Site Visit Questions and Answers.pdf

PDF 87 KB Posted

Attached to
GAOA Crow Valley Olive Ridge Water System Federal contract opportunity
Solicitation number
1240LT24B0001
Issued by
Department of Agriculture Forest Service R2-Rocky Mountain Region

About this file

The document provided is a set of questions and answers related to a site visit for the GAOA Crow Valley Olive Ridge Water System federal contract opportunity. The key details are:

The contract requires a licensed professional to perform well work, as specified in Section 33 11 16 1.4 of the quality assurance requirements. No discharge permit is needed, and the compaction requirements are detailed in Section 31 22 50 of the specifications. There are no specific brushing requirements, and any vegetation removal should be included in the schedule of items.

The federal contract opportunity is for the GAOA Crow Valley Olive Ridge Water System, with a solicitation number of 1240LT24B0001. All questions are due by May 29, 2024 and should be sent to paula.sales@usda.gov, per the instructions in Section L. The contracting agency is the Department of Agriculture Forest Service R2-Rocky Mountain Region.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Visit Questions and Answers

1. Does the person doing the well work need to be a licensed professional?

Yes, Section 33 11 16

1.4 Quality Assurance

A. Regulatory Requirements:

1. Comply with standards of authorities having jurisdiction for potable water service piping, including materials, installation, testing, and disinfections.

2. Does a discharge permit need to be acquired?

No permit required.

3. What are the compaction requirements?

See specification 31 22 50 Earthwork

3.15 Compaction of Backfill and Fills

4. What are the brushing requirements?

No specific brushing requirements. Any vegetation removal should be included for specific contract line items in the schedule of items.