This is a Statement of Work (SOW) for a federal construction contract to build barbwire fencing near Kalamazoo Campground on the Ely Ranger District in Nevada.
The project involves constructing approximately 0.5 miles (2,500 feet) of new barbwire drift fences to exclude active grazing within Kalamazoo Campground, addressing livestock safety hazards and public complaints. The work includes installation of an estimated four 12-foot wire gates as a lump sum. All brace and anchor posts must be schedule-40 galvanized steel except for wood posts at wire gates. Fences will end at natural rock barriers, with a potential rock crib brace required at the northeast end, and fence wings will tie into existing cattleguards along Forest Service Road 427. Vegetation clearing is permitted using chainsaws or handsaws to maintain a straight fence line with no more than 12-inch deviation between braces. A clear corridor of 8 feet total width (4 feet on each side of centerline) and 8 feet above ground must be established, with slash scattered outside the corridor. Off-road vehicles may be authorized for post and supply transport with Contracting Officer Representative (COR) approval. Heavy equipment is prohibited for clearing. Work must comply with FP-24 Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects and Forest Service Supplement. The contract is estimated to start Summer 2027 with a Notice to Proceed issued for work to commence within 10 days. The base contract time is 90 calendar days from Notice to Proceed. The project location is approximately 80 minutes from Ely, Nevada, in White Pine County within Spring Valley adjacent to the High Schells Wilderness Area.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C04d WD NV20260067 dtd 7-30-2026 1240LT27Q0025.pdf | ||
| C04f Performance Data Sheet 1240LT27Q0025.docx | DOCX document | |
| C04 SF1442 - 1240LT27Q0025 - Combined SS.pdf | ||
| C04a Schedule of Items 1240LT27Q0025.xlsx | XLSX spreadsheet | |
| C04e Experience Questionnaire 1240LT27Q0025.docx | DOCX document | |
| C04c Maps-Drawings - KzooFenceRevkwsigned 1240LT27Q0025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
Kalamazoo Fence
1.1 SCOPE OF CONTRACT
A. The intent of this project is to construct approximately 0.5 miles of barbwire fence lines near Kalamazoo Campground on the Ely Ranger District.
B. Kalamazoo: The intent of this project is to construct two barbwire drift fences totaling approximately 0.5 miles in length to exclude active grazing within Kalamazoo Campground. Livestock in the campground presents a safety hazard and has resulted in numerous complaints from the public. In addition, limiting livestock activities within the campground will also extend protection of newly installed recreational infrastructure.
This project includes construction of approximately 2,500 feet of new barbwire fence including installation of an estimated four 12-foot wire gates as a lump sum.
All brace and anchor posts are to be schedule-40, galvanized steel except for wood posts located at the wire gates. Fences will end at natural rock barriers; a rock crib brace may be required at the northeast end. Fence wings will tie into existing cattleguards along FS Road 427.
C. Kalamazoo: Clearing of vegetation is allowed as needed to ensure a straight fence, however heavy equipment will not be allowed to clear the fence lines. Chainsaws are allowed for vegetation clearing. Fence runs should not deviate more than 12-inches from a straight line between braces. Clear corridor to 8 ft total width (approx. 4 ft on each side of fence centerline) and 8 ft above ground. Slash generated from clearing shall be scattered outside the corridor; do not leave in ditches or roadways.
D. Off Road Vehicles may be authorized to transport posts and supplies outside the fence right of way; confirm with COR and Inspector for site specific protection needs.
E. Work shall be performed in accordance with specifications and drawings in the plan sheets, followed by the ‘Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24).’
1.2 PROJECT LOCATION
A. Kalamazoo: From Ely, NV travel south along US-50 for 28 miles. Turn north on State
Route 893 for 40 miles until you reach National Forest Road 427 (Kalamazoo Road).
Turn right and travel approximately 2 miles east to arrive at Kalamazoo Campground.
Total drivetime is about 80 minutes from Ely, NV. The Kalamazoo Campground is a small rural campground in White Pine County located within Spring Valley and adjacent to the High Schells Wilderness Area.
1.3 SITE INFORMATION AND LIMITATIONS
A. Roads in the Project Area must remain open.
B. Crews are permitted to camp in the area, however campsites must be approved by the
District Ranger. Campsites must have porta-potties or other approved toilet facilities.
C. Utilities are not available at the site for construction purposes.
D. Vegetation clearing in the Project Area may be done using chainsaws or handsaws.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Do not measure controlling and protecting public traffic for payment. Payment for such work is indirectly included under other pay items listed in the bid schedule.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the COR.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.7 ESTIMATED START DATE:
A. Summer 2027
B. A Notice to Proceed will be issued with work started within 10 days.
1.8 CONTRACT TIME
A. Base Bid: 90 Calendar Days from Notice To Proceed.
1.9 SPECIFICATIONS
A. FP-24 Standard Specifications for Construction of Roads and Bridges on Federal
Highway Projects and Forest Service Supplement
1. Copies are available electronically on the U.S. DEPARTMENT OF TRANSPORTATION Federal Highways Administration website at https://highways.dot.gov/federal-lands/specs/fp-24
END OF SECTION C