This document is a set of specifications for the Brainard Lake Recreation Area Deferred Maintenance project on the Arapaho-Roosevelt National Forest. The project includes site improvements at the Niwot Trailhead, Red Rock Lake Picnic Ground, and Arickaree Picnic Ground. Work includes demolition, clearing, new picnic sites and trails, parking lot reconstruction, toilet replacements, and revegetation. The project is estimated to cost between $500,000 and $1,000,000 and is being set aside for small businesses. The solicitation number is 1240LT24R0059 and all questions are due by August 23, 2024. The project is located in the Arapaho-Roosevelt National Forest on the Boulder Ranger District. The contracting agency is the USDA Forest Service Region 2.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1 1240LT24R0059.pdf | ||
| Attachment 7 Project Map.jpg | JPG image | |
| 1240LT24R0059 Solicitation.pdf | ||
| Attachment 6 Wage Determination.pdf | ||
| Attachment 8 Past_Performance_Questionnaire.doc | DOC document | |
| Attachment 3 Drawings.pdf | ||
| Attachment 5 FSSS.pdf | ||
| Attachment 1 Schedule of Items.pdf | ||
| Attachment 2 Statement of Work.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture
Forest Service
Region 2
Arapaho & Roosevelt National Forests Pawnee National Grassland
Boulder Ranger District
November 2023
BRAINARD LAKE
RECREATION AREA
DEFERRED
MAINTENANCE
Phase #1 -
Recreation Site Improvements
Final Specifications
AUSD
BLRA DEFERRED MAINT. PHASE #1 – REC. SITE IMPROVEMENTS 001500-1
ARAPAHO & ROOSEVELT NATIONAL FORESTS LIST OF DRAWINGS & SPECS
SECTION 001500
LIST OF DRAWINGS AND SPECIFICATIONS
PART 1 – GENERAL
1.1 DESCRIPTION
A. List of Contract Drawings:
B. List of Contract Specifications
DIVISION 01 - GENERAL REQUIREMENTS
Section 001500 LIST OF DRAWINGS AND SPECIFICATIONS
BLRA DEFERRED MAINT. PHASE #1 – REC. SITE IMPROVEMENTS 001500-2
Section 010150 Section 010200 Section 010250 Section 013200 Section 013223 Section 013300 Section 014420 Section 015000 Section 015050 Section 015100 Section 016000 Section 017100
GENERAL REQUIREMENTS
CONTROL OF MATERIALS
MEASUREMENT & PAYMENT
CONST. PROGRESS DOCUMENTATION
CONST. SURVEY AND STAKING
SUBMITTAL PROCEDURES
QTY. CONTROL & QTY. MEASUREMENT
TEMP. FACILITIES & CONTROLS
MOBILIZATION
GOVERNMENT FURNISHED MATERIALS
MATERIAL & EQUIPMENT
CLEAN UP & DISPOSAL
DIVISION 02 - EXISTING CONDITIONS
Section 022210 Section 024116 Section 024119 Section 025190
EXCAVATION & EMBANKMENT
STRUCTURE DEMOLITION
SELECTIVE DEMOLITION
AGGREGATE TRAILS
DIVISION 03 - CONCRETE
Section 033000 Section 034000
CAST-IN-PLACE CONCRETE
PRECAST CONCREATE
DIVISION 04 – MASONRY
Section 048600
STONE VENEER ASSEMBLIES
DIVISION 05 – METALS
Section 051200 Section 055000 Section 055200
STRUCTURAL STEEL
METAL FABRICATIONS
ACCESS HOLE RING & COVER
DIVISION 06 - WOOD, PLASTICS, COMPOSITES
Section 060000 Section 061000
REFERENCE CODES, STANDARDS & SPECS
ROUGH CARPENTRY
Section 061920 Section 062000
PREFABRICATED WOOD TRUSSES
FINISH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
Section 071650 DAMPPROOFING & VAULT EPOXY COAT.
BLRA DEFERRED MAINT. PHASE #1 – REC. SITE IMPROVEMENTS 001500-3
Section 072100 Section 076200
THERMAL INSULATION
SHEET METAL FLASHING AND TRIM
Section 079200 JOINT SEALANTS
DIVISION 08 - OPENINGS
Section 081100 Section 086500 Section 087100
HOLLOW METAL DOORS & FRAMES
SPECIAL WINDOWS
FINISH HARDWARE
DIVISION 09 - FINISHES
Section 097250 Section 099000
EPOXY FLOOR COATING SYSTEM
PAINTING
DIVISION 10 – SPECIALTIES
Section 108000 TOILET ACCESSORIES
DIVISION 12 – FURNISHINGS
Section 124720 Section 129300
PICNIC TABLES
MISC. SITE FURNISHINGS
DIVISION 13 – SPECIAL CONSTRUCTION
Section 136010 STICK BUILT TOILET STRUCTURE
DIVISION 15 –
Section 152010 Section 153150
TOILET STOOLS
MANHOLES, RISERS, & CLEANOUT
DIVISION 31 – EARTHWORK
Section 311100 Section 312250 Section 312500 Section 312523 Section 313219
CLEARING & GRUBBING
EARTHWORK
TEMPORARY EROSION CONTROL
BARRIER BOULDERS
GEOSYNTHETICS
DIVISION 32 – EXTERIOR IMPROVEMENTS
Section 321123 Section 321216 Section 321312 Section 321713
AGGREGATE
ASPHALT PAVING
CONCRETE PAVEMENT
CONCRETE WHEELSTOP
BLRA DEFERRED MAINT. PHASE #1 – REC. SITE IMPROVEMENTS 001500-4
Section 321723 Section 323000 Section 323002 Section 329219
PAVEMENT MARKINGS
SIGNS
USE PADS & PATHS
SEEDING
END OF SECTION 001500
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 1
ARAPAHO & ROOSEVELT NATIONAL FORESTS GENERAL REQUIREMENTS
SECTION 010150
GENERAL REQUIREMENTS
PART 1 – SUMMARY OF WORK
1.1 DESCRIPTION
A. The intent of this section is to provide a general outline of the work required under this contract and identify special project conditions and/or requirements. It is not intended to provide detailed specifications for materials, labor, and workmanship. These are covered in other sections of these specifications.
B. Brainard Lake Recreation Area is a unique set of developed sites that are nestled up next to the Indian Peak Wilderness Area on the Boulder Ranger District. This project covers a few of these recreation sites including Niwot Trailhead, Red Rock Lake Picnic Ground, and Arickaree Picnic Ground. This area is a heavily utilized recreation area for the winter and summer months. There are a lot of recreation opportunities within this area, and it sees approximately one-quarter of a million visitors annually.
C. The Niwot Trailhead has 3 picnic sites with some historic retaining walls and some sites that need to be reconstructed with all new picnic tables. There are several undesignated and unimproved trails that are not accessible and not maintained which will be designated and reconstructed. The site has a degraded 15 space asphalt parking lot that will be reconstructed, reconfigured, and re-striped. The toilet will remain as it was replaced within the last decade and is functioning well.
D. The Red Rock Lake Picnic Ground has a 10-vehicle asphalt parking lot that is crumbling and is immediately adjacent to the main road’s flow of traffic. There is a lower dirt parking area that services the old toilet and a network of social trails. The toilet will be replaced and relocated up to the asphalt parking area and formalized aggregate trails may be constructed.
E. The Arickaree Picnic Ground has a 1980’s era Inter-L style toilet that will be replaced in the same location. The old concrete pathway is in very poor condition and not accessible which will be replaced with an accessible concrete pathway.
1.2 LOCATION
A. Brainard Lake Recreation Area is located 23 miles northwest of Boulder, Colorado.
1.3 SPECIFICATIONS
A. The specifications establish the construction procedures and materials to be employed throughout.
1.4 GENERAL SITE CONDITIONS AND WEATHER
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 2
A. The elevation of the site is approximately 10,300 feet above mean sea level. The site generally experiences heavy snowfalls beginning in October and ending in May with snowpack covering the ground until late June to early July. The average annual temperatures range from 34 degrees F to 76 degrees F in summer and 5 to 40 degrees F in the winter. The site is generally accessible July through October.
1.5 SITE ACCESS
A. Directions from Boulder, CO: Travel approximately 10 miles north of Boulder and then turn west onto Lefthand Canyon Drive. Drive west approximately 17 miles to the town of Ward. Turn north onto Highway 72 for approximately 100 yards and then turn west onto Brainard Lake Road and travel approximately 5 miles to the project sites.
1.6 USE OF FACILITIES AND UTILITIES
A. Water may be available on-site but will need to be approved by the Forest Service.
B. There is no cell phone coverage in this area and there is no land-line phone at the site.
C. Vault toilets will not be available for contractor use at the site during the project.
D. Electrical service is not available at this site.
1.7 STAGING AREA
A. An area at or near the project site will be made available for use as a staging area. Staging areas shall be approved by the Contracting Officer (CO) prior to use. No camping will be allowed at the site. Security and clean-up of this area shall be the responsibility of the Contractor.
1.8 WORK RESTRICTIONS
A. Nonsmoking Buildings: Smoking is not permitted within the buildings or within 25 feet (8
m) of entrances.
1.9 SCHEDULE
A. Pre-work conference shall be conducted virtually with the Forest Service and the Prime.
B. The Contractor shall not work on weekends, federally recognized holidays or holiday weekends.
C. See Section 13200 Construction Progress Documentation for “Project Schedule General Requirements.”
1.10 PROTECTION OF PUBLIC
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 3
A. The Brainard Lake Recreation Area will remain open during construction and every precaution shall be taken to protect the public.
B. Install and maintain suitable barriers to ensure the protection of the public, employees, and facilities.
1. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry to the work area.
2. Erect and maintain barricades and warning signs in accordance with ANSID6.1.
3. Material may be new or used but shall be suitable for intended purpose.
4. Fences and barriers shall be structurally adequate and neat in appearance.
1.11 CONTRACTOR’S RESPONSIBILITIES
A. Confine storage of materials to areas as approved by the CO.
B. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Minimize disturbance of all undisturbed areas.
C. The Contractor at the Contractor’s expense shall repair Existing Forest Service roads and parking areas disturbed by construction activities. Repair includes any work needed to return the roads and parking areas to their existing condition before construction began and shall include replacing road aggregate if necessary.
D. All areas where the existing grass vegetation is removed or damaged, or destroyed due to construction activities, shall be decompacted, regraded, and revegetated. Contractor shall furnish and apply all approved seed in accordance with specifications.
E. The Contractor shall be responsible for all damage that results from the Contractor's action during completion of the project work. Any damage that occurs due to action of the Contractor shall be repaired at the Contractor's expense.
F. Protect trees and vegetation within project area from damage unless otherwise directed by
CO.
1.12 UTILITY LOCATIONS
A. No utilities are known to exist at the site; however, the Contractor shall be responsible for hiring a locating service to locate all utility lines including but not limited to electrical, water, and phone. This includes the Forest Service lines.
1.13 CONSTRUCTION WASTE DISPOSAL FACILITIES
A. Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.
B. Provide bear-proof waste-collection containers in sizes adequate to handle any waste deemed an attractant to wildlife. There is a lot of bear activity in this area.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 4
1.14 SITE CLEANUP AND DISPOSAL AREA
A. The Contractor shall cleanup construction debris at the completion of each day’s work.
Disposal of construction debris shall be at an established Sanitary Landfill, with all permits and related costs of disposal being the responsibility of the Contractor. The Contractor and the CO shall mutually agree to the frequency of disposal. The Contractor shall not use existing on-site trash receptacles for disposal or interim storage of construction debris.
Burning of construction debris shall not be allowed on lands administered by the Forest Service.
1.15 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
B. Contractor shall visit the project site and appraise themselves of conditions prior to bidding.
1.16 PERMITS
A. Obtain any applicable permits required by County, State, or Federal laws or regulations.
PART 2 – DEFINITION OF ITEMS AND PAYMENT
2.1 DESCRIPTION
A. This section explains what is and what is not included in each pay item; the limits or cut-off points where one item ends, and another begins; and basis of payment for work items listed in the Schedule of Items.
B. Payment: For each individual item listed here and in the Schedule of Items (SOI), payment shall be full compensation for all work related to the particular item in accordance with these specifications, and as shown on the drawings.
2.2 SCHEDULE OF ITEMS
A. Schedule of Items: The project Schedule of Items includes several sections to organize the work into Base Items and Optional Items.
1. Provide pricing for all items listed in the Schedule of Items.
2. Contract award will be made for all Base Items.
3. Optional Items will be awarded based on available project funding.
B. Determination of Quantities:
1. The contractor shall perform, or cause to be performed, all measurement of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 5
2. Quantity Measurements:
a. The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Actual Quantity (AQ), Designed Quantity (DQ) or Lump Sum Quantity (LSQ).
b. The contractor shall compute the quantities for periodic progress payments;
the Contracting Officer shall compute the quantities for the final payment based on measurements taken by the Contractor.
c. All Contractor measurements are subject to verification.
d. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.
e. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.
C. Units of Measurement:
1. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
a. Designed Quantities (DQ): Estimated quantities which are determined from contract design measurements and determinations.
b. Actual Quantities (AQ): Estimated quantities which are determined from actual measurements of completed work.
c. Linear Feet (LF): Linear feet measured horizontally.
d. Lump Sum Quantities (LSQ): These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
e. Each (EA): One complete unit, which may consist of one or more parts.
D. Base Items (BI):
1. Base Item No. 1 – Niwot Trailhead Mobilization
a. This base item consists of all materials, personnel, equipment and supplies to complete all preparatory work and operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site. This base item applies to work included in the base items only.
b. This base item consists of all survey work and construction staking necessary to adequately control the work and set horizontal and vertical alignments.
Contractor shall establish control points and perform all surveying and staking necessary to locate sidewalks, pathways, retaining walls, parking areas, and picnic sites as shown on the drawings and described in the specifications. The Contracting Officer shall approve all alignments and layouts before construction begins.
c. Payment shall be made at the contract lump-sum price.
2. Base Item No. 2 – Niwot Trailhead Demolition
a. This base item consists of all materials, personnel, equipment and supplies to complete all associated site work, demolition work and salvaging of existing
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 6
site components associated with the trailhead as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, removal, hauling, disposal, and reclamation of all disturbed areas.
b. Payment shall be made at the cost per cubic yard of the designated quantities
(DQ).
3. Base Item No. 3 – Niwot Trailhead Clearing & Grubbing complete all associated site work, stripping and stockpiling of topsoil and remove and dispose of brush, vegetation, and debris within 3-feet of the proposed improvements and includes all removal of existing trees of with a caliper of greater than 3-inches where staked in the field and/or as shown on the drawings and described in the specifications. This bid item includes tree removal for the trailhead as required in the specifications. All trees to be removed will be flagged in the field after construction staking has been completed. Work includes all associated earthwork, grading, removal, hauling, disposal, and reclamation of all disturbed areas.
b. Payment shall be made at the cost per acre of the designated quantities (DQ).
4. Base Item No. 4 – Niwot Trailhead Picnic Sites complete all associated site work, picnic site work, and furnish and install all picnic ground site furnishings including kiosks, picnic tables, bear-proof trash receptacle, and existing signage relocation as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, aggregate, wood posts, sign hardware, and reclamation of all disturbed areas.
b. Payment shall be made at the cost per each of the designated quantities (DQ).
5. Base Item No. 5 – Niwot Trailhead Compacted Aggregate Picnic Site Trails complete all associated site work and picnic site trails as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, aggregate, compaction, and reclamation of all disturbed areas.
b. Payment shall be made at the cost per square feet of the designated quantities
6. Base Item No. 6 – Niwot Trailhead Compacted Aggregate Sidewalk complete all associated site work and sidewalk as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, aggregate, compaction, and reclamation of all disturbed areas.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 7
7. Base Item No. 7 – Niwot Trailhead Rock Retaining Wall
a. This base item consists of all materials, personnel, equipment and supplies to complete all associated site work, furnish and installation of barrier rock retaining wall as shown on the drawings and described in the specifications.
Work includes all associated earthwork, grading, and aggregate.
8. Base Item No. 8 – Niwot Trailhead Timber Steps complete all associated site work, construct the new timber framed steps with compacted aggregate landings as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, aggregate, compaction, and carpentry.
9. Base Item No. 9 – Niwot Trailhead Revegetation complete all associated site work and revegetation as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, soil amendment, soil decompaction, and seed spreading.
10. Base Item No. 10 – Niwot Trailhead Parking Improvements complete all associated site work, installation of an accessible parking space, pavement striping, concrete wheel-stop installations, new sign installation, and existing sign relocations as shown on the drawings and described in the specifications. Work includes all associated pavement striping materials, signposts and hardware, and colored concrete wheel-stops.
b. Payment shall be made at the contract lump sum price.
E. Optional Bid Items (OBI):
1. Option Item No. 1 – Red Rock Lake Picnic Ground Demolition
a. This option item consists of all materials, personnel, equipment and supplies to complete all associated site work, demolition work and salvaging of existing site components associated with the picnic ground as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, hauling, disposal, and reclamation of all disturbed areas.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 8
2. Option Item No. 2 – Red Rock Lake Picnic Ground Clearing & Grubbing
a. This option item consists of all materials, personnel, equipment and supplies to complete all associated site work, stripping and stockpiling of topsoil and remove and dispose of brush, vegetation, and debris within 3-feet of the proposed improvements and includes all removal of existing trees of with a caliper of greater than 3-inches where staked in the field and/or as shown on the drawings and described in the specifications. This bid item includes tree removal for the picnic ground as required in the specifications. All trees to be removed will be flagged in the field after construction staking has been completed. Work includes all associated earthwork, grading, removal, hauling,
3. Option Item No. 3 – Red Rock Lake Picnic Ground Picnic Sites to complete all associated site work, picnic site work, and furnish and install all picnic ground site furnishings including picnic tables, and existing signage relocation as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, aggregate, wood posts, sign hardware, and reclamation of all disturbed areas.
b. Payment shall be made at the cost per each of the designated quantities (DQ).
4. Option Item No. 4 – Red Rock Lake Picnic Ground Compacted Aggregate Sidewalk to complete all associated site work and construct the new compacted aggregate sidewalk. Work includes all associated earthwork, grading, aggregate, compaction, and revegetation of disturbed areas.
5. Option Item No. 5 – Red Rock Lake Picnic Ground Timber Steps to complete all associated site work, construct the new timber framed steps with compacted aggregate landings as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, aggregate, compaction, and carpentry.
6. Option Item No. 6 – Red Rock Lake Picnic Ground Single Unit Toilet Construction to complete all associated site work, construction of a single unit toilet with a concrete vault as shown on the drawings and described in the specifications.
Work includes all associated earthwork, grading, slope stabilization, aggregate, compaction, carpentry, concrete, and reclamation of disturbed areas.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 9
7. Option Item No. 7 – Red Rock Lake Picnic Ground Revegetation to complete all associated site work and revegetation as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, soil amendment, soil decompaction, and seed spreading.
8. Option Item No. 8 – Red Rock Lake Picnic Ground New Asphalt Parking Area &
Gate
a. This option item consists of all materials, personnel, equipment and supplies to complete all associated site work, replace the picnic ground’s asphalt parking lot, pavement striping, and install a new road closure gate, as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, aggregate, compaction, bituminous, and reclamation of disturbed areas. Work also includes demolition, removal, and hauling away of existing asphalt parking area materials.
9. Option Item No. 9 – Arickaree Picnic Ground Demolition to complete all associated site work, demolition work and salvaging of existing site components associated with the picnic ground as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, hauling, disposal, and reclamation of all disturbed areas.
10. Option Item No. 10 – Arickaree Picnic Ground Clearing & Grubbing to complete all associated site work, stripping and stockpiling of topsoil and remove and dispose of brush, vegetation, and debris within 3-feet of the proposed improvements and includes all removal of existing trees of with a caliper of greater than 3-inches where staked in the field and/or as shown on the drawings and described in the specifications. This bid item includes tree removal for the picnic ground as required in the specifications. All trees to be removed will be flagged in the field after construction staking has been completed. Work includes all associated earthwork, grading, removal, hauling,
11. Option Item No. 11 – Arickaree Picnic Ground Single Unit Toilet & Sidewalk Construction
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 10
a. This option item consists of all materials, personnel, equipment and supplies to complete all associated site work, construction of a single unit toilet with a concrete vault, compacted aggregate sidewalk, as shown on the drawings, and described in the specifications. Work includes all associated earthwork, grading, slope stabilization, aggregate, compaction, carpentry, concrete, and reclamation of disturbed areas.
12. Option Item No. 12 – Arickaree Picnic Ground Revegetation to complete all associated site work and revegetation as shown on the drawings and described in the specifications. Work includes all associated earthwork, grading, soil amendment, soil decompaction, and seed spreading.
13. Optional bid items may be awarded up to 90 days after contract award if funds become available.
PART 3 – ACCIDENT PREVENTION
3.1 DESCRIPTION
A. This section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.
3.2 SUBMITTALS
A. Traffic Plan: Before on-site work begins, submit a plan to handle vehicular and pedestrian traffic for each of the project sites. Submittal shall also include a schedule.
B. Accident Prevention and Safety Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. No progress payments will be processed until the plan is received. As a minimum the plan shall include:
1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.
2. Name and contact information of supervisor responsible to carry out the plan.
3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 11
4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.
C. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
D. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
E. Submit a brief report of safety meetings and of inspections.
F. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
3.3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions: In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees: Ensure employees are physically qualified to perform assigned duties in a safe manner.
3.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 calendar days of a reportable accident, fill out and forward to the CO a CA-1 form, which may be obtained from CO.
B. All Other Accidents: Report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
3.5 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
3.6 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
B. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 12
C. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.7 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.8 SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
3.9 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. The CO will designate a hard hat area. Post the hard hat area in a manner satisfactory to the CO.
B. It is the Contractor's responsibility to require, at all times, that all those working on or visiting the site to wear hard hats and other necessary personal protective equipment. As a minimum, provide two hard hats for use by visitors. Change liners or clean and disinfect before reissuing hats.
3.10 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
PART 5 – EXECUTION REQUIREMENTS
5.1 DESCRIPTION
A. This section consists of general procedural requirements governing execution of the Work including, but not limited to, the following:
1. General installation of products.
2. Progress cleaning.
3. Protection of installed construction.
4. Correction of the Work.
5.2 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 13
B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO.
Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.
5.3 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
B. Comply with manufacturer's written instructions and recommendations for installing products.
C. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.
5.4 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.
1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.
2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).
3. Containerize hazardous and unsanitary waste materials separately from other waste.
Mark containers appropriately and dispose of legally, according to regulations.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
D. Waste Disposal: Burying or burning waste materials on-site will not be permitted. Washing waste materials down sewers or into waterways will not be permitted.
5.5 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
5.6 CORRECTION OF THE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 14
1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
PART 6 – CLOSEOUT PROCEDURES
6.1 DESCRIPTION
A. This section consists of administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Inspection procedures.
2. Project Record Documents.
3. Final cleaning.
6.2 SUBSTANTIAL COMPLETION
A. Definition of Substantial Completion: The Date certified by the Contracting Officer when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.
B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.
1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.
2. Advise Contracting Officer (CO) of pending insurance changeover requirements.
3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.
4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.
5. Prepare and submit Project Record Documents, operation and maintenance manuals, Final Completion construction photographs and photographic negatives, and similar final record information.
6. Deliver tools, spare parts, extra materials, and similar items to location designated by Government. Label with manufacturer's name and model number where applicable.
7. Complete startup testing of systems.
8. Submit changeover information related to Government occupancy, use, operation, and maintenance.
9. Complete final cleaning requirements, including touchup painting.
10. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 15
C. Inspection: Submit a written request for inspection for Substantial Completion at least 24 hours before inspection is needed. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for Final Completion.
6.3 FINAL COMPLETION
A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:
1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.
2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.
3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.
B. Inspection: Submit a written request for final inspection for acceptance at least 24 hours before inspection is needed. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
6.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.
6.5 PROJECT RECORD DOCUMENTS
A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.
BLRA DEFERED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010150 – 16
B. As-Built Drawings: Maintain and submit, upon contract completion, two physical sets and one electronic copy of As-Built Contract Drawings and Shop Drawings.
1. The contractor shall keep and maintain current red-lines on-site and shall be regularly monitored. Monthly progress payments shall be withheld if as-built drawings are not being maintained.
2. Electronic as-built drawings shall be in both PDF and AutoCAD 2018 DWG formats.
3. As-built drawings shall show the actual construction or installation where construction or installation varies from that shown originally. Require individual or entity who obtained the data, whether individual or entity is installer, subcontractor, or similar entity, to prepare the as-built drawings.
a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.
b. Record data as soon as possible after obtaining it. Record and check the as-builts before enclosing concealed installations.
4. Mark as-built sets to clearly distinguish between changes for different categories of the Work at the same location.
a. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.
6.6 FINAL CLEANING
A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.
B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:
1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.
2. Remove tools, construction equipment, machinery, and surplus material from Project site.
3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.
Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.
D. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.
END OF SECTION
BLRA DEFERRED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010200-1
ARAPAHO & ROOSEVELT NATIONAL FORESTS CONTROL OF MATERIALS
SECTION 010200
CONTROL OF MATERIALS
PART 1 - GENERAL
1.01 HANDLING MATERIALS
A. All materials shall be transported and handled to preserve their quality and fitness for the work.
B. Aggregates shall be stockpiled, loaded, and transported in a manner that will preserve specified gradation and avoid contamination. Stockpiles of aggregate having different gradations shall not be intermingled.
1.02 SAMPLING & TESTING
A. For contractor-furnished sources, the contractor shall submit test results and a Certificate of Compliance that states that the aggregate meets the contract requirements.
1.03 MATERIAL SOURCES
A. Designated Sources. Specific government designated sources are not available.
B. Contractor-Furnished Sources. Sources shall be non-Forest Service sources supplied from a commercial rock source.
C. Quality testing in conformance with applicable requirements and acceptable to the Engineer to establish the equivalency of the product shall be the responsibility of the contractor. Test results shall be furnished to the CO.
END OF SECTION 010200
BLRA DEFERRED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010250-1
ARAPAHO & ROOSEVELT NATIONAL FORESTS MEASUREMENT & PAYMENT
SECTION 010250
MEASUREMENT & PAYMENT
PART 1 – GENERAL
1.01 MEASUREMENT & PAYMENT
A. Measurement and payment for contract work will be made only for and under those pay items included in the SCHEDULE OF ITEMS. All other work and materials will be considered as included in the payment for items shown.
1.02 DETERMINATION OF QUANTITIES
The following measurements and calculations are used to determine contract quantities.
A. For individual construction items, longitudinal and lateral measurements for area computations will be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for seeding, mulching, geotextiles, netting, erosion control blankets, and sodding will be along slope lines.
B. The average end area method will be used to compute volumes of excavation or embankment. However, if in the judgment of the CO, the average end area method is impractical, measurement will be made by volume in hauling vehicles or by other three-dimensional methods.
C. Structures will be measured according to neat lines SHOWN ON THE
DRAWINGS or as altered by the CO in writing to fit field conditions.
D. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, and underdrains, measurements will be made parallel to the base or foundation upon which the structures are placed. Pipe and pipe arch culverts shall be measured along center of invert and arches shall be measured at spring line.
E. For standard manufactured items identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances will be accepted.
1.03 UNITS OF MEASUREMENT
A. Payment will be by units defined and determined according to U.S. Standard measure and by the following:
a. Lump Sum. Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete
BLRA DEFERRED MAINTENANCE PHASE #1 – REC. SITE IMPROVEMENTS 010250-2
ARAPAHO & ROOSEVELT NATIONAL FORESTS MEASUREMENT & PAYMENT
the work for that item.
b. Linear Feet (LF). One linear foot measured horizontally.
1.04 METHODS OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:
a. Designed Quantities (DQ). These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:
i. As a result of changes in the work authorized by the CO.
ii. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
iii. As a result of the contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item
iv. quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
b. Actual Quantities (AQ). These quantities are determined from measurements of completed work. The contractor shall be responsible for measuring all "AQ" items.
c. Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They will not be measured.
END OF SECTION 010250
BLRA DEFERRED MAINT. PHASE #1 – REC. SITE IMPROVEMENTS 013200-1
ARAPAHO & ROOSEVELT NATIONAL FORESTS PROGRESS DOCUMENTATION
SECTION 013200
CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Contractor's Construction Schedule.
2. Daily construction reports.
3. Field condition reports.
B. See Division 1 Section "Price and Payment Procedures" for submitting the Schedule of Values.
1.2 SUBMITTALS
A. Contractor's Cost Loaded Construction Schedule: Submit one electronic copy of initial schedule.
1. Include type of schedule (Initial or Updated) and date on label.
B. Daily Construction Reports: Submit one electronic copy at weekly intervals.
C. Field Condition Reports: Submit one electronic copy at time of discovery of differing conditions.
1.3 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Contractor's Cost Loaded Construction Schedule with the list of subcontracts, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from parties involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 – PRODUCTS (Not Used)
PART 3 - EXECUTION
BLRA DEFERRED MAINT. PHASE #1 – REC. SITE IMPROVEMENTS 013200-2
3.1 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
1. List of workers, including subcontractors, at Project site.
2. Summary of work completed.
3. Equipment at Project site.
4. Material deliveries.
5. High and low temperatures and general weather conditions.
6. Accidents.
7. Stoppages, delays, shortages, and losses.
8. Meter readings and similar recordings.
9. Orders and requests of authorities having jurisdiction.
10. Services connected and disconnected.
11. Equipment or system tests and startups.
B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
3.2 PROJECT SCHEDULE GENERAL REQUIREMENTS
A. Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15
Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
B. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 60 days of date established for the Notice of Award.
3.3 BASIS FOR PAYMENT AND COST LOADING SCHEDULE
A. The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN or Bid Schedule Item must equal the value of the CLIN or Bid Schedule Item.
B. Activity cost loading must be reasonable and without front-end loading. Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
C. Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial, or periodic schedule updates and subsequent rejection of payment requests until compliance is met. In the event that the Contracting Officer directs schedule revisions and
BLRA DEFERRED MAINT. PHASE #1 – REC. SITE IMPROVEMENTS 013200-3
those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
3.4 PROJECT SCHEDULE DETAILED REQUIREMENTS
A. Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
1. Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 workdays or 30 calendar days.
2. Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
B. Contract Milestones and Constraints: Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates.