This is a Questions and Answers document for federal contract opportunity 1240LT26Q0097 addressing the Driggs and Dubois Siding Replacement project. The document clarifies contract scope and specifications for bidders considering this opportunity.
The project requires siding replacement at both the Driggs and Dubois locations and cannot be bid for a single location. Fiber cement siding with integral factory finish is specified, and all bids must include fully-finished, painted products. For Dubois, contractors must submit white siding samples for approval; for Driggs, log wood color samples require approval by the Contracting Officer after award. Post wraps are excluded from the contract scope. Soffit and fascia work is limited to the Driggs Bunkhouse only as shown in contract drawings. Paint application may be completed by spray or roller. End vents may be eliminated on Dubois units due to ridge vent roof replacements, but existing end vents must be retained for Driggs and Dubois Bunkhouse units. A radon system at the Driggs location requires coordination with the Contracting Officer/Contracting Officer's Representative to de-energize the fan system before work begins; the radon vent must be detached during demolition and reattached after siding installation. Payment follows FAR 52.232-16 Progress Payments, with the government making progress payments monthly in amounts of $2,500 or more as approved by the Contracting Officer. Subcontracting is permitted as prescribed in the solicitation. A local dump is available for waste disposal. Award decisions will be made according to solicitation criteria with appropriate notices issued as diligently as possible.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1240LT26Q0097 Driggs and Dubois Siding Replacement Questions & Answers
1. Question: Is there a local dump?
Answer: Yes
2. Question: Are Post wraps included in the contract?
Answer: No
3. Question: Can we Eliminate End vents on Units with vented siding?
Answer: Yes, for Dubois units because roofs will be replaced with ridge vent. For Driggs and Dubois Bunkhouse-use existing end vents.
4. Question: Is Soffit and Fascia included in the contract?
Answer: Only for Driggs Bunkhouse as shown in the drawings.
5. Question: Can we spray paint or is rolling required?
Answer: Paint may be applied by spray or roller.
6. Are there any special qualifications or considerations to be taken for what appears to be a Radon system at the Driggs location? There is a stack attached to the existing siding.
Answer: Coordinate with CO/COR to de-energize fan system prior to starting work. Detach radon vent during demolition and retain. Reattach after siding is installed
7. Fiber cement siding is spec’d — I did not see anything regarding refinished siding or paint. Are all bids required to include a fully painted product?
Answer: All bids should include the fully-finished product.
8. How does the payment schedule work for this project? Do the terms allow for a standard deposit?
Answer: Payment schedule for this project will be in accordance with FAR 52.232-16 Progress Payments - The Government will make progress payments to the Contractor when requested as work progresses, but not more frequently than monthly, in amounts of $2,500 or more approved by the Contracting Officer, under the following conditions:
Visit https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part- 52#FAR_52_232_16 for more information
9. What is the timeline on a decision for this?
https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52#FAR_52_232_16 https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52#FAR_52_232_16
1240LT26Q0097 Driggs and Dubois Siding Replacement Questions & Answers
Answer: Award decision will be made in accordance with solicitation criteria and all applicable rules and regulations. The government plans to issue an award and appropriate notices as diligently as possible.
10. The solicitation says primed fiber cement board, there is nothing about paint. Is there a separate solicitation for painting this project? Have colors been established?
Answer: Color for Dubis is white siding, contractor to submit samples upon award for approval
- Color for Driggs will be a log wood color, contractor to submit samples upon award for approval
-Utilize an Integral Factory Finish. Refer to the manufacturer’s Exterior Finish Schedule.
Color to be approved by the CO after award.
11. Can we just bid the fiber cement project in Driggs?
Answer: No. Project must be for both locations.
12. Can we use a subcontractor for a portion of the project?
Answer: Yes, subcontracting is allowed as prescribed in the solicitation.