERAL

1.1 Scope - Furnish all labor, materials, and equipment required to paint all exterior walls, and applicable trim, soffit and facia and doors on the building included in the contract.

Any failing sections of paint, is to be removed down to the base layer/material, primed and covered with two coats minimum. Sections of exterior siding are missing and will need to be repaired/replaced before painting. Submit all instructions, warranties, specifications, and color samples to the Contraction Officer (C.O.) for approval.

PART II - PRODUCTS

2.1 Materials:

A. Paint Stripper B. Paint (Exterior) Sherwin Willaims Duration or approved equal.

C. Primer.

D. Replacement Siding, Trim etc. as needed.

2.2 Submittals

A) Submit product information, color samples, warranties, and manufacturer installation instructions before ordering for the following:

1. Schedule

2. Paint to be applied-colors

3. Primer

4. Paint stripper.

5. Siding replacement material

Written approval from the COR is required prior to ordering materials. Allow 7 days for COR approval.

PART III - EXECUTION

3.1 Application

A. Before ordering materials or starting work, verify governing dimensions at buildings:

examine, clean and repair, replace if necessary, any adjoining work on which this work is in any way dependent for its proper installation. Submit warranty, specifications, and installation instructions to C.O. prior to beginning work. The Contractor is required to provide any additional materials or appurtenances in order to properly install and finish all items. All costs for completing any item shall be included in bid items in the schedule.

B. Install all items in according to manufacturer’s instructions, Latest Version of the

International Building Code, and according to industry standard. All items shall be neat, and straight. A professional installation is required.

C. Irregular surfaces, as is typical of older structures, will be encountered. The Contractor will be required to compensate for those irregularities so the finished work is both structurally sound and conforming to the standards of the industry.

D. Existing exterior siding and trim may be damaged/missing in places and shall be repaired prior to painting.

E. Paint all exterior walls, and applicable trim, soffit and facia and doors on the building included in the contract. Any failing sections of paint, is to be removed down to the base layer/material, primed and covered with two coats minimum.

PART IV – PAYMENT

A. Payment shall be as shown on the schedule of items.

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

FAR 52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

FAR 52.211-18 Variation in Estimated Quantity (APR 1984) FAR 52.242-14 Suspension of Work (APR 1984)

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

AGAR 452.204-70 Modification for Contract Closeout

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

H.2 OTHER REQUIREMENTS

Pursuant to FAR clause FAR 52.228-5, Insurance-Work on a Government Installation paragraph (a), Contractors shall present evidence and maintain, as a minimum, the amounts of insurance coverage indicated below:

(1) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they must be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 must be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(2) General Liability. The Contractor must have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(3) Automobile Liability. The Contractor must have automobile liability insurance written on a comprehensive form of policy. The policy must provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States must provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(4) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor must have aircraft public and passenger liability insurance. Coverage must be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury must be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR): https://www.acquisition.gov/browse/index/far (Clauses are located at FAR part 52 and begin with 52)

Department of Agriculture Acquisition Regulation (AGAR):https://www.acquisition.gov/agar (Clauses are located at AGAR part 452 and begin with 452)

Deviations to clauses may be viewed at: USDA FAR Class Deviations

FAR 52.203-7 Anti-Kickback Procedures (JUN 2020) FAR 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN

2020) FAR 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower

Guidance to contractor employees) FAR 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (JAN 2017) FAR 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(JUN 2020)

FAR 52.204-13 System for Award Management Maintenance (OCT 2018) FAR 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) FAR 52.204-19 Incorporation by Reference of Representations and Certifications (DEC

2014) FAR 52.204-23 Prohibition on Contracting for Hardware, Software, and Services

Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/far/part-52 https://www.acquisition.gov/agar https://www.acquisition.gov/agar/part-452-solicitation-provisions-and-contract-clauses https://www.usda.gov/about-usda/general-information/staff-offices/departmental-administration/office-contracting-and-procurement-ocp/usda-far-class-deviations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK

FAR 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)

FAR 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) FAR 52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition (Dec

2023) FAR 52.209-6 Protecting the Government's Interest when Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment, or Voluntarily Excluded (JAN 2025)

FAR 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

FAR 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) FAR 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) FAR 52.219-28 Postaward Small Business Program Rerepresentation (JAN 2025) FAR 52.222-3 Convict Labor (JUN 2003) FAR 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation

(MAY 2018)

FAR 52.222-6 Construction Wage Rate Requirement (AUG 2018) FAR 52.222-7 Withholding of Funds (MAY 2014) FAR 52.222-8 Payrolls and Basic Records (JUL 2021) FAR 52.222-9 Apprentices and Trainees (JUL 2005) (DEVIATION FEB 2025) FAR 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) FAR 52.222-11 Subcontracts (Labor Standards) (MAY 2014) FAR 52.222-12 Contract Termination - Debarment (MAY 2014) FAR 52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations (MAY 2014) FAR 52.222-14 Disputes Concerning Labor Standards (FEB 1988) FAR 52.222-15 Certification of Eligibility (MAY 2014) FAR 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) FAR 52.222-37 Employment Reports on Veterans (JUN 2020) FAR 52.222-50 Combating Trafficking in Persons (NOV 2021) FAR 52.222-54 Employment Eligibility Verification (JAN 2025) FAR 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026

(JAN 2022)

FAR 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) FAR 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts

(MAY 2024) (DEVIATION FEB 2025)

FAR 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2024) FAR 52.223-23 Sustainable Products & Services (MAY 2024) (DEVIATION FEB 2025) FAR 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) FAR 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving

(MAY 2024)

FAR 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) FAR 52.228-2 Additional Bond Security (OCT 1997) FAR 52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION MAY

2023) https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf

FAR 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) FAR 52.228-14 Irrevocable Letter of Credit (NOV 2014) FAR 52.228-15 Performance and Payment Bonds -- Construction (JUN 2020)

(DEVIATION MAY 2023)

FAR 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) FAR 52.232-23 Assignment of Claims (MAY 2014) FAR 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) FAR 52.232-33 Payment by Electronic Funds Transfer – System for Award Management

(OCT 2018)

FAR 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) FAR 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR

2023) FAR 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) FAR 52.233-3 Protest after Award (AUG 1996) FAR 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) FAR 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) FAR 52.236-5 Material and Workmanship (APR 1984) FAR 52.236-7 Permits and Responsibilities (NOV 1991) FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) FAR 52.236-10 Operations and Storage Areas (APR 1984) FAR 52.236-12 Cleaning Up (APR 1984) FAR 52.236-13 Accident Prevention (NOV 1991) FAR 52.236-14 Availability and Use of Utility Services (APR 1984) FAR 52.236-26 Preconstruction Conference (FEB 1995) FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by

American Security Drone Act-Covered Foreign Entities (NOV 2024) FAR 52.243-5 Changes and Changed Conditions (APR 1984) FAR 52.244-6 Subcontracts for Commercial Products and Commercial Services (JAN

2025) (DEVIATION FEB 2025)

FAR 52.246-21 Warranty of Construction (MAR 1994) Alternate I (MAR 1994) FAR 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short

Form) (APR 1984) FAR 52.249-10 Default (Fixed-Price Construction) (APR 1984) FAR 52.253-1 Computer Generated Forms (JAN 1991)

FAR 52.225-9 Buy American Act-Construction Materials (OCT 2022)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy-original-documents-signatures-notarization-seals-bonds-other-seals.pdf https://www.acquisition.gov/far/part-2#FAR_2_101

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.

However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.

https://www.acquisition.gov/far/part-25#FAR_25_105

Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners.

Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. Chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505

12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

_None____________________________________…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .