1240LU24Q0004 Attachment 4 FS Specifications Warms Spring Well Upgrade BNF.pdf
PDF 2 MB Posted
- Solicitation number
- 1240LU24Q0004
- Issued by
-
Department of Agriculture Forest Service
About this file
This document outlines technical specifications for a water system upgrade project on the Bitterroot National Forest in Montana. The project includes installing new 1-inch HDPE water lines, connecting to the existing water system, constructing a new well, installing a UV disinfection system and interior plumbing inside the pumphouse. The contractor will be responsible for site work, excavation, trenching and backfill, equipment installation and other related work. The specifications provide requirements for materials, testing, safety, traffic control and other execution details. The Forest Service will administer the contract and oversee construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BITTERROOT NATIONAL FOREST, MONTANA
TECHNICAL
SPECIFICATIONS
WARM SPRINGS
WELL UPGRADE
TECHNICAL SPECIFICATIONS
FOR THE
WARM SPRINGS WELL UPGRADE
FOR THE
BITTERROOT NATIONAL FOREST
HAMILTON, MONTANA
MARCH 2023
PREPARED BY:
BITTERROOT NATIONAL FOREST
ENGINEERING DEPT.
1801 N. 1ST Street
HAMILTON, MT 59840
TABLE OF CONTENTS
TECHNICAL SPECIFICATIONS
SECTION TITLE
DIVISION 1: GENERAL REQUIREMENTS
01010 SUMMARY OF WORK
01040 COORDINATION AND SITE CONDITIONS
01050 CONSTRUCTION STAKING
01150 MEASUREMENT AND PAYMENT
01300 SUBMITTALS
01400 QUALITY CONTROL AND QUALITY ASSURANCE
01500 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
01560 ENVIRONMENT QUALITY CONTROL
01570 TRAFFIC CONTROL
01600 PRODUCT SHIPMENT, HANDLING, PROTECTION, AND STORAGE .. 60
01700 CONTRACT CLOSEOUT
01720 RECORD DRAWINGS
DIVISION 2: SITE WORK
02015 MOVE IN AND SITE PREPARATION
02020 DEMOLITION AND SALVAGE
02030 CLEARING AND GRUBBING
02221 TRENCH EXCAVATION AND BACKFILL FOR PIPELINES AND
APPURTENANT STRUCTURES
02235 CRUSHED BASE COURSE
02480 FINISH GRADING AND SEEDING
02665 WATER DISTRIBUTION SYSTEM
DIVISION 3: CONCRETE
03410 PLANT-PRECAST STRUCTURAL CONCRETE
DIVISION 16: ELECTRICAL
16010 BASIC ELECTRICAL REQUIREMENTS
16028 CODES AND STANDARDS
16100 ELECTRICAL SYSTEM
16900 CATALOG SHEETS
DRAWINGS
G-1 Title
C-1 Existing Site Conditions
C-2 Demolition Plan
C-3 Site Plan
S-1 Pumphouse Plan
S-2 Pump House Plumbing Detail
D-1 Details
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01010
DIVISION 1 – GENERAL REQUIREMENTS SUMMARY OF WORK
SUMMARY OF WORK
PART 1: GENERAL
1.01 GENERAL
A. This section describes the project and the work to be performed in a general summary. Detailed requirements and extent of work are stated in applicable Specification sections and are shown on the Drawings.
1.02 ORGANIZATION AND INTERPRETATION OF DRAWINGS AND SPECIFICATIONS
A. Specifications and Drawings included in these Construction Documents establish the performance, quality requirements, location and general arrangement of materials and equipment, and establish the minimum standards for quality of workmanship and appearance.
B Specification sections have not been divided into groups for work of subcontractors or various trades. Should there be questions concerning the applicability or interpretation of a particular section or part of a section or Drawing, direct questions to the Contracting Officer (CO).
C. Piping shown on the Drawings is intended to be depictive and may not be an exact and complete representation of the actual finished work. Include fittings, joints, supports, nuts, bolts, and other accessories required to provide complete and satisfactory piping systems, as specified even though some items may not be specifically shown on the Drawings.
D. Any part of the work that is necessary or required to make each installation satisfactory and operable for its intended purpose, even though it is not specifically included in the Specifications or on the Drawings, shall be performed as incidental work as if it were described in the Specifications and shown on the Drawings.
1.03 WORK BY OTHERS
A. Seasonal campground operation may be present during project construction.
Also see Section 01040, COORDINATION AND SITE CONDITIONS.
1.04 DESCRIPTION OF PROJECT
A. This project generally consists of some or all of the following major items of work as further defined by the bid schedule:
1. Construction of new water distribution lines.
2. Construction of new well.
3. Installation of a UV disinfection system.
4. Installation of the interior plumbing inside pumphouse.
B. The work includes but is not limited to: furnishing and installation of equipment, materials and related appurtenances, and providing all labor in the following general trades of work: site work, excavation, trenching and backfill, piping, equipment installation and other related trades to complete the work.
1.05 LOCATION AND INSPECTION OF SITE
A. The project is located at the Warm Springs Campground, Bitterroot National Forest on Forest Development Road 370A off FDR 370, Warm Springs Laird Road, approximately 5 miles from Sula, Montana.
B. Prospective bidders are encouraged to visit the site and become familiar with existing conditions.
C. Inquiries concerning these Specifications and Drawings may be made to Justin Catanach, Civil Engineer, Bitterroot National Forest, 1801 N. First, Hamilton, MT 59840, 406-360-7170, or Shawn Boelman, Facilities Engineer, Bitterroot National Forest, 1801 N. First, Hamilton, MT 59840, 406-363-7107.
1.06 TIME FOR COMPLETION
A. Time for completion shall be as specified in the Bid Form and the Agreement.
1.07 BOUNDARIES OF WORK
A. The Government shall make suitable provisions for ingress and egress and shall not cause the Contractor to enter or occupy with workers, tools, equipment or material, any ground outside the property of the Government without the written consent of the owner of such ground. The final location and extent of the areas to be used shall be coordinated with the CO. Other contractors and employees or agents of the Government may for all necessary purposes enter upon the premise used by the Contractor, providing the operations of other contractors do not interfere with the actual scheduled operations. The Contractor shall conduct his work so as not to impede unnecessarily any work being done by others on or adjacent to the site.
B. It shall be understood that the responsibility for protection and safekeeping of equipment and materials on or near the site will be entirely that of the Contractor and that no claim shall be made against the Government by reason of any act of an employee or trespasser. It shall be further understood that should any occasion arise necessitating access by the Government to the sites occupied by these stored materials and equipment, the Contractor owning or responsible for the stored materials or equipment shall immediately remove same. No materials or equipment may be placed upon the property of the Government until the CO has agreed to the location contemplated by the Contractor to be used for storage.
C. The Contractor shall be solely responsible for obtaining and shall pay all costs in connection with any additional work area, storage sites, access to the site, or temporary right-of-way, which may be required for proper completion of the work.
1.08 PROTECTION OF SITE
A. Except as otherwise provided herein, the Contractor shall take all necessary precautions and provide all material and equipment to protect, shore, brace, support and maintain all public and private property in the proximity or otherwise affected by the construction work performed by him. The Contractor shall remove from the site all unused materials.
B. Contractor shall retain and protect all adjacent improvements not called for removal on the Drawings. Restore damaged items to pre-construction condition. The Contractor is responsible to protect from damage any structures near the trench excavation. Unless otherwise noted, Contractor shall retain and protect (at no additional cost) existing utility poles, culverts, signs, water wells, trees, fences, irrigation ditches, landscaping, and other facilities, features or improvements not specified for removal and outside of the limit of construction. Damage to existing improvements shall be repaired within 10 calendar days of the work in the immediate area.
Temporary restoration may be requested by the Government in critical situations.
C. All surfacing, landscaping, driveways, walks, buildings, utility poles and boxes, guy wires, fences and other surface or subsurface structures removed or damaged by construction operations, except for trees and shrubs in the public right-of-way, shall be restored to their original condition as determined and accepted by the CO. All replacements shall be made with new materials. All fences may not be shown on the project drawings.
D. The Contractor shall be responsible for all damage to streets, roads, highways, shoulders, ditches, embankments, culverts, bridges, and other public or private property, regardless of location or character, that may be caused by transporting equipment, materials or labor forces to or from the Work or any part or site thereof, whether by him or his subcontractor. If property is damaged, the Contractor shall make satisfactory and acceptable arrangements with the owner of, or the agency or authority having jurisdiction over, the damaged property concerning its repair or replacement or payment of costs incurred in connection with the damage.
1.09 TEMPORARY FACILITIES
A. The Contractor shall be responsible for supplying his own office, toilet and storage facilities at the site. The Contractor shall also be responsible for providing potable water and water needed for construction and testing purposes. All expenses for connection of electrical service, telephone or other temporary services shall be the responsibility of the Contractor. The Contractor shall remove all traces of these facilities prior to completion of the project.
1.10 SITE ACCESS
A. The Contractor shall be responsible for determining the adequacy of all roads and bridges used in moving equipment and materials to the construction site. The Contractor shall provide alternative methods of access, such as temporary crossings, for any equipment that exceeds the capacity of existing access facilities.
1.11 SAFETY
A. The Contractor shall be solely responsible for all project personnel on the jobsite and members of the public needing to travel through the jobsite. No acts or comments by the CO shall be interpreted as a transfer of responsibility for safety.
PART 2: PRODUCTS (Not Used)
PART 3: EXECUTION (Not Used)
END OF SECTION 01010
SECTION 01040
DIVISION 1 – GENERAL REQUIREMENTS COORDINATION AND SITE CONDITIONS
COORDINATION AND SITE CONDITIONS
PART 1: GENERAL
1.01 SECTION INCLUDES
A. Requirements for coordinating and sequencing the work under the Contract, and requirements regarding existing site conditions.
B. Requirements for cutting and patching of new and existing work.
1.02 JOBSITE COORDINATION
A. Coordination with Other Work: The project shall be coordinated with the following work and activities:
1. Public and agency use of the Warm Springs Campground.
2. Contractor shall maintain traffic on Forest Administrative roads at all times. Proper signage indicating construction in progress shall be provided by the contractor.
B. Government may perform additional work related to this project or
Government may let other direct contracts therefore which shall contain General Requirements similar to these. Contractor shall afford the other Contractors who are parties to such direct contracts, (or Government if they are performing the additional work), reasonable opportunity for the introduction and storage of materials and equipment and execution of work, and shall properly coordinate his work with theirs.
C. If any part of Contractor’s work depends on proper execution or results from the work of any such other Contractor (or Government), Contractor shall inspect and promptly report to CO in writing any defect or deficiencies in such work that renders it unsuitable for such proper execution or results.
His failure to so report shall constitute an acceptance of the other work as fit and proper for the execution of his work except as to defects and deficiencies that may appear in the other work after the execution of his work.
D. Contractor shall do all cutting, fitting, and patching of his work that may be required to make its several parts come together properly and fit it to receive or be received by such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their work with the written consent of the CO and of the other Contractors whose work will be affected.
E. If the performance of additional work by other Contractors or Government is not noted in the Contract Documents prior to the execution of the Contract, written notice thereof shall be given to Contractor prior to starting any such additional work. If Contractor believes that the performance of such additional work by Government or others involved results in additional expense or requires an extension of the contract time, Contractor may make a claim therefore.
F. Contractor shall be responsible for all areas of the site used by him and all Subcontractors in performance of the work. He shall exert full control over the actions of all employees and other persons with respect to the use and preservation of property and existing facilities, except such controls as may be specifically reserved to Government or others.
G. Contractor and all Subcontractors shall cooperate in the coordination of their separate activities in a manner that will provide the least interference with the Government’s operations and utility companies working in the area, and in the interfacing and connection of the separate elements of the overall project work. If any difficulty or dispute should arise in the accomplishment of the above, the problem shall be brought immediately to the attention of the Government. All Contractors working on this site are subject to this requirement for cooperation, and all shall abide by the CO’s decision in resolving project coordination problems without additional cost to the Government.
H. The Contractor shall have a designated job superintendent on site at all times during construction operations. The superintendent shall be capable of project level decisions, manpower authorization and equipment utilization.
1.03 SUBMITTALS
A. Contractor shall submit the following information as applicable to coordination activities:
1. Shop Drawings
a. Drawings detailing the design of any precast components provided for the project.
2. Safety Plan
a. A document detailing the step the Contractor will make to mitigate risk during the project.
1.04 SITE CONDITIONS
A. Information on Site Conditions:
1. General: Information obtained by the Government regarding site conditions, topography, subsurface information, groundwater elevations, existing construction of site facilities as applicable, and similar data is included in the Contract Documents or will be available for inspection at the office of the Government upon request. Such information is offered as supplementary information only. The Government assumes no responsibility for its accuracy or completeness or for the Contractor’s interpretation of such information.
2. Subsurface Information:
a. Contractor is cautioned that high seasonal groundwater is present at various locations at the project site during times of the year.
B. Existing Utilities:
1. Location:
a. Known utilities and facilities adjacent to or within the work area are shown on the Drawings. The locations shown are taken from existing records and the best information available from existing utility plans; however, it is expected that there may be some discrepancies and omissions in the locations and quantities shown. Contractor's request for additional compensation or Contract time resulting from encountering utilities not shown will not be considered as this work is considered incidental to the overall project work.
The Contractor is solely responsible for locating and avoiding conflicts with all existing utilities.
b. Contractor shall verify locations of utilities and facilities shown on the Drawings and to determine the presence of those not shown. Immediate and adjacent areas where excavations are to be made shall be thoroughly checked by visual examination for indications of underground facilities and also checked with electronic metal and pipe detection equipment. Where there is reasonable cause to verify the presence or absence of an underground facility, make exploratory excavations prior to proceeding with major excavation in the area. Where information on buried facilities is required to verify their nature, shape, configuration, dimensions, materials, or other properties, make exploratory excavations as required to ensure avoidance of conflicts and as acceptable to the CO.
c. The Contractor is advised that there is a 811 utility locate number in use for utility location requests within the State of Idaho for buried gas, electrical and telecommunication lines. The Montana 811 number is 1-800-424-5555 or 811.
Also see the Montana 811website at http://www.Montana811.org
d. Utilities located within the construction area or trenches shall be protected in-place. Any abandoned utility shall be confirmed abandoned by the CO and removed from the construction area by the Contractor.
2. Contractor’s Responsibilities:
a. Notify affected users, the CO, and emergency services of planned service outages a minimum of 48 hours in advance of planned outage. Provide details such as phone number of superintendent, date and times for outage.
b. Protect all utility poles from damage. If interfering utility poles will be encountered, notify the utility company at least 48 hours in advance of construction operations to permit necessary arrangements to protect or relocate the poles.
c. Contractor shall be solely and directly responsible to owner and operator of such properties for damage, injury, expense, loss, inconvenience, delay, suits, actions, or claims of any character brought because of injuries or damage that may result from construction operations under this Contract.
d. Neither Government nor its officers or agency shall be responsible to Contractor for damages as a result of
Contractor’s failure to protect utilities encountered in the
e. Maintain a legible log of all utility crossings showing type, depth, date of crossing. Location referenced to project stationing, and a notation if the utility was damaged, type of repair, and who made the repair. The Contractor will work with CO to maintain an accurate and complete log that will become part of the as-constructed contract drawings.
C. Interfering Structures:
1. Take necessary precautions to prevent damage to existing structures whether on the surface, above ground or underground.
2. Protect existing structures from damage, whether or not they lie within limits of easements obtained by the Government. Where existing fences, gates, sheds, buildings or other structures must be removed to properly carry out the work, or are damaged during work, restore them to original condition and to the satisfaction of property owner.
3. Contractor may remove and replace in equal or better than original condition, small structures such as fences, or signposts that interfere with Contractor’s operations. Contractor shall obtain permission from the small structure owner prior to removal and replacement.
D. Monuments and Markers:
1. Preserve and protect survey monuments and markers throughout construction. If damage occurs or removal becomes necessary, notify CO.
2. Preserve private and public monuments that are found. If monument must be removed, it shall be replaced at its original location using a registered land surveyor. Notify CO when monuments are encountered. If government monuments are encountered, reference the monument for future replacement and provide 10-day advance notification to CO who will notify the proper authority.
E. Connecting to Existing Facilities: Unless otherwise shown or specified, determine methods of connecting new work to existing facilities, and obtain CO’s review and acceptance of connections.
1. Determine location, elevation, nature, materials, dimensions, and configurations of existing facilities where necessary for connecting new work.
2. Inspect existing record drawings and shop drawings, conduct exploratory excavations and field inspections, and conduct similar activities as needed.
F. Erosion and Dust Control On-Site:
1. The Contractor shall be responsible for reducing soil erosion and dust due to wind or water to a level meeting federal, state, and local regulations at the construction site. Control measures that may be required include, but may not be necessarily limited to, the following:
a. Suspension of excavation during high wind or rain.
b. Minimization of land exposure in area and time.
c. Covering erodible areas as quickly as possible with gravel or by compaction.
d. Stabilizing construction site soils.
e. Controlling dust during construction by use of water spray.
f. On-site burning of waste materials is not allowed.
1.05 PROJECT MEETING OR REPORTS
A. Pre-construction Conference: A pre-construction conference will be scheduled after the Notice of Award.
B. Progress Meetings: Regular progress meetings will be held to review work progress, schedules, and other matters needing discussion and resolution.
C. Purpose of Meetings and Reports: The purpose of the meetings or reports will be to review the progress of work, maintain coordination of efforts, discuss changes in scheduling, and resolve other problems that may develop. At a minimum, each meeting must be attended by the Contractor’s project manager or field superintendent.
1.06 SCHEDULING OF WORK
A. Modifications to Existing Facilities:
1. Connections to existing service or utilities, or other work that requires the temporary shutdown of any existing operations of utilities shall be planned in detail with appropriate scheduling of the work and coordinated with the CO. The schedule for shutdown or restart shall be given by written advance notice at least 15 days prior to the scheduled work in order that the CO may witness the shutdown, tie in, and startup.
2. All materials and equipment, including emergency equipment, necessary to expedite tie-ins shall be on hand prior to the shutdown of existing services or utilities.
3. Unless otherwise specified or indicated, Contractor shall make all necessary connections to existing facilities including manholes, structures, pipelines, and utilities. In each case, Contractor shall obtain permission from the CO or the owning utility prior to undertaking connections. Contractors shall protect facilities against deleterious substances and damage.
4. Connections to existing facilities that are in service shall be thoroughly planned in advance, and all required equipment, materials, and labor shall be on hand at the time of undertaking the connections. All equipment, materials, and labor that the Contractor plans to have available shall be coordinated with the CO in order to ensure the work is done in the minimum amount of time.
B. Time of Work:
1. No work shall be done between 7:00 p.m. and 6:00 a.m., nor on
Saturdays, Sundays or legal holidays, without the written permission of the CO. However, maintenance or emergency work during these hours may be done without prior permission.
2. The CO will provide for periodic onsite observation by a USFS representative whenever pipe or other items of work are being buried or otherwise concealed.
PART 2: PRODUCTS (Not Used)
PART 3: EXECUTION
3.01 CUTTING AND PATCHING
A. General:
1. Execute cutting (including excavating), fitting, or patching of work, required to:
a. Make the several parts fit properly.
b. Uncover work to provide for installation of specified work.
c. Remove and replace defective work or work not conforming to requirements of Contract Documents.
d. Install specified work in existing construction.
2. Perform the following upon written instruction of CO:
a. Uncover work to provide for CO’s observation of covered
b. Remove work to provide for alteration of existing work.
3. Contractor shall not, without written consent of CO:
a. Cut or alter work of another Contractor.
b. Cut structural or reinforcing steel.
c. Endanger existing or new structures or facilities.
d. Shut down or disrupt existing operations.
4. Materials for replacement of work removed shall comply with applicable sections of these Specifications for corresponding type of work to be done.
5. Provide all tools and equipment required to accomplish cutting and patching.
B. Inspection and Preparation:
1. Inspect existing conditions of work, including elements subject to movement or damage during cutting, patching, excavating, and backfilling.
2. After uncovering work, inspect conditions affecting installation of new products.
3. Prior to cutting, provide safety protection.
C. Procedures:
1. Execute fitting and adjustment of products to provide finished installation to comply with specified tolerances and finishes.
2. Execute excavating and backfilling as specified in Section 02221, TRENCH EXCAVATION AND BACKFILL.
3. Restore work that has been cut or removed; install new products and provide completed work in accordance with specified requirements.
4. Restore structures and surfaces damaged that are to remain in the completed work including piping, conduit, and other utilities.
5. Make restorations with new materials and appropriate methods as specified for new work of similar nature; if not specified, use best recommended practice of manufacturer or appropriate trade association.
6. Restore damaged work so there is a secure and intimate bond or fastening between new and old work. Finish restored surfaces to such planes, shapes, and textures that no transition between new and old work is evident in finished surfaces.
3.02 TELEPHONE AND/OR ELECTRICAL CROSSINGS
A. It is the responsibility of the Contractor to review buried and overhead utility conflicts that may affect the Work. All costs associated with the construction and these utilities shall be the responsibility of the Contractor.
All work near buried telephone and/or electrical cables shall be coordinated with the utility provider. The Contractor shall protect these utilities and will not cut them. The telephone and electric companies also utilize an overhead distribution system within the project area. It is the Contractor’s responsibility to field review the magnitude of any construction conflict
(crossings or pole support) created by the overhead utility conflicts.
Contractor shall coordinate with the utility companies to ensure pole relocations are completed so as not to delay the Work.
B. Power poles that are exposed to trenching will be supported by the Contractor at the Contractor’s expense. The utility company must accept the Contractor’s equipment and methods of stabilizing the power poles. The utility company must be contacted a minimum of 48 hours prior to stabilizing a power pole.
3.03 REMOVAL/RELOCATION/REPLACEMENT OF EXTRANEOUS ITEMS
A. Contractor shall be responsible to relocate, remove or replace signs, culverts, power poles, telephone poles and any other items in conflict with construction. Contractor shall notify owner or utility company of such items prior to construction and shall coordinate with owner as to methodology required. Unless a specific bid item is identified and the removal is accepted by the CO, the cost for this work will be considered incidental to all other items.
END OF SECTION 01040
SECTION 01050
DIVISION 1 – GENERAL REQUIREMENTS CONSTRUCTION STAKING
CONSTRUCTION STAKING
A. Requirements for furnishing qualified personnel and necessary equipment and material to survey, stake, calculate and record data for the control of
1.02 RELATED SECTIONS
A. See FAR Clause 52.236-17 Layout of Work for additional requirements.
1.03 GENERAL
A. Include staking activities in the construction schedule.
B. Preserve all initial reference and control points. After beginning construction, replace all destroyed or disturbed initial reference or control points necessary to the work.
C. Prior to surveying or staking, discuss and coordinate the following with the
CO:
1. Surveying and staking methods;
2. Stake marking;
3. Grade control for courses of material;
4. Referencing;
5. Structure control; and,
6. Any other procedures and controls necessary for the work.
D. Prepare field notes in an approved format. Furnish all survey notes to the
CO weekly. All field notes and supporting documentation become the property of the Government upon completion of the work.
E. Remove and dispose of all flagging, lath, stakes, and other staking material after the project is complete.
1.04 PERSONNEL, EQUIPMENT AND MATERIAL
A. Furnish technically qualified survey crews experienced in construction survey and staking. Provide personnel capable of performing in a timely and accurate manner. An acceptable crew supervisor shall be on the project whenever surveying/staking is in progress.
B. Furnish survey instruments and supporting equipment capable of achieving the specified tolerances.
C. Furnish acceptable tools, supplies, and stakes of the type and quality normally used in highway survey work and suitable for the intended use.
Furnish stakes and hubs of sufficient length to provide a solid set in the ground with sufficient surface area above ground for necessary legible markings.
3.01 GENERAL
A. Perform all survey, staking, recording of data, and calculations as necessary to construct the project from the initial layout to final completion. Reset stakes as many times as necessary to construct the work.
3.02 WORK ELEMENTS
A. Control points. Relocate initial horizontal and vertical control points in conflict with construction to areas that will not be disturbed by construction operations. Furnish the coordinates and elevations for the relocated points before the initial points are disturbed.
B. Slope stakes and references. Set slope stakes and references on both sides of centerline at the cross-section locations. Establish slope stakes in the field as the actual point of intersection of the design slope with the natural ground line. Set slope stake references outside the clearing limits. Include all reference point and slope stake information on the reference stakes. When initial references are provided, slope stakes may be set from these points with verification of the slope stake location with field measurements. Set additional references even when initial references are provided.
C. Clearing and grubbing limits. Set clearing and grubbing limits on both sides of centerline along pipeline alignments and building or well pump pads.
D. Grade finishing stakes. Set grade finishing stakes, for grade elevations and horizontal alignment. Set stakes at the top of subgrade and the top of each aggregate course. Stakes shall be set in a grid pattern with maximum spacing of 20 feet.
3.03 STAKING TOLERANCES
A. The following table lists the applicable tolerances for field staking for various phases of the work.
Staking Phase Horizontal Vertical
Existing Government network control points ±0.06 ft ±0.035 ft ×√M Local supplemental control points set from existing Government network points
±0.03 ft ±0.01 ft ×√N
Clearing and grubbing limits ±2.00 ft NA Slope stake references ±0.16 ft ±0.16 ft Centerline points – PC, PT, POT and POC ±0.03 ft ±0.03 ft Minor drainage structures ±0.16 ft ±0.06 ft Subgrade finish stakes ±0.16 ft ±0.03 ft Finish Grade Stakes ±0.16 ft ±0.03 ft
Where: M is the distance in miles and N is the number of instrument setups.
END OF SECTION 01050
SECTION 01150
DIVISION 1 – GENERAL REQUIREMENTS MEASUREMENT AND PAYMENT
MEASUREMENT AND PAYMENT
A. This section provides bid item descriptions and specifies the method of measurement and basis of payment for work covered by the Contract Documents.
1.02 GENERAL
A. The bid price for each item of the Contract shall cover all work shown on the Drawings and required by the specifications and other Contract Documents. All costs in connection with the work, including furnishing all materials, equipment, supplies and appurtenances; providing all required construction support plants, equipment, and tools; and performing all necessary labor and supervision to fully complete the work, shall be included in the unit and/or lump sum prices bid in the Bid Form Schedule.
The amounts shown on the Bid Form Schedule shall be the contract price.
B. No item that is required by the Contract Documents for the proper and successful completion of the work will be paid for outside of or in addition to the prices submitted in the bid. All work not specifically set forth as a pay item in the Bid Form shall be considered a subsidiary obligation of the Contractor and all costs in connection therewith shall be included in the prices bid.
1.03 ESTIMATED QUANTITIES
A. All estimated quantities stipulated in the Bid Form or other Contract Documents are approximate and are to be used (1) only as a basis for estimating the probable cost of the work and (2) for the purpose of comparing the bids submitted for the work.
B. The actual amount of work done and materials furnished under unit price items may differ from the estimated quantities. The basis of payment for work and materials will be the actual amount of work done and materials furnished to the pay-lines defined in this section. The Contractor agrees that he will make no claim for damages, anticipated profits, or otherwise on account of any difference between the amount of work actually performed and materials actually furnished and the estimated amounts herein except as allowed in the Contract Conditions.
1.04 SURVEYS AND MEASUREMENTS
A. All quantity measurements shall be the responsibility of the Contractor and will be checked by the CO. When considered necessary by CO, Contractor shall demonstrate how quantity measurements were determined.
1.05 METHOD OF MEASUREMENT
A. Measurement of unit price items contained in the Contract will be made in the field by the Contractor and will be verified by the CO.
1.06 BASIS OF PAYMENT
A. The bid for the work in this Contract is a lump sum bid for all construction activities and materials required to complete the work described in the Contract Documents. Payment for the items shall include all labor, materials, equipment, and incidentals required to complete the item. The work included in each item is more completely described below.
B. Lump sum bid items will be paid on a periodic basis in an amount equal to the percentage of the total work deemed complete by the CO.
Item Description
101 Mobilization/Demobilization, Bonding, Insurance, General Requirements.
Item includes moving equipment and other necessary work items to and from the project site. Payment will be made at the lump sum contract unit price for this item.
Contractor may request payment for performance and payment bonds. The amount of the premium, including coinsurance and reinsurance agreements, will be paid upon receipt of evidence of full payment to the surety. When separate payment for boding cost is made, the bonding cost will be subtracted from the total contract amount for this pay item and the balance paid in accordance with the progress payment schedule outlined below:
(a) When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.
(b) When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less will be paid.
(c) Upon completion of all work on the project, any unpaid amount for mobilization will be paid.
102 Concrete Pad Demolition. Payment will be made at the lump sum contract price for this item. Item includes all labor, equipment, and materials necessary for structure removal, and other clearing necessary for installation of the new well, pump and site improvements.
201 1 ½” IPS DR 11 HDPE 3408 Water Line. Payment will be made at the contract price per linear foot for installed and accepted 1 ½ - inch water line. Item includes all labor, equipment and materials necessary to furnish and install 1 ½ -inch water line, including excavation, trench dewatering, soil stabilization, Type 1 bedding material, pipe joining and installation, backfill, compaction, pipe locating wire and marker tape. Measurement will be made through valves and fittings.
202 Well Decommissioning. Payment will be made at the lump sum contract price for this item. Item includes all labor, equipment and materials necessary to decommission the existing well inside the pumphouse.
203 Connect to Existing Water System: Payment will be at the lump sum contract price for this item. The work shall include all labor, materials and equipment required to complete installation, including, but not limited excavation, connecting to water lines, installing a pitless adapter, connecting to pumphouse, bedding material, crushed rock, backfill, compaction, and pipe marker tape.
Note: All cleanup, electricity, temporary access, construction water, restoration of surfaces beyond pay limits or restoration at areas outside the construction zone damaged by this construction and required to be restored, discharge and other permits not identified as a bid item, and any other items not shown as a pay item are considered subsidiary to the pay items shown and as such receive no direct payment.
PART 2: PRODUCTS (Not Used) PART 3: EXECUTION (Not Used)
END OF SECTION 01150
SECTION 01300
DIVISION 1 – GENERAL REQUIREMENTS SUBMITTALS
SUBMITTALS
PART 1: GENERAL
1.01 SECTION INCLUDES
A. Submittal procedures.
B. Construction progress schedules.
C. Proposed products list.
D. Shop drawings.
E. As-Built Drawings
F. Product data.
G. Manufacturers' instructions.
H. Manufacturers' certificates.
1.02 RELATED SECTIONS
A. Section 01400 - QUALITY CONTROL: Manufacturers' field services and reports.
B. Section 01700 - CONTRACT CLOSEOUT: Contract closeout submittals.
1.03 SUBMITTAL PROCEDURES
A. The Contractor shall submit to Government a submittal schedule with his proposed submittal dates for all equipment and materials for which a submittal is required. The completed schedule shall be submitted to Government by the Contractor within ten (10) working days after the date of the Notice of Award.
B. General Procedures:
1. Procedures and requirements for submittals are specified herein.
CO reserves the right to modify the procedures and requirements for submittals, as necessary to accomplish the specific purpose of each submittal. Direct all inquiries to CO regarding the procedure, purpose, or extent of any submittal.
2. Review, acceptance, or approval of substitutions, schedules, shop drawings, lists of materials, and procedures submitted or requested by Contractor shall not add to the Contract amount, and additional costs which may result therefrom shall be solely the obligation of Contractor. Where Contractor suggests use of a substitution, he must demonstrate why the substitution is in the Government’s best interest and pay all associated costs for re-engineering, as required.
3. Government is not precluded, by virtue of review, acceptance, or approval, from obtaining a credit for construction savings resulting from allowed concessions in the work or materials therefore.
4. Government is not responsible to provide Engineering or other services to protect Contractor from additional costs accruing from submittals.
5. Submittals processed by Government do not become Contract Documents and are not Change Orders; the purpose of submittal review is to establish a reporting procedure and is intended for Contractor's convenience in organizing the work and to permit Government to monitor Contractor's progress and understanding of the design.
6. Submittals will be acted on by Government as promptly as possible and returned to the Contractor not later than the time allowed for review in Paragraph 1.03C, SPECIFIC SUBMITTAL PROCEDURES. Delays caused by the need for resubmittal shall not constitute basis for claim or for an extension of contract time.
7. After checking and verifying all field measurements, make submittals to Government, in accordance with the submittal register for review.
a. Submittals shall bear a stamp or specific written indication that Contractor has satisfied its responsibilities under the Contract Documents with respect to the review of the submittal.
b. Data shown shall be complete with respect to quantities, dimensions, specified performance and redesign criteria, materials, and similar data to enable Government to review the information.
c. Submitted data shall be fully sufficient in detail for determination of compliance with the Contract Documents.
8. Before submission of each submittal, determine and verify quantities, dimensions, specified performance criteria, installation requirements, materials, catalog numbers, and similar data with respect thereto; review and coordinate each submittal with other submittals, requirements of the work, and Contract Documents.
9. At the time of each submission, provide mark-ups of the technical specification indicating each variation that the submittal may have from the requirements of the Contract Documents; if variations are not listed, it is assumed that the submitted equipment meets the specification; in addition, make specific notation on each shop drawing submitted to Government for review and approval of each such variation.
10. Government 's review will be only for conformance with the design concept of the project and for compliance with the information given in the Contract Documents, not extending to means, methods, techniques, sequences, or procedures of construction (except where a specific means, method, technique, sequence, or procedure of construction is indicated in or required by the Contract Documents) nor to safety precautions or programs incident thereto. The review of a separate item as such will not indicate review of the assembly in which the item functions.
11. Government's review of submittals shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has in writing called Government 's attention to each such variation at the time of submission, and Government has given written approval of each such variation by a specific written notation thereof incorporated in or accompanying the shop drawing or sample approval; nor will any approval by Government relieve Contractor from responsibility for errors or omissions in the shop drawings or from responsibility for having complied with the provisions therein.
12. Where a shop drawing or sample is required by the Specifications, related work performed prior to Government 's review and approval of the pertinent submission shall be the sole expense and responsibility of Contractor.
13. Should the Contractor propose any item on his shop drawings, or incorporate an item into the work, and that item should subsequently prove to be defective or otherwise unsatisfactory, (regardless of Government 's preliminary review), the Contractor shall, at his own expense, replace the item with another item that will perform satisfactorily.
14. Review of first submittal and second resubmittals will be performed by Government at no cost to the Contractor.
Subsequent submittals will be reviewed by Government; however, Government will document the work-hours and other expenses required for such review(s) and the Contractor shall reimburse Government for the effort with a deduction from the Contractor's monthly pay estimate.
C. SPECIFIC SUBMITTAL PROCEDURES
1. The Contractor shall submit an electronic submittal plan to Government for their approval.
a. Provide general submittal information with each PDF submittal, including project, subject, submittal number, submittal date, supplier, and keywords.
b. For large shop drawing files greater than 5MB, submittals should be made to an FTP site.
c. Review comments and resubmittals are to be provided electronically, after which a minimum of two hard copies of the final and approved shop drawings are submitted for distribution. Distribution would be to the CO.
d. Submittals shall be an electronic file in Adobe Acrobat
Portable Document File (PDF) format created directly to PDF (preferred) or via scans of the hard copy. Scans must be legible.
e. Electronic files that contain more than 10 pages in PDF format shall contain internal bookmarks linked from an index page to major sections of the document.
f. PDF files shall be set up to print legibly at 8.5-inch by 11-inch or 11-inch by 17-inch. No other paper sizes will be accepted.
g. New electronic files shall be submitted for each resubmittal, i.e., resubmit entire submittal when individual pages or portions thereof are modified.
2. Combine submittals specified in each Specification section into a single package. Partial packages will not be reviewed until all submittals required for the section have been received. These shop drawings shall be accurate, distinct, and complete, and shall contain all required information, including satisfactory identification of items, units, and assemblies in relation to the Contract Drawings and Specifications.
3. Transmit each submittal with a Government accepted form.
4. Sequentially number the transmittal forms. Resubmittals to have original number with an alphabetic suffix.
5. Identify project, Contractor, subcontractor or supplier; pertinent
Drawing sheet and detail number(s), and Specification section number, as appropriate.
6. Apply Contractor's stamp, signed or initialed certifying that review, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.
7. Deliver hard copies of approved submittals to the CO.
8. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of the completed work.
9. Provide space for Contractor and Government review stamps.
10. Revise and resubmit submittals as required, identify all changes made since previous submittal.
11. Distribute copies of reviewed submittals to concerned parties.
Instruct parties to promptly report any inability to comply with provisions.
12. Submittals will be acted upon by Government and transmitted to
Contractor not later than 20 regular working days after receipt by Government. Shop drawings shall be submitted in sufficient time to allow Government not less than 20 regular working days for examining the shop drawings.
1.04 CONSTRUCTION PROGRESS SCHEDULES
A. Submit initial progress schedule in duplicate within 15 days after date of Government's Notice of Award for Government 's review.
B. Submit revised schedules with each Application for Payment, identifying changes since previous version.
C. Submit a chart with separate line for each major section of work or operation, identifying first work day of each week.
D. Show complete sequence of construction by activity, identifying work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, critical path, and duration.
E. Indicate estimated percentage of completion for each item of work at each submission.
F. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates.
1.05 PROPOSED PRODUCTS LIST
A. Within 7 days after date of Government’s Notice of Award, submit complete list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.
B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.
C. Should the Contractor elect to propose use of a substitute equipment or material, which is not listed in the specification as an "equal" and cannot be considered an equal because it does not meet the specifications, Contractor must submit adequate documentation allowing Government to determine the equivalency of the material. Contractor shall pay Government for costs incurred in reviewing the proposed substitution.
1.06 SUBSTITUTIONS
A. Where items of equipment and materials are identified herein by a manufacturer’s name, model, or catalog number followed by the words “or approved equal,” Contractor must obtain Government’s approval for using a non-listed piece of equipment or material.
C. Note that use of an “or equal” item must not increase the cost to the Government or increase contract times.
D. If using a “substitute,” note that Contractor will be responsible for any costs resulting from a change in Contract Documents, design change, Government’s review and evaluation.
1.07 SHOP DRAWINGS
1. The Contractor shall submit shop drawings, equipment and materials data as required in the Technical Provisions of these specifications concerning the specific item as soon as practical. The Contractor may proceed, only at his own risk, with manufacture or installation of any equipment or work covered by said drawings, etc.
until they are approved, and no claim, by the Contractor, for extension of the contract time will be granted by reason of his failure in this respect.
2. Shop drawings, as defined herein, consist of all drawings, diagrams, illustrations, schedules, and other data which are specifically prepared by or for Contractor to illustrate some portion of the work;
and all illustrations, brochures, standard schedules, performance charts, instructions, diagrams, and other information prepared by a manufacturer and submitted by Contractor to illustrate material or equipment for distinct portions of the work.
3. Submittal of incomplete or unchecked shop drawings will not be acceptable. Shop drawing submittals which do not clearly show Contractor's review stamp or specific written indication of Contractor review will be returned to Contractor for resubmission.
4. Submittal of shop drawings not required under these Contract Documents and not shown on the Submittal Register will be returned to the Contractor unreviewed and unstamped by Government.
B. Stamp of Approval: All drawings, equipment, materials, and other submitted data shall be carefully reviewed by an authorized representative of the Contractor prior to submission to Government. Each submittal shall be dated, signed, and certified by the Contractor, as being correct and in strict conformance with the Contract Documents. No consideration for review by Government of any Contractor submittals will be made for any items which have not been so certified by the Contractor. All non-certified submittals will be returned to the Contractor without action taken by
Government, and any delays…
This is the start of the file's text. The full file is on GovTribe.