QuestionsAnswers9-5-2025.pdf
PDF 78 KB Posted
- Solicitation number
- 1240LU25Q0051
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Questions and Answers (Q&A) file for solicitation 1240LU25Q0051, specifically addressing lead-based paint removal and painting for a GAOA (likely Government-Owned/Agency-Operated) Cabin Building project. The Q&A, dated 9/5/2025, provides two key clarifications: first, the contractor must remove all lead-based paint completely (100%), not just loose and flaky paint; second, the contractor will be responsible for handling all hazardous materials associated with the lead paint removal process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J3_1240LU25Q0051Maps_Photos.pdf | ||
| J2_1240LU25Q0051WDStillwater.pdf | ||
| 1240LU25Q0051.pdf | ||
| J1_1240LU25Q0051WDSweetgrass.pdf | ||
| J4_1240LU25Q0051ExperienceQuestionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1240LU25Q0051
GAOA Cabin Building Lead Based Paint Removal & Painting
Questions and Answers
As of 9/5/2025
Q: Do we need to remove loose and flaky lead paint, or do we need to remove all lead paint complete 100%? A: Remove all lead-based paint.
Q: Who handles the hazardous material? A: Contractor