1240LT26Q0006.0001 - Sunbeam Dam Stairs.pdf
PDF 88 KB Posted
- Attached to
- Sunbeam Dam Stairs
- Solicitation number
- 1240LT26Q0006
- Issued by
-
Department of Agriculture Forest Service
About this file
Amendment of Solicitation/Modification of Contract
This is Amendment 0001 to solicitation 1240LT26Q0006, issued by USDA-FS CSA Intermountain 8 (Ogden, UT) on February 6, 2026. The amendment extends the offer due date from March 6, 2026 at 1600 MST to March 20, 2026 at 1600 MST to allow additional time for proposal submission. No other changes are made to the solicitation. Contracting Officer Brian J. Wharton signed the amendment.
The underlying solicitation concerns the Sunbeam Dam Stairs project in the Sawtooth National Recreation Area of the Sawtooth National Forest, Custer County, Idaho. The project removes and replaces a large set of timber stairs at the Sunbeam Dam Interpretive Site, located approximately 13 miles east of Stanley, Idaho, accessed via State Highway 75. The site is open to the public and no pre-proposal site visit is scheduled. Questions are due February 27, 2026 by 1600 MST, and proposals must be submitted electronically to Westley.Bisson@usda.gov with reference 1240LT26Q0006 in the subject line. The period of performance runs from July 6, 2026 through October 16, 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240LT26Q0006
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40LT
OGDEN UT 84401-2310
324 25TH ST
USDA-FS CSA INTERMOUNTAIN 8
GAOA02/06/20260001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/06/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 0001 - The purpose of this amendment is to extend the offer due date from
03/06/2026 through 03/20/2026 @ 1600 (MST) to allow additional time for proposal submission. There are no other changes.
Project Name: Sunbeam Dam Stairs
Project Description: This project removes and replaces a large set of timber stairs at the
Sunbeam Dam Interpretive Site in the Sawtooth National Recreation Area.
Project Location: The project is located in the Sawtooth National Recreation Area of the
Sawtooth National Forest, Custer County, Idaho, in Section 20, T11N, R15E. It is located
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
BRIAN J. WHARTON
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
1240LT26Q0006/0001
approximately 13 miles east of Stanley, Idaho.
The project site is accessed from State Highway
75.
Pre-Proposal Site Visit Scheduled? No. Site open to the public.
Questions Due: February 27th, 2026 by 1600 (MST)
Quotations Due: March 6th, 2026 by 1600 (MST)
Submit questions and proposals to
Westley.Bisson@usda.gov. Do not mail proposals.
Reference 1240LT26Q0006 in the subject line.
Period of Performance: 07/06/2026 to 10/16/2026
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .