This document is a Questions and Answers (Q&A) addendum for the Island Park Housing Reroofing federal contract opportunity, Solicitation No. 1240LT25R0016. The Q&A addresses multiple technical and procedural aspects of the roofing project, including contract performance details, material specifications, and site-specific considerations. Key clarifications include: the contract period runs from 8/1/2025 to 8/31/2026 with work to be completed within 90 days, the government will handle removal of antennae/dishes and certain obstructing materials prior to project start, and soffit vents are required in new metal soffits. The document also confirms that the contractor should bid according to unit quantities provided, assign a superintendent on-site during work, and have access to power at each dwelling. The project involves removing and replacing metal roofs on 10 housing units, including 3 bunkhouses, 3 duplexes, and 4 single-family homes, with potential optional work for sheathing replacement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Island Park Housing Reroofing Q&A’s 001:
Q. Some of the fascia is wood. Should it be replaced with metal?
A. Steel as noted in Specification 076200.2.7.A.
Q. There are antennae/dishes on some of the buildings. Do they need to be replaced after?
A. The Government will remove any antennae/dishes necessary prior to construction and will be responsible for replacement.
Q. Some buildings have the siding integrated into the soffit. What should we do in this situation?
A. In this scenario the existing wood may be vented and covered with soffit as per the contract.
Q. The solicitation states the contract period is 396 days with a start date of 8/1/2025 to 8/31/2026. The specifications state the contract time is 90 days from 6/1/2025. Please clarify the period of performance.
A. Contract period is 8/1/2025-8/31/2026. Work must be completed with 90 days of beginning work. If it becomes necessary to stop work due to winter snow conditions, we will suspend work and continue the 90 day performance period in the spring. All work on any building started in 2025 must be completed before winter weather sets in to prevent damage to unfinished work. Winter weather typically sets in by October 1st.
Q. Should the contractor include costs division 1 costs for project management, supervision, etc. in the mobilization line of the schedule of items? Or should the contractor distribute division 1 costs between each line item in the base bid?
A. Refer to specification 011900.1.1.A. Mobilization is not intended to pay for project management beyond those items explicitly stated in the specification.
Q. If any structural deficiencies in the trusses are identified during roof demolition will this be seen as a differing site condition and handled in accordance with FAR Clause 52.236- 2?
A. Yes.
Solicitation No: 1240LT25R0016 Project Name: ISLAND PARK HOUSING REROOFING Page 1 of 3
Q. Please confirm that the contractor is to only bid per the unit quantities provided in the schedule of items, and that if those quantities differ from actual quantities, it will be seen as a differing site condition and handled in accordance with FAR Clause 52.236-2.
A. Correct.
Q. Please confirm that it is the government’s expectation that the GC will assign a superintendent to the project, and that the superintendent will always be on site during the performance of work per FAR clause 52.236-6.
A. Correct.
Q. Please confirm that power will be provided at each of the dwellings for contractor use.
A. Correct.
Q. It was stated during the site visit that the government is expecting 50% of all materials removed to be recycled. Please confirm this is the government’s expectation, as some of the materials are not recyclable.
A. Refer to specification 017419 - Construction Waste Management And Disposal.
Q. During the site visit it was discussed that the contractor laydown area would be adjacent to building 1357. Question: Will the contractor be able to use other areas that are closer to each of the buildings as they progress through the schedule?
A. Contactor laydown areas can be designated prior to commencement of work.
There are open areas closer to the housing that can be utilized.
Q. Please confirm that the government will be responsible for removing any fencing that impedes the contractor’s ability to perform any work associated with this contract.
A. Negative. Contractor may elect to remove fencing at their own expense to aid in construction. The fence should be re-installed as soon as practical.
Q. During the site visit it was discussed that soffit existing on the rear porches were not to be removed and replaced with metal soffit. Please confirm that existing wood soffit on the rear of the dwellings are not in the scope of this contract.
A. Porch soffits are included in contract quantities shown. They should be placed anywhere they already exist or would be appropriate.
Q. Please confirm that no structural repairs to the porches are to be considered as part of this contract.
A. Correct. No structural repairs.
Project Name: ISLAND PARK HOUSING REROOFING Page 2 of 3
Q. Are soffit vents required in the new metal soffits?
A. Yes. Refer to project description.
Q. Building 1147: There are window shutters that flush up to the soffit. Are the shutters to be removed and reinstalled after the new soffit is completed?-
A. Government will remove the shutters prior to project start date.
Q. Building 1159: It appears that there has been metal roofing used as siding that impedes on the installation of the soffit. Please clarify the government’s expectation on how the contractor is to install new soffit at this location.
A. Government will remove the metal roofing used as siding prior to project start date.
Q. Building 1155: The open soffit area at the south gable exhibits signs of rodent/animal entry that contains wire mesh over the entry point. Does the government wish to have the contractor repair this area? If so, please provide governments expectation for such repairs.
A. No. Government will repair at a later date.
Project Name: ISLAND PARK HOUSING REROOFING Page 3 of 3