RV1 - K-MtnPipelineReconstruct_SOW.pdf
PDF 214 KB Posted
- Attached to
- Pipeline Reconstruction - Salmon-Challis NF - ID Federal contract opportunity
- Solicitation number
- 1240LT25Q0009
- Issued by
- Department of Agriculture Forest Service
About this file
This Statement of Work details requirements for reconstructing approximately 7,500 feet (1.4 miles) of buried 1-1/4" IPS SDR11 Black HDPE non-potable water pipeline on the Salmon-Challis National Forest in Idaho. The project involves removing existing waterline and installing new pipeline to serve water from a spring source to three rangeland water troughs on Forest Service property, with work divided into a base section and two optional sections. The base section includes 2,025 feet of pipeline from the spring headbox at 6,743' elevation to the first trough at 6,200', while optional sections add 3,618 feet to the second trough and 1,800 feet to the third trough.
The contractor must provide all labor, equipment, and materials, with key requirements including: minimum 18-inch burial depth unless prevented by bedrock, pressure testing of all sections, clearing/grubbing vegetation for equipment access, and site restoration. The pipeline will traverse varied terrain including open sagebrush and timbered areas in the Kadletz Creek drainage. Notable specifications include use of butt fusion joining techniques for HDPE pipe, installation of daylight drains at section endpoints, and requirements for equipment cleaning to prevent noxious weed spread. The contractor will not be responsible for connecting to the spring box or installing water troughs. The base contract period is 30 calendar days, with work to be performed at a site approximately 22 miles southeast of Salmon, ID.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 MOD 0001 1240LT25Q0009.pdf | ||
| K-MtnPipeline-PreBid Qs and As.pdf | ||
| RV1 -K-MtnPipelineReconstruct_Attachement 1_Maps.pdf | ||
| Attach J.3 - Maps - 10 Pages.pdf | ||
| Attach J.4 - WD ID20240053 dtd 11-15-24 - 6 Pages.pdf | ||
| Attach J.1 - SOW - Pipeline Reconstruct - 21 Pages.pdf | ||
| Attach J.2 - SOI - MtnPipelineReconstruct.pdf | ||
| Attach J.5 Experience Questionnaire_3 pages.pdf | ||
| SF1442 - 1240LT25Q0009- Final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C - Description/Specifications/Statement of Work
STATEMENT OF WORK & GENERAL SPECIFICATIONS
K-MTN PIPELINE RECONSTRUCT
Revision 1 (Highlighted Red) Dated: December 31, 2024
1.1 SCOPE OF CONTRACT
A. This project includes the installation of approximately 7,500 feet of buried 1-1/4” IPS SDR11 Black HDPE non-potable water line. Work also includes the removal and disposal of all existing waterline and associated connections. The pipeline serves water from a spring source to three rangeland water troughs on Forest Service owned property. Final location and routing of pipeline will be flagged and determined onsite with Contracting Officer’s Representative (COR).
1. Contractor shall furnish all labor, equipment, and materials as required to accomplish the work under this contract.
2. Pipeline to be installed will total of approximately 1.4 miles (7500 feet) of 1 1/4" IPS SDR11 Black HDPE poly pipe and installing 3 short spur pipelines to service three trough locations.
3. The contractor will not be required to plumb newly installed pipeline to the spring box, nor required to plumb or install water troughs.
4. The new pipe will be buried 18 inches minimum, unless prevented in areas by bedrock.
5. Work also includes performing all required clearing and grubbing of existing vegetation to accommodate heavy equipment access and new improvements, including any hazard tree removal as applicable, completing all required excavating, backfill, and trenching as applicable, and performing site restoration / cleanup at each respective site when complete.
B. The following project scope items are described herein and in further detail in the Specification Sections:
1. Base Item 001: Mobilization, in accordance with Specification Section 012000 Mobilization. Site is located on the Salmon-Challis National Forest, Leadore Ranger District approximately 22 miles southeast of Salmon, ID. Travel will consist of highway/paved roads from contractor’s duty location to Haynes Creek Road. From this turn off, there is a mixture or road conditions including paved, well maintained dirt roads, rough unmaintained dirt roads, and cross-country travel to the construction site approximately 4-5 miles off Highway 28.
2. Base Item 002: Removal/Demolition of Existing Pipe – All existing water line will be removed and disposed of. The Contractor shall be responsible for disposal of materials in a manner consistent with State, Federal and local laws and for all expenses incurred with disposal.
3. Base Item 003: Pipeline Installation Section 1 – This item includes the installation of approximately 2,025 feet of 1-1/4” IPS SDR11 Black HDPE water line originating at the spring headbox in the Kadletz Creek drainage at 6,743’ in elevation. The pipeline climbs out of the shallow drainage to the bench, and then follows the bench downslope to terminating at the first trough location, which is located approximately 2025 feet from the headbox, at an elevation of 6200’. This also includes the installation of a daylight drain at the end of the line, final location to be determined in field with COR. This section of piping includes a majority (>50%) of rough, steep, tree covered terrain, leading from the spring box to the clearing above the first trough. This will include significant clearing and grubbing to follow the existing pipes route.
4. Option Item 1001: Pipeline Installation Section 2 – This item includes the installation of approximately 3,618 feet of 1-1/4” IPS SDR11 Black HDPE water line, connecting to the end of Section 1 and continuing approximately 0.6 miles to the second trough at an elevation of 6,140’. This also includes the installation of a daylight drain and air vacuum valve, final location to be determined in field with
COR.
5. Option Item 1002: Pipeline Installation Section 3 – This item includes the installation of approximately 1,800 feet of 1-1/4” IPS SDR11 Black HDPE water line connecting to the end of Section 2 and terminates at the third trough at an elevation of 6,071’. This also includes the installation of a daylight drain at the end of the line, final location to be determined in field with COR
1.2 PROJECT LOCATIONS
A. The project is located on the Leadore Ranger District of the Salmon-Challis National Forest, Lemhi County, Idaho. Access to the area is via Forest Service roads 350 and 427 on the Leadore Ranger District. Off-road/non-system route travel will be required to get to some areas of the pipeline. Authorization of cross-country travel where appropriate will be designated by the COR and will also be dependent on weather that may limit use due to potential resource damage.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction site is on Forest Service land open to the public. The Forest Service will notify Forest Employees and the public of construction work. The Contractor will be responsible for signing and limiting of Forest Service employees and members of the public within construction boundary.
2. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks, and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brush guard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
3. Water is available at the site for construction purposes.
4. Most of the pipeline will be placed in an open sagebrush landscape. One length of the pipeline will be installed in a mountain draw with timber (Kadletz Creek drainage). The terrain is varied and moderately rugged with a general landform of benches, rolling hills, and along a canyon drainage. Vegetation is comprised of sagebrush and Douglas fir communities.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Idaho Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site.
B. No overnight camping will be allowed on site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
B. Dimensions and Distances provided in the photos and maps are for informational purposes only. A dimension may be shown on the maps provided, but the actual dimension may vary, from very small to large increments, depending on jobsite conditions.
1.7 START DATE
A. To be determined.
1.8 CONTRACT TIME
A. Base Bid: 30 Calendar Days total contract length
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental, and no additional compensation will be made.
Section 011250 - Measurement And Payment
Section 011900 – Mobilization
Section 221100 - Water Distribution Systems
Section 024102 - Removal And Disposal Of Structures And Obstructions
Section 311000 - Clearing And Grubbing
USDA FOREST SERVICE, R4
Salmon-Challis NF, K-Mtn Pipeline Reconstruct
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100-feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point; parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
April 2024
USDA FOREST SERVICE, R-4
Salmon-Challis NF, K-Mtn Pipeline Reconstruct
SECTION 011900 - MOBILIZATION
PART 2 - GENERAL
2.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
2.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 3 - PRODUCTS (NOT USED)
PART 4 - EXECUTION (NOT USED)
END OF SECTION 011900
January 2025
END OF SECTION C
SECTION 221100 - WATER DISTRIBUTION SYSTEMS
PART 5 - GENERAL
5.1 SUMMARY
A. This Section shall consist of furnishing and installing the following:
1. Non-Potable water distribution pipe and fittings.
2. Drains.
B. Related Sections include the following:
1. Section 024102 - Removal And Disposal Of Structures And Obstructions
2. Section 311000 - Clearing And Grubbing
5.2 DEFINITIONS
A. GSP: Galvanized Steel Pipe.
B. HDPE: High Density Polyethylene plastic.
C. NPWL: Non-potable waterline (includes sewerline).
D. PVC: Polyvinyl chloride plastic.
5.3 SUBMITTALS
A. Product Data: For the following:
1. Pipe and fittings.
B. Protect stored piping from moisture and dirt. Elevate above grade.
C. Protect flanges, fittings, and specialties from moisture and dirt.
D. Store plastic piping protected from direct sunlight. Support to prevent sagging and bending.
5.4 COORDINATION
A. Coordinate connection to existing waterlines with Contracting Officer.
B. Verify piping materials, sizes, entry locations and pressure requirements are compatible with connection point.
5.5 MEASUREMENT AND PAYMENT
A. Payment will be lump sum for Water Distribution Systems and will include pipes and fittings, valves, drains, and all other equipment, material, work and incidentals necessary to complete the item.
B. Payment will be as listed for the following items:
1. Pipeline: Linear Feet of pipe of each type and size designated, including fittings, trench, drains and connections to existing waterlines.
2. Daylight Drains: Number of Daylight Drains, including excavation, galvanized steel pipe, fittings, screen, suction strainer, riprap, backfill and all work within 10 feet of the drain outlet, as shown on the Drawings.
PART 6 - PRODUCTS
6.1 GENERAL
A. All waterlines, pipes, and fittings shall be new and unused, of the type, pressure rating or class, and size specified and as shown on the Drawings.
6.2 PIPES AND FITTINGS
A. HDPE:
1. Pipe, AWWA C901:
a. Material Designation: PE 4710 resin
b. Minimum Cell Classification: ASTM D 3350, 445574C
c. Dimension Ratio and Minimum Pressure Rating: 1-1/4” IPS SDR11 Black
HDPE
2. Fittings:
a. Molded HDPE Fittings: ASTM D 3350, PE 4710 resin, butt-fusion type, made to match HDPE pipe dimensions and class.
b. Insert Fittings: Not allowed. Allowed if meets pressure testing
c. Transition Fittings to non-HDPE Pipe: Approved by HDPE pipe manufacturer and meet pressure testing when installed. Compression-type fittings are not allowed.
3. Pipe Larger than 2-inch Diameter: Provide in 40-foot lengths rather than in rolls.
4. Pipe and Fittings 4-inch Diameter and Larger: Conform to AWWA C906 in addition to above requirements.
6.3 PIPING SPECIALTIES
A. Daylight Drains and Overflows
1. Suction Strainer
a. Design: Galvanized (zinc plated), cold rolled, 16-gage steel strainer with threaded end to fit GSP drain pipe size.
b. Model: “SSS” Series, Round Hole Strainer, as manufactured by Campbell Manufacturing Inc., or an approved equal.
2. Insect Screens
a. For Daylight Drains: 4-mesh woven wire cloth, galvanized steel.
b. For Water Storage Tank and Spring Development Drains and Overflows: 24-mesh woven wire cloth, type 304 stainless steel standard grade, non-corrodible.
3. Riprap
a. The stones may be obtained from on-site excavated material or a borrow source designated by the Contracting Officer. Stones used shall be such that not more than 10 percent of the individual stones shall have a perimeter less than 12 inches in the smallest section. All of the stones shall have a volume less than a 1/2 cubic foot.
b. The stones shall be sound, hard, durable and free from laminations, fractures, or other structural defects. They shall be of such quality that they will not disintegrate on exposure to water or weathering.
PART 7 - EXECUTION
7.1 PIPING INSTALLATION
A. Construct the water system to the lines and grades shown or established in the field.
B. All waterline shall be graded to drain.
C. All pipe, fittings, and appurtenances shall be handled and installed in strict conformance to the manufacturer’s recommendations.
D. Drains, valves, and other regulating and controlling devices shall be installed in the line where called for on the drawings or established in the field.
E. The interior of all pipe, fittings, and other accessories shall be kept as free as possible from dirt and foreign matter at all times. Each piece of line as it is laid shall be cleaned of all debris. When the pipeline has become dirty on the inside during shipment or storage, it shall be swabbed out by drawing a damp swab through the line before placing in trench. Care shall be exercised to keep all joining surfaces clean. Any pipe with contaminated or damaged joining surfaces, which cannot be satisfactorily cleaned or repaired, shall be discarded. Under no circumstances shall pipe be installed in water, and no pipe shall be installed when trench conditions or the weather is unsuitable for such work. At all times when work is not in progress, all open ends of the pipe and fittings shall be securely closed to the satisfaction of the Contracting Officer so that no trench water, rodents, earth, or other substance will enter the pipe or fittings.
F. Any section of pipe already installed and found to be defective shall be removed and replaced with new pipe at the Contractor’s expense.
G. Culvert Crossings: Where waterline crosses a road culvert, adjust grade of waterline to provide a minimum of 12 inches of separation between the waterline and culvert, maintaining slope of waterline to drain.
H. Bury piping with depth of cover over top at least 18 inches, I. Cutting and Handling of Pipe
1. Cutting of pipe for closure pieces or for other reasons shall be done in a neat manner by methods, which will not damage the pipe. The pipe and fittings shall be handled in such a manner as to insure delivery and final placement in good, undamaged condition. Particular care shall be exercised not to injure the pipe surfaces or coatings. Damaged pipe shall not be used in the work.
J. Laying Pipe
1. No pipe shall be placed in the trench until the Contracting Officer has approved the trench and bedding.
2. Do not drop pipe into trench. If HDPE pipe is fusion welded above ground outside of the trench, gently lay pipe into the trench. Ensure installation procedures meet the manufacturer’s requirements.
3. Pipes shall be placed true to the lines and grades shown on the Drawings and as specified in the field. Complete water system shall be constructed to drain by gravity to drains for seasonal shutdown. Waterlines shall be constructed to drain at a minimum grade of 2% Waterlines not meeting this requirement shall be removed by the Contactor and replaced at no cost to the Government.
4. Each section of the pipe shall rest upon the pipe bed for the full length of its barrel.
5. Backfill the pipe within 24 hours after installing the pipe in the trench, leaving the joints and one foot of pipe on each side of each joint exposed until testing is complete.
6. When work is not in progress, securely close open ends of pipe and fittings.
7. When high density polyethylene or solvent weld joint pipe is used, it shall be weaved in the trench to provide horizontal slack in the line for expansion and contraction.
8. High density polyethylene pipe shall be allowed to cool to within 20ºF of the shaded trench bottom temperature before backfilling.
9. When pipes are installed in a structure or utility box, they shall be adequately supported.
10. Use proper fittings in order to follow the required line and grades and to avoid excessive curvature. Deflections from a straight line or grade, as required by vertical curves, horizontal curves, or offsets, shall not exceed the manufacturer's recommended maximum joint deflection or curvature for their pipe.
11. When more than one pipeline is in the same trench, the pipes shall be separated by at least eight horizontal inches, or as shown on the Drawings.
12. Bends that result in joint tension or permanent pipe deformation are prohibited.
13. Pipelines may be relocated slightly, if necessary, to avoid existing obstacles.
However, the required slopes must be maintained.
K. Branch Connections
1. Branch connections to the main shall be made with tees.
2. Horizontal tees for waterline laterals shall not be permitted. The branch side of tees shall be up when drainage is toward the tee, and down when drainage is away from the tee.
3. Waterline tees shall be the same diameter as the largest pipe connected to the tee.
L. Pipe Joints
1. Joints shall be made, using jointing materials and applied with the proper accessories, in accordance with the manufacturer's instructions. Completed joints shall be watertight, and capable of passing the required hydrostatic testing. If pipe and fittings are assembled with a lubricant, it must be nontoxic.
2. Dissimilar Joints: Connections between two dissimilar pipes or fittings shall be installed in manner recommended by the pipe manufacturer and approved by the Contracting Officer. Use adapters compatible with both piping materials, outer diameters and system working pressure.
a. For HDPE pipelines:
1) Use HDPE/GSP transition fittings for connections to galvanized steel pipe.
a) Stainless steel transition fittings are not to be used on galvanized steel pipe.
2) Use HDPE/PVC transition fittings for connections to PVC pipe.
b. For other situations, use fittings to suit the actual conditions.
c. Compression-type fittings are not allowed.
3. HDPE Heat-Fusion Joints
a. According to ASTM D 2657 and piping manufacturer's written instructions.
b. The joining method shall be butt fusion method and shall be performed in accordance with the pipe manufacturer's recommendations. Butt fusion equipment used in the joining procedures shall be capable of meeting all conditions recommended by the pipe manufacturer, including but not limited to, temperature requirements, alignment, and fusion pressures.
c. Personnel trained in butt fusion techniques by the manufacturer of the pipe, shall supervise or perform butt fusion operations.
d. Butt fusion shall be performed between pipe ends or pipe ends and fitting and valve outlets, of like outside diameter and wall thickness, SDR or DR. Butt fusion joining between same diameters but unlike wall thickness shall not be permitted. Transitions between unlike wall thickness shall be made with a transition nipple (a short length of the heavier wall pipe with one end machined to the lighter wall) or by mechanical means.
e. Branch connections to the main shall be made with polyethylene fittings, and butt fused.
f. Bent Strap Test: On each day that butt fusions are to be made, perform a “Bent Strap Test.” The first fusion of the day shall be a trial fusion. The trial fusion shall be allowed to cool completely, and then fusion test straps shall be cut out. The test strap shall be 12" (min) or 30 times the wall thickness in length with the fusion in the center, and 1" (min) or 1.5 times the wall thickness in width. Bend the test strap until the ends of the strap touch. If the fusion fails at the joint, a new trial fusion shall be made, cooled completely and tested. Butt fusion of pipe to be installed shall not commence until a trial fusion has passed the bent strap test.
4. Plastic Piping Solvent-Cemented Joints: Clean and dry joining surfaces. Join pipe and fittings according to the following:
a. PVC Pressure Piping: Join schedule number ASTM D 1785, PVC pipe and PVC socket fittings according to ASTM D 2672. Join other-than-schedule-number PVC pipe and socket fittings according to ASTM D 2855.
M. Install piping by directional boring, tunneling, jacking, or combination, under streets and other obstructions that cannot be disturbed.
7.2 DAYLIGHT DRAINS
A. Transition from water system piping to galvanized steel pipe 10-feet from atmospheric outlet of daylight drain.
B. Install suction strainer and insect screens on the atmospheric outlet of daylight drains.
Attach insect screens to pipe with stainless steel hose clamps.
C. Minimum grade of slope of drain shall be 2%.
D. Place riprap securely around outlet with a minimum 12” air gap.
7.3 HYDROSTATIC TESTING
A. General
1. The Contractor shall conduct pressure and leakage tests on all newly constructed portions of the water system, including water mains, service lines, fittings, valves, and hydrants. New waterlines that are extensions or modifications of an existing water system shall be tested at the test pressure specified here unless the Contracting Officer specifies another pressure. Pneumatic testing will not be allowed.
2. The contractor shall ensure that any appurtenance attached to the pipeline at the time of testing is rated to withstand the pressures that will exist during testing.
3. Conduct piping tests before joints are covered and after thrust blocks, if required, have hardened sufficiently. Joints shall remain uncovered until testing is completed satisfactorily.
4. The Contractor shall furnish the pump, pipe, gauge, measuring device, connections, and all other necessary equipment, and shall furnish the necessary personnel to conduct the tests. All equipment, gauges, and attachments shall be subject to approval by the Contracting Officer.
5. The Contracting Officer shall be present during the testing period.
6. Waterlines shall be tested in sections not to exceed 2,000 ft in length or a maximum pressure differential of 30 psi in the test section.
7. No paints, asphalts, tars, enamels, or other types of pipe compounds shall be used to eliminate leaks.
B. Pressure and Leakage Test
1. The test pressure shall:
a. Equal at least 100 psi at the highest elevation of the test but not exceed 160 psi at any point being tested.
b. Not exceed the thrust restraint design pressures.
c. Not vary by more than +/- 5 psi from the established test pressure.
d. Not exceed twice the rated pressure of valves when the test section includes closed valves.
2. Pressure Test Procedure
a. Equipment: The test pressure shall be applied by means of a pump connected to the pipe or in a manner satisfactory to the Contracting Officer.
b. Preparation: Fill pipeline 24 hours before testing. Use only potable water.
Each valved section of pipeline shall be slowly filled with water and all air shall be expelled from the pipeline. Apply test pressure to stabilize system.
c. Pressurization:
1) Increase pressure in 50-psig increments and inspect each joint between increments.
2) Hold at test pressure for 1 hour.
3) Decrease to 0 psig.
4) Slowly increase again to test pressure and hold for 1 more hour. If the test pressure cannot be sustained within +/- 5 psi during this time, then the system will be determined to have leakage.
5) Leakage shall be verified by the Contractor and the CO
6) Locate and repair leaking joints with new materials and repeat test until leakage is within allowed limits. All visible leaks are to be repaired regardless of the amount of leakage.
d. Examination: All exposed pipe, fittings, valves, and joints shall be carefully examined. Any cracked or defective pipe, fitting, or valve discovered shall be repaired or replaced by the Contractor at his own expense with new material and the test repeated until satisfactory to the Contracting Officer.
3. Results
a. The Contractor shall furnish a written report to the Contracting Officer describing the results of each test. The report must identify the specific portions of the pipeline tested, the pressure, the duration of the tests, and the amount of leakage.
END OF SECTION 221100
January 2025
SECTION 024102 - REMOVAL AND DISPOSAL OF STRUCTURES AND OBSTRUCTIONS
PART 8 - GENERAL
8.1 SUMMARY
A. Includes removal disposal, and backfilling of existing water lines and all other items to the extent shown on the Drawings. This item also includes scarifying and regrading the area around features and structures removed.
B. Related Sections Include the Following:
1. Section 024100 “Waste Material Disposal.”
8.2 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for this item.
B. Payment will be lump sum for removal and disposal of structures and obstructions, including demolition, excavation, backfill, removal, hauling and all incidentals and work required to complete this item.
PART 9 - PRODUCTS
9.1 SELECT BACKFILL
A. Select backfill shall be native or imported soil, sand, or granular soil free of stones larger than 6 inches in greatest dimension.
PART 10 - EXECUTION
10.1 SALVAGE
10.2 GENERAL
A. Topsoil stripping and storage, if required, shall comply with the applicable specification.
B. The Contractor may use any means to remove the existing waterline if it is visible above ground or incidental to installing the new waterline. structures or items shown on the Drawings to be removed, as long as the safety of the public is provided and the surrounding site and structures are preserved
C. All of a substructure shall be demolished to a depth of 1 foot below the present ground level. All wood, concrete, and metal materials to be removed shall be broken into sufficiently small pieces to enable handling and disposal. All other structures shall be backfilled and the surrounding ground restored to as near normal conditions as practicable in accordance with these specifications.
D. Backfill for removed items may be excess material from other excavation or borrow from an approved source.
1. Backfill shall be brought up in 12-inch compacted layers.
2. Compaction shall be by mechanical tampers, with at least three passes over the entire surface.
3. Maximum size of rock in backfill shall be 8 inches.
4. Backfill shall be compacted and rounded 6 inches above the natural ground.
5. If the backfill is not in an existing roadway or parking area, and at least 20 feet away from any proposed structure, the backfill shall be as specified above, except backfill shall be graded to blend with the natural ground and each layer compacted to 85 percent of the optimum dry density determined by AASHTO T-99, Method C.
6. In areas where backfill is in graveled or paved surface roadways, or within 20 feet of a proposed structure, the backfill shall be as specified above, except it shall be terminated at the grade shown on the drawings and each layer compacted to 95 percent of the optimum dry density determined by AASHTO T-99, Method C.
Completion of backfill shall be in accordance with the applicable surfacing specifications.
7. When topsoil replacement is required, backfill and compaction shall be as specified above, except the backfill shall terminate 6 inches below the natural ground.
Placement of topsoil, when required, shall comply with the applicable specification.
E. Excessive settlement or other evidence of improper backfill shall be corrected by reopening the excavation to the depth required for proper refilling and compaction.
10.3 VAULT TOILET AND SEPTIC TANK PUMPING
A. Prior to removal, the vault toilet waste shall be pumped by a commercial hauler with equipment for pumping and hauling human waste. Hauler shall have the necessary equipment to add water to the tank and break up solids in order to pump waste.
B. Disposal of vault waste shall be at any sewage treatment facility approved by the State Department of Health. The Contractor shall be responsible to obtain permission to dump the waste in the treatment facilities and pay any fees required.
10.4 DISPOSAL
A. Disposal of debris shall comply with Section 024100 “Waste Material Disposal.”
10.5 FINISHING AND CLEANUP
A. After the area has been backfilled, the disturbed area shall be finish graded to present a natural appearance and cleaned up by removing all debris and materials left from the removal of items in this Section.
END OF SECTION 024102
SECTION 311000 - CLEARING AND GRUBBING
PART 11 - GENERAL
11.1 SUMMARY
A. This work shall consist of clearing, grubbing, trimming, removing, and disposing of or treatment of timber, construction slash, and debris. This work shall also include preservation of vegetation and objects designated to remain from injury or defacement.
11.2 RELATED SECTIONS
A. Section 024100 “Waste Material Disposal.”
11.3 DEFINITIONS
A. Areas to be Cleared and Grubbed - The limits of clearing and grubbing will be established by this specification, by other specification items, or on contract Drawings. The clearing and grubbing limits will normally coincide with the designated working limits; however, the Contracting Officer may also designate individual trees and snags outside the clearing limits for selective removal and disposal, or he may designate areas within the working limits where clearing and grubbing is not required or allowed within the provisions of this specification.
1. Grading Limits - Area that is to be excavated or covered with additional materials during construction.
2. Working Limits - Area consisting of the grading limits plus room for equipment to maneuver to perform the necessary clearing and grubbing. These limits, to be held to a minimum, will be designated for each project.
3. Clearing Limits - Area consisting of the working limits plus any additional area to operate a boom or other above-ground clearance requirement.
11.4 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this Section. Clearing and Grubbing is considered incidental to other items of work shown in the Schedule of Items.
PART 12 - PRODUCTS (Not Applicable)
PART 13 - EXECUTION
13.1 CLEARING AND GRUBBING
A. All trees, brush, shrubs, stumps, roots, and other vegetative material and debris within the designated clearing limits, shall be cleared, grubbed, removed, and disposed of except the following condition:
1. Those items designated to remain by the Contract or Contracting Officer.
2. Undisturbed stumps outside the roadway, trailway, and parking area, provided they do not extend more than 12 inches above the original ground (measured from the uphill side) and are not closer than 2 feet from the edge of road or parking area, are not in the cut or fill slopes, and they do not interfere with the placement or compaction of embankments.
B. All roots over 3 inches in diameter within the roadbed area shall be grubbed to a minimum depth of 6 inches below subgrade. Roots over 3 inches in diameter protruding from the excavated slope shall be cut flush with the excavated slope surface.
C. Clearing slash shall be treated in accordance with “Slash Treatment” paragraph below.
D. Trees shall be felled within the clearing limits, usually towards the center, so as to prevent damage to the trees that are to be left standing. In some cases, controlled felling, cutting of trees into sections from the top downward, or other means shall be used when required to prevent damage to property, structures, traffic, and trees/vegetation to remain.
E. Branches on remaining trees or shrubs shall be trimmed to give a clear height of 14 feet above the roadbed unless otherwise shown on the Drawings. Tree limbs shall be trimmed as near flush with the trunk as practicable.
13.2 UTILIZATION OF TIMBER
A. Merchantable timber is timber that meets Utilization Standards. Utilization Standards shall be trees larger than 8-inches in diameter measured 12-inches above grade.
B. Utilization and Removal of Timber: Trees that meet “Merchantable Timber” standards shall be treated as follows:
1. Logs meeting utilization standards shall be limbed and decked at locations shown on the Drawings or approved by the Contracting Officer. Decking shall be done in such a manner that logs are piled parallel one to the other, can reasonably be removed by standard log loading equipment, will not damage standing trees, and will not roll. Decks shall be free of brush and soil. Title to all such timber cut from National Forest land shall remain with the Forest Service, U.S. Department of Agriculture, in accordance with its regular procedures, unless otherwise specified.
2. Removal from Government Land. Merchantable timber, designated for removal, shall become the property of the contractor without charge and removed from Government land. This timber shall not be exported from the United States nor used as substitution (as defined in 36 CFR 223 Subpart D) for timber from private lands exported by the contractor or an affiliate directly or indirectly.
3. Logs meeting utilization standards shall be limbed, cut into 16-inch to 36-inch lengths, and stacked in various locations throughout the recreation development.
Logs stacked shall be stable and free of brush and soil.
4. Disposal as Unmerchantable Timber. Timber on this project is not considered merchantable and shall be disposed of in accordance with “Slash Treatment” paragraph below.
13.3 PIONEER
A. Pioneering operations shall be done in a manner that prevents undercutting of final excavation slopes, maintains materials within the road, trail, or parking limits, and controls runoff.
13.4 SLASH TREATMENT
A. Treatment of construction slash larger than 3-inches in diameter and 3-feet in length shall be accomplished by one or more of the following methods as Designated by the Contracting Officer:
1. Scattering: Construction slash shall be scattered outside the clearing limits without damaging trees. All logs shall be limbed and placed away from trees, positioned so they will not roll, and not be placed on top of one another. Stumps shall be removed and disposed of off site. Other construction slash shall be limbed and scattered to reduce slash concentrations.
2. Burying: Construction slash shall be buried at the locations shown on the Drawings and designated on the ground. Construction slash shall be matted down in layers and covered with at least 2 feet of rock and soil. The final surface shall be smoothed and sloped to drain.
3. Chipping: Construction slash up to at least 3 inches in diameter and longer than 3 feet shall be processed through a chipping machine. Chips shall be deposited on embankment slopes or outside the roadway to a loose depth not exceeding 6 inches.
Minor amounts of chips may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
4. Piling and Burning: Construction slash shall be deposited in areas shown on the Drawings and designated on the ground. Piles shall be constructed so that burning does not damage standing trees. If burning is incomplete, the slash remaining shall be repiled and burned until pieces are reduced to less than 3 inches in diameter and 3 feet in length. These pieces shall then be scattered.
5. Decking Unmerchantable Material: Logs not meeting utilization standards and other material that exceeds 8-inches in diameter shall be decked in areas shown on the Drawings and approved by the Contracting Officer. Material shall be cut into lengths not to exceed 32 feet and all limbs removed. Decks shall be stable and free of brush and soil.
6. Stacking of Unmerchantable Material: Logs not meeting utilization standards and other material that exceeds 4-inches in diameter shall be limbed, cut into 16-inch to 36-inch lengths, and stacked in various locations throughout the recreation development. Log stacked shall be stable and free of brush and soil.
7. Removal: Construction slash shall be removed or hauled to locations shown on the Drawings and designated on the ground.
8. Piling: Construction slash shall be piled in areas shown on the Drawings and designated on the ground for later burning or disposal by others. Piles shall be placed and constructed so burning will not damage remaining trees. All stumps shall be reasonably free of dirt. Unmerchantable logs shall be cut into lengths less than 20 feet prior to placement in the pile.
9. Placing Slash on Embankment Slopes: Construction slash shall be placed on completed embankment slopes to reduce soil erosion where shown on the Drawings. Construction slash shall be placed as flat as practicable on the completed slope. Slash shall be placed from the toe of the embankment to a point at least 2 feet below subgrade elevation. Priority for the use of available slash shall be given to (1) through fills, (2) inside of curves, and (3) ditch relief outlets.
B. Construction slash less than 3 inches in diameter and 3 feet in length may be scattered within the clearing limits.
C. No construction slash shall be deposited in lakes, meadows, streams, or streambeds.
Construction slash that interferes with drainage structures shall be removed immediately.
13.5 CLEARING OR CLEARING AND GRUBBING REQUIREMENTS FOR VARIOUS
ITEMS:
A. Paths and Trails - The path and trail clearing limits shall be 3 feet on each side of the tread centerline and extend to a height of 8 feet above the tread. Shrubs normally growing less than 2 feet tall when mature shall be left undisturbed where they occur outside the cut and fill slope areas. All branches, except short shrubs, which extend into the travelway shall be removed by cutting them flush with the trunk of the tree or shrub.
B. Roadways and Parking Areas - On roadways and parking areas, the area to be grubbed shall be an area between the cut and/or fill stakes. The clearing area will normally be an additional 5 feet on each side of the grubbed area and shall extend to a height of 14 feet above the finished roadway surface.
C. Snow Play Areas - Clearing for the snow play areas will consist of the removal of trees, larger shrubs, and other objects as designated. No heavy construction equipment will be permitted on slopes steeper than 20 percent. Stumps and trees within the designated snow play areas are to be cut not to exceed 4 inches above ground level and stumps are not to be removed. Shrubs indicated for removal are to be cut off at ground level. All disturbed areas resulting from the clearing operation are to be smoothed and compacted.
D. Summer Play Areas - Trees and shrubs are to be removed from summer play area sites.
Tree stumps may be left if cut within 4 inches of the finished ground surface.
E. Trenches for Water, Sewer, Electrical Lines, and other Underground Utilities - If no reference is made elsewhere, a clearing of 10 feet on each side of centerline will be allowed.
F. Buildings - Construction work shall disturb a minimum of the existing terrain and plant life adjacent to the building site. Only trees, shrubs, stumps, and major roots which interfere may be removed. When excavation reveals the major roots of a live and significant tree nearby, the Contractor shall not remove the tree unless it interferes with the construction and removal is authorized by Contracting Officer.
1. Comfort Stations, Pumphouse, and Sewage Lift Stations - Maximum clearing limits shall be confined to an area 20 feet outside the outside structure foundation wall on two sides and to an area 10 feet outside the outside structure foundation wall on the other two sides, unless otherwise shown on Drawings.
2. Offices, Homes, and Warehouses - Maximum clearing limits shall be confined to an area 50 feet outside the outside structure foundation wall on one side and to an area 15 feet outside the outside structure foundation wall on the other three sides, unless otherwise shown on the Drawings.
3. Bituminous-Surfaced Pads, Fire Areas, and Other Campground Items (Hydrants, Wastewater Sumps, Tent Sites, Pads at Individual Units, Trailer Dump Station, etc.)
- Maximum clearing limits shall be confined to an area 5 feet outside the exterior sides of the completed unit on three sides. On the fourth side, sufficient space will be allowed to properly perform the work with equipment of sufficient size to do the work. Normally, the limits will be as indicated on the Drawings. Construction work shall disturb a minimum of the existing terrain and plant life adjacent to the site work. Branches of trees extending over the cleared area shall be trimmed to give a clear height of 12 feet above the cleared areas.
G. Wells: The clearing area shall be minimized, but shall be large enough for the well to be constructed safely. Provide an adequate area for the well drilling rig to operate.
H. On Site Wastewater Systems and Drainfields - for drainfields and absorption beds, clearing and grubbing limits shall be the entire area that contains the drainfield and/or absorption bed and to a minimum of 10 feet outside the edge of the drainfield or absorption bed. All stumps and large root balls shall be removed from the area.
I. Septic Tanks and Sewage Holding Tanks – Clearing and grubbing limits shall be a minimum of 5 feet outside the edge of the tank.
END OF SECTION 311000
| Section C - Description/Specifications/Statement of Work |
| 1. Contractor shall furnish all labor, equipment, and materials as required to accomplish the work under this contract. |
| 2. Pipeline to be installed will total of approximately 1.4 miles (7500 feet) of 1 1/4" IPS SDR11 Black HDPE poly pipe and installing 3 short spur pipelines to service three trough locations. |
| 3. The contractor will not be required to plumb newly installed pipeline to the spring box, nor required to plumb or install water troughs. |
| 4. The new pipe will be buried 18 inches minimum, unless prevented in areas by bedrock. |
| 5. Work also includes performing all required clearing and grubbing of existing vegetation to accommodate heavy equipment access and new improvements, including any hazard tree removal as applicable, completing all required excavating, backfill, and t... |
| 1. Base Item 001: Mobilization, in accordance with Specification Section 012000 Mobilization. Site is located on the Salmon-Challis National Forest, Leadore Ranger District approximately 22 miles southeast of Salmon, ID. Travel will consist of highwa... |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .