This document is a Request for Proposals (RFP) for the Carolyn Creek Trail Bridge (GAOA) project located in the Humboldt-Toiyabe National Forest near Elko, Nevada. The U.S. Forest Service is seeking a contractor to provide all materials, labor, equipment, and other incidentals necessary to design, fabricate, deliver, and install a 27-foot span glulam timber trail bridge with metal railing. The work also includes removing and disposing of the existing bridge.
The project is a total small business set-aside with an estimated value between $50,000 and $110,000. The site is accessible only by hiking trail, and the contractor may need to use a helicopter to transport materials. The period of performance requires all construction to be completed no later than September 30, 2025. Contractor questions are due by August 2, 2024, and proposals are due by August 6, 2024. Evaluation and award factors are outlined in Sections L and M of the RFP.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1113044
U.S FOREST SERVICE (USDA)
CSA INTERMOUNTAIN 8
324 25TH STREET
OGDEN, UT 84401-2310
40LT
U.S FOREST SERVICE (USDA)
ATTN: ELIZABETH RATCLIFF
elizabeth.ratcliff@usda.gov
a. NAME
Elizabeth Ratcliff
b. EMAIL elizabeth.ratcliff@usda.gov
(GAOA)
x
07/10/20241240LT24R0017
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Project Title: Carolyn Creek Trail Bridge (GAOA) The contractor shall provide all materials, labor, equipment, tools, transportation, supervision, expertise, and other incidentals necessary, except as otherwise provided, to successfully complete this project.
Set Aside: Total Small Business Set-Aside (FAR 19.5)
Magnitude: Between $50,000.00 to $110,000.00
Location: This project is located on a hiking trail with no vehicle access. From Elko, NV drive southeast on NV-227 for 20 miles toward Lamoille, NV. Turn right(South)on NF-660, Lamoille Canyon Road, and drive 11.7 miles to the roads end parking lot. Hike on foot up the island lake trail 1.4 miles to the project site. The bridge is located at the following coordinates: 40.616571, -115.376915
Period of Performance: All construction work to be completed NLT 9/30/2025 (60 Days After NTP)
Site Visit: 07/30/2024 at 11:00 AM PT (Not Mandatory)
Contractor Questions Due No Later Than: 08/02/2024 12:00 PM PT. Use document titled "Contractor Questions and Answers Template" to write down your questions and send it to elizabeth.ratcliff@usda.gov before 08/02/2024 12:00 PM PT.
Request for Proposal Solicitation Close Date: 08/06/2024 12:00 PM PT
Instructions to Bidders: See Section L (Page 40) Evaluation/Award Factors: See Sections L&M (Pages 40 and 46).
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
60 60 calendar days and complete it within ________________ ________________ calendar days after receiving
FAR 52.211-10
08/06/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ _____________ (hour) local time
________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected .
STANDARD FORM 1442 (Rev. 8/2014)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
12:00 PM PT
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND COMPLETE ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE # AND EMAIL ADDRESS:
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
U.S FOREST SERVICE (USDA)
CSA INTERMOUNTAIN 8
324 25TH STREET
OGDEN, UT 84401-2310
40LT
31a. NAME OF CONTRACTING OFFICER (Type or print)
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 8/2014) BACK
INVOICE PROCESSING PLATFORM (IPP)
ALL INVOICES MUST BE SUBMITTED
ELECTRONICALLY THROUGH THE
INVOICE PROCESSING PLATFORM (IPP)
AT WWW.IPP.GOV
SAM UEI NUMBER: _______________________
NOTE: ONLY OFFERORS WITH AN ACTIVE SAM REGISTRATION MAY SUMBIT BIDS
Grand Total: ______________
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 46
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
1240LT24R0017
Period of Performance: 08/01/2025 to 09/30/2025
0001 Mobilization (151-01) 1 LS
0002 Soil Erosion and Pollution Control (157-01) 1 LS
0003 Removal and Disposal of Bridge (203-01) 1 LS
0004 Fabrication and Delivery of Glulam Deck Trail 1 LS
Bridge and Steel Railing to Staging Area (557-01)
0005 Install Prefabricated Glulam Bridge (557-02) 1 LS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
(Estimated Date)
GRAND TOTAL: _________
Note: LS= Lump Sum
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SCHEDULE OF ITEMS
Item/Sub Number Description Quantity Unit of
Issue Unit Price Total Item Amount
0001 Mobilization (151-01) 1 LS 0002 Soil Erosion and Pollution Control (157-01) 1 LS 0003 Removal and Disposal of Bridge (203-01) 1 LS
Fabrication and Delivery of Glulam Deck Trail Bridge and Steel Railing to Staging Area (557-01)
1 LS
0005 Install Prefabricated Glulam Bridge (557-02) 1 LS
B.2 SCHEDULE NOTES
a) Items labeled as optional are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with the terms and conditions of this contract.
b) One award will be made from this solicitation, contractors must submit pricing for all items.
c) All bond costs shall be included in mobilization costs.
ElizabethRatcliff Highlight
FILL OUT ALL HIGHLIGHTED SECTIONS
ElizabethRatcliff
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK GENERAL
SPECIFICATIONS
CAROLYN CREEK TRAIL BRIDGE
1.1 SCOPE OF CONTRACT
A. This project consists of design (taking the government drawings to a fabricator and having them do shop drawings), purchasing, delivering, and installing a 27-foot span glulam timber trail bridge with metal railing. The site is roughly one mile up a hiking trail with a 10% grade (approx.) with two switchbacks and may require the use of a helicopter for transport. In this case, the contractor would be responsible for coordinating the weight of the various bridge components with the available helicopter. The site is not accessible by a vehicle and the topography around the existing bridge is very steep. Existing rock/ stacked abutments will remain in place and be used as abutments for the new bridge.
A staging area (approx. 3,200 SF) will be made available for bridge materials at the Roads End trailhead at the end of Lamoille Canyon Road, which is where the trail to the site begins.
B. The existing bridge will be removed and disposed of. All nonnative components must be removed from the forest.
C. Quantities associated with this work are identified in the Schedule of Items.
D. All work shall be in compliance with the contract documents. Work includes, but is not limited to purchase, transportation, and installation of a new glulam trail bridge placed on preexisting abutments as per the attached plans, and the removal of the existing bridge structure and components.
The Contracting Officers Representative (COR) will designate a staging/laydown/assembly area at the construction site. Limited camping for project personnel at nearby campgrounds will be allowed based on availability with permission of the COR. Staging materials for the project will be allowed in designated areas if approved in writing by the COR at the time of the project implementation. Any detours or disruptions to public access will require prior notification and approval from the COR and CO. The contractor must obtain this approval a minimum of 14 days prior to any disruptive action.
- Depending on the snow year, the site is commonly accessible between July 4 and October 30 on most years.
E. Bridge installation shall conform to FP-14 Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects.
1.2 RESOURCE PROTECTION MEASURES (RPM)
The contractor shall adhere to the following Resource Protection Measures (RPM) for each resource area:
A. General
1. The contractor will be briefed on minimum impact/leave no trace ethics prior to starting work and will follow minimum impact/leave no trace ethics while working at the site.
2. Pack stock used to support project work will be tied and/or held in such a way as to minimize soil disturbance and avoid loss of native/desirable vegetation.
3. Bridge design and materials will be compatible with the scenic setting.
4. Old bridge materials: Nails, bolts, metal, timber decking, timber railing, concrete and any other non-native bridge materials will be removed from the forest or disposed of as per COR direction.
5. Staging of materials, tools and supplies will be coordinated with the COR to ensure safety for all and to avoid conflicts with the general public and other users of the trailhead and trail.
6. Borrow sources for gravel and fine material will be weed-free, located off trail, and rehabilitated to a natural appearance following use. Borrow shall be obtained only from areas designated by the COR.
B. Fisheries/Hydrology
1. Clearing of riparian vegetation will be minimized to that necessary for bridge construction and generally limited to the immediate bridge sites to conserve existing vegetation for shade and stream bank stability.
2. Native materials collected on site (e.g., logs, slash, rock, gravel, fine material, etc.)
for construction and rehabilitation activities will be collected from areas outside of the ordinary high-water mark (i.e., the bank full channel).
3. Best Management Practices (BMPs) for using treated wood in aquatic environments will be followed.
4. All tools and boots/waders will be cleaned of mud, dirt, or plant materials before entering the National Forest and when leaving the work site to prevent the introduction or spread of aquatic nuisance species.
C. Wildlife
1. To eliminate the chance of habituating wildlife, food and garbage will be stored in a hard sided vehicle or other approved bear resistant container throughout the duration of the project. Food and other bear attractants will be stored in compliance with current best practices.
D. Cultural Resources
1. If previously unrecorded heritage resources are encountered during project implementation, activities will be halted, and the CO will be notified. The CO will consult with the archeologist. If necessary, additional RPMs will be devised in consultation with the State Historic Preservation Office.
E. Noxious Weeds
1. In order to prevent the introduction or potential spread of nonnative, or noxious weeds the contractor will be required to clean all equipment, tools, and supplies prior to entering the National Forest.
2. Implement required weed protection measures outlined in Forest Service Manual 2080 (Noxious Weed Management) including:
a. The Forest requires all hay and straw to be certified Weed Free, and the contractor will be required to furnish proof of certification. Stock should be fed weed free feed 1-2 days prior to entering the National Forest. Brush stock to remove any weed seed prior to entering the Forest.
1.3 PROJECT LOCATION
A. This project is located on a hiking trail with no vehicle access. From Elko, NV drive southeast on NV-227 for 20 miles toward Lamoille, NV. Turn right (South) on NF-660, Lamoille Canyon Road, and drive 11.7 miles to the road’s end parking lot. Hike on foot up the island lake trail 1.4 miles to the project site. The bridge is located at 40.6167° N, - 115.377° W.
1.4 SITE INFORMATION AND LIMITATIONS
A. The trail and or bridge may be closed when needed and approved by the Forest Service, such as during construction. The Contractor must notify the Forest Service 14 days in advance of any trail or bridge closure. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access with fencing.
B. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, crossmembers, motor mounts, and underneath steps, running boards, and front bumper/brush guard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
C. Utilities are not available at the site for construction purposes.
1.5 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.6 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the COR.
B. Another contract may be occurring simultaneously at the Road’s End parking lot in Lamoille Canyon. Contractor is expected to coordinate staging.
1.7 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.8 PERIOD OF PERFORMANCE
A. Anticipated July 29, 2024
1.9 CONTRACT TIME
A. 60 Calendar Days for ground disturbing activities from Notice to Proceed (NTP). All work to be complete no later than September 30, 2025.
1.10 SPECIFICATIONS
A. FP-14 Standard Specifications for Construction of Roads and Bridges on Federal
Highway Projects and Forest Service Supplement as detailed on drawings.
1. Copies are available electronically on the U.S. DEPARTMENT OF TRANSPORTATION Federal Highways Administration website at https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf
B. Submittals are required to be approved by CO, as table below:
Submittal # Section Title Required
Submittal Schedule Notes
C-01 General Specifications
Construction Schedule
45 days before construction
Simple traffic plan for trail users and staging area
C-02 General Specifications
Safety Plan 30 days before construction
Safety Plan
C-03 General Specifications
Traffic Control Plan
30 days before construction
Traffic control plan (trail users, forest road impact)
C-04 General Specifications
Erection/Remova l plan
30 days before construction
See drawings. Full equipment list required.
0001 Treated Timber Footbridge
Shop Drawings As available See drawings
0002 Treated Timber Footbridge
Certificate of Inspection
Upon delivery See drawings. Certificate of Inspection showing AWPA/WWPI compliance https://flh.fhwa.dot.gov/resources/specs/fp-14/fp14.pdf ElizabethRatcliff
SPECIFICATIONS FOR LINE ITEMS
1.11 APPENDIX: REFERENCE MATERIAL
FP-14 Subsection 109.05 Scope of Payment. Payment for contract work is provided, either directly or indirectly, under the pay items listed in the bid schedule.
Direct payment. Payment is provided directly under a pay item listed in the bid schedule when one of the following applies:
1. The work is measured in the Measurement Subsection of the Section ordering the work and the bid schedule contains a pay item for the work from the Section ordering the work.
2. The Measurement Subsection of the Section ordering the work, references another Section for measuring the work and the bid schedule contains a pay item for the work from the referenced Section.
Indirect payment. Work for which direct payment is not provided is a subsidiary obligation of the Contractor. Payment for such work is indirectly included under other pay items listed in the bid schedule. This includes instances when the Section ordering the work references another Section for performing the work and the work is not referenced in the Measurement Subsection of the Section ordering the work.
Compensation provided by the pay items included in the bid schedule is full payment for performing contract work in a complete and acceptable manner. Risk, loss, damage, or expense arising out of the nature or prosecution of the work is included in the compensation provided by the pay items. Work measured and paid for under one pay item will not be paid for under other pay items.
The quantities listed in the bid schedule are approximate unless designated as a contract quantity.
Limit pay quantities to the quantities staked, ordered, or otherwise authorized before performing the work. Payment will be made for the actual quantities of work performed and accepted or material furnished according to the contract. No payment will be made for work performed in excess of that staked, ordered, or otherwise authorized.
1.12 PROJECT MAP PHOTOS
SECTION D - PACKAGING AND MARKING
D.1 PACKING AND MARKING
All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.
D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E - INSPECTION AND ACCEPTANCE
E.1 CLAUSES
52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (AUG 1996)
SECTION F - DELIVERIES OR PERFORMANCE
F.1 CLAUSES
52.211-13 Time Extensions (SEP 2000) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 60 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use no later than 60 days after NTP. The time stated for completion shall include final cleanup of the premises.
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within 15 days after the date of contract award. The conference will be held virtually on Microsoft Teams.
G.2 INVOICES & PAYMENTS
All invoices are to be submitted via the electronic Invoice Processing Platform (IPP) System.
https://www.ipp.gov/index.htm Register at: https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account. These items must be uploaded as Attachments, and itemized invoices must include:
• Name and address of the Contractor (include phone number, mailing address, person to notify if there are issues with the invoice).
• Invoice date and invoice number;
• Contract number;
• Taxpayer Identification number;
• Description, unit, and price of items being invoiced, Date of services or completion;
• Shipping and Payment Terms
Certified payrolls for Construction: Contractor and all subcontractors. Final Payment - Following completion and acceptance of the work (including return of Government-furnished property and site cleanup), Final payment will made within 30 calendar days after presentation of a properly executed invoice. Final payrolls shall be marked “Final”. Contractor Notification & Release of Claims (FS-6300-16) for Final Payment. A contractor notification and release of all claims form shall be completed by the COR and the contractor. The completed form shall be uploaded as an attachment with the Final Payment.
https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm https://www.ipp.gov/vendors/enrollment-vendors.htm
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
452.228-71 Insurance Coverage (NOV 1996) Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of $500,000 per occurrence.
(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
452.237-74 Key Personnel (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel:
Project Foreman.
(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I.1 CLAUSES
52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Federal Acquisition Regulation (FAR) Clauses:
https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:
https://www.acquisition.gov/agar (AGAR clauses begin with 452) FAR and AGAR Deviations to clauses may be viewed at: Policies & Regulations | USDA
52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(MAY 2014)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights (NOV 2023) (Whistleblower
Guidance to contractor employees) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or
Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY
2011) 52.204-7 System for Award Management (OCT 2018) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN
2020) 52.204-12 Unique Entity Identified Maintenance (OCT 2016) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or
Provided by Kaspersky Lab Covered Entities (DEC 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video
Surveillance Services or Equipment (NOV 2021) 52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors
Debarred, Suspended, or Proposed for Debarment (NOV 2021) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.usda.gov/da/ocp/ppd/policies-regulations https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK https://view.officeapps.live.com/op/view.aspx?src=https%3A%2F%2Fcontent.govdelivery.com%2Fattachments%2FUSDAPSD%2F2023%2F04%2F04%2Ffile_attachments%2F2456937%2FWhistleblower%2520Guidance.docx&wdOrigin=BROWSELINK
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.211-13 Time Extensions (SEP 2000) 52.214-3 Amendments to Invitations for Bids (DEC 2016) 52.214-4 False Statements in Bids (APR 1984) 52.214-5 Submission of Bids (DEC 2016) 52.214-6 Explanation to Prospective Bidders (APR 1984) 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (NOV 1999) 52.214-12 Preparation of Bids (APR 1984) 52.214-15 Period for Acceptance of Bids (APR 1984) 52.214-16 Minimum Bid Acceptance Period (APR 1984) 52.214-18 Preparation of Bids – Construction (APR 1984) 52.214-21 Descriptive Literature (APR 2002) 52.214-34 Submission of Offers in the English Language (APR 1991) 52.214-35 Submission of Offers in U.S. Currency (APR 1991) 52.215-1 Instruction to Offerors – Competitive Acquisition (NOV 2021) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.215-19 Notification of Ownership Changes (OCT 1997) 52.216-4 Economic Price Adjustment-Labor and Material (JAN 2017) 52.216-7 Allowable Cost and Payment (AUG 2018) 52.216-8 Fixed Fee – Construction (JUN 2011) 52.216-23 Execution and Commencement of Work (APR 1984) 52.217-3 Evaluation Exclusive of Options (Apr 1984) 52.217-4 Evaluation of Options Exercised at Time of Contract Award (JUN 1988) 52.217-5 Evaluation of Options (JUL 1990) 52.217-6 Option for Increased Quantity (MAR 1989) 52.219-1 Small Business Program Representations (Feb 2024) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns (SEP 2023) 52.219-14 Limitations on Subcontracting (OCT 2022)
☒ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.
52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY
2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
(MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-30 Construction Wage Rate Requirements - Price Adjustment (None or Separately
Specified Pricing Method) (AUG 2018) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC
2010) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-54 Employment Eligibility Verification (MAY 2022) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN
2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction
Contracts (SEP 2013) 52.223-3 Hazardous Material Identification and Material Safety Data (FEB 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential
Hydrofluorocarbons (Jun 2016) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction
Contracts (AUG 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN
2020) 52.223-20 Aerosols (JUN 2016) 52.223-21 Foams. (JUN 2016) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT
2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023)
52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)
Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-16 Quantity Surveys (APR 1984)
Alternate 1 (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)
Alternate I (APR 1984) Alternate II (APR 1984)
52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994)
Alternate I (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)
Alternate I (SEP 1996) 52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or
Removal of Improvements) (APR 2012) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV
1996) 452.236-70 Additive or Deductive Items (FEB 1988) 452.236-71 Prohibition Against the Use of Lead-Based Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archaeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)
52.204-27 Prohibition on a Byte Dance Covered Application (JUN 2023)
(a) Definitions. As used in this clause— Covered application means the social networking service TikTok or any successor application or service developed or provided by Byte Dance Limited or an entity owned by Byte Dance Limited.
Information technology, as defined in 40 U.S.C. 11101(6)—
(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a contractor under a contract with the executive agency that requires the use—
(i) Of that equipment; or
(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;
(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but
(3) Does not include any equipment acquired by a Federal contractor incidental to a Federal contract.
(b) Prohibition. Section 102 of Division R of the Consolidated Appropriations Act, 2023 (Pub.
L. 117-328), the No TikTok on Government Devices Act, and its implementing guidance under Office of Management and Budget (OMB) Memorandum M-23-13, dated February 27, 2023, “No TikTok on Government Devices” Implementation Guidance, collectively prohibit the presence or use of a covered application on executive agency information technology, including certain equipment used by Federal contractors. The Contractor is prohibited from having or using a covered application on any information technology owned or managed by the Government, or on any information technology used or provided by the Contractor under this contract, including equipment provided by the Contractor’s employees; however, this prohibition does not apply if the Contracting Officer provides written notification to the Contractor that an exception has been granted in accordance with OMB Memorandum M-23-13.
(c) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts, including subcontracts for the acquisition of commercial products or commercial services.
(End of Clause)
52.217-7 Option for Increased quantity – Separately Priced Line Item (MAR 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 45 days.
(End of Clause)
52.225-9 Buy American Act - Construction Materials (OCT 2022)
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if–
(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of https://www.acquisition.gov/far/part-2#FAR_2_101 https://www.acquisition.gov/far/part-25#FAR_25_105 foreign iron and steel constitutes less than 5 percent of the cost of all component used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows: None
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505 particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent…