1240LT22R0011 12062021 rev 3.pdf

PDF 351 KB Posted

Attached to
GAOA Willow Creek Bridge Replacement- Sawtooth NF Federal contract opportunity
Solicitation number
1240LT22R0011
Issued by
Department of Agriculture Forest Service R4-Intermountain Region

About this file

This solicitation requests proposals for a bridge replacement project. Key details include replacing an existing nail laminated timber bridge and abutments with a new steel superstructure, concrete grade beams, gravel wear surface, installing rip-rap and four Type 3 object markers. The project is located on the Sawtooth National Forest in Elmore County, Idaho. The estimated price range is between $250,000 to $500,000. Proposals are due by January 13, 2022. The performance period is 120 calendar days. This set-aside opportunity is for a 100% Women-Owned Small Business concern.

View the file

Other files for this federal contract opportunity

Other files attached to GAOA Willow Creek Bridge Replacement- Sawtooth NF, newest first.
File Type Posted
Sol_1240LT22R0011_Amd_ 0002.pdf PDF
Sol_1240LT22R0011_Amd_0001.pdf PDF
Attachment 2 G-062 WILLOW CREEK FINAL PLANS 6_7_21.pdf PDF
Attachment 3 Wage Determination.pdf PDF
Attachment 1 SPECS WILLOW CREEK PRELIM FSSS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1046410

USDA-FS CSA INTERMOUNTAIN 8

ATTN KELLIE SHAW

1405 HOLLIPARK DRIVE

IDAHO FALLS ID 83401

40LT

Kellie Shaw, Contracting Officer kellie.shaw@usda.gov

SHERRI MITCHELL 334-333-0223

1046410 x 12/07/2021

1240LT22R0011

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

WILLOW CREEK BRIDGE REPLACEMENT SAWTOOTH NATIONAL FOREST ELMORE COUNTY, IDAHO

Contractor shall furnish all labor, materials, tools, equipment and supervision to replace the Willow Creek Bridge located in Elmore County, Idaho. This project consists of removing an existing nail laminated timber bridge and abutements, furnishing and installing a new steel superstructure in accordance with specifications and drawings.

Magnitude of Construction: Between $250,000 and $500,000

100% Set Aside - Women-Owned Small Business (WOSB)

NAICS: 237310 Small Business Size: $39.5M

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 120 calendar days and complete it within ________________ ________________ calendar days after receiving

01/13/2022

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

KELLIE SHAW

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 38

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

1240LT22R0011

Delivery: 120 Days After Notice to Proceed

Delivery Location Code: 0270

USDA FOREST SERVICE

SAWTOOTH NATIONAL FOREST

617 SOLDIER ROAD

FAIRFIELD ID 83327-9999 US

0001 GAOA Willow Creek Bridge Replacement - SEE B.1

SCHEDULE OF ITEMS

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No: 1240LT22R0011 Project Name: WILLOW CREEK BRIDGE REPLACEMENT

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

B.2 Payment for Bond Premiums

B.3 Basis for Payment

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATON

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 CONTRACT TIME

C.5 ANTICIPATED START DATE

C.6 INSPECTION AND ACCEPTANCE

C.7 TECHNICAL SPECIFICATIONS

SECTION D--PACKAGING AND MARKING

D-1 PACKING AND MARKING

D-2 PROJECT LABELING FOR OFFICIAL COORESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS

L.1 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROPOSAL EVALUATION

M.2 TECHNICAL EVALUATION FACTORS

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS

Item No. Description Method of

Measurement Unit Qty Unit Cost Total

15101 Mobilization LSQ LS 1 $ $ 15221 Construction Survey and taking LSQ LS 1 $ $ 15713 Soil erosion and pollution control LSQ LS 1 $ $ 20102 Clearing and Grubbing, Slash Treatment

Methods for Tops and Limbs (f), Logs (i), and Stumps (f)

LSQ LS 1 $ $

20305 Removal of Existing Timber Bridge, Disposal Method (a)

LSQ LS 1 $ $

20401 Roadway Excavation and Embankment, Compaction Method 6 (Government Source)

LSQ LS 1 $ $

20806 Structure Excavation and Backfill LSQ LS 1 $ $ 25101 Placed Riprap, Class 4 (Commercial Source

Structure Excavation and Backfill)

AQ CY 135 $ $

30101 Aggregate surface course, Grading (S), Compaction method (B) (Commercial Source)

AQ CY 113 $ $

55201 26'x18"x30" Precast Concrete Grade Beam CQ EA 2 $ $ 57102 60' Long x 24' Wide Prefabricated Bridge

Superstructure, Design, Fabricate, Transport, and Install (includes railing and bulkhead)

LSQ LS 1 $ $

63305 Object Markers (Type 3) CQ EA 4 $ $

TOTAL PROPOSED $________________

* Designated Method of Measurement:

CQ – Contract Quantities, DQ - Designed Quantities, AQ - Actual Quantities, LSQ - Lump Sum Quantities, SQ - Staked Quantities

B.2 Payment for Bond Premiums Payment for bond premiums in accordance with FAR Clause 52.232-5, Payments Under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 – Mobilization.

B.3 Basis for Payment Payment will be made upon completion and acceptance according to pay items listed in the Schedule of Items

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

This project consists of removing an existing nail laminated timber bridge and abutments, furnishing and installing a new steel superstructure, concrete grade beams, a gravel wear surface on bridge and approaches, installing rip-rap, and installing 4 Type 3 object markers on glued-laminated guard posts. No stream crossings will be allowed and as such, contractor should be prepared to have equipment on both sides of the stream.

C.2 PROJECT LOCATON

This project is located on FS Road 70227; Elmore County; Township 7 North, Range 14 East, Section 25; approximately 7 miles east of Featherville Idaho. The project may be reached by following State Highway 20 from Fairfield headed west approximately 20 miles then turn north toward Pine. Follow the Pine-Featherville Road for 32.5 miles until you reach the town of Featherville. Driving though Featherville stay on the asphalt road and follow it as it turns and heads east.

Continue for 7 miles on the road, along the South Fork of the Boise River until you reach Willow Creek.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

The estimated price range of this project is between $250,000 and $500,000

C.4 CONTRACT TIME

120 Calendar Days

C.5 ANTICIPATED START DATE

Planning and Bridge Fabrication – Winter of 2022 Construction - Spring of 2022.

C.6 INSPECTION AND ACCEPTANCE

Periodic field inspection will be made by the Contracting Officer’s Representative (COR) or the COR’s designative inspector. Work not completed to Contract specifications shall be revoked without additional compensation to the contractor.

C.7 TECHNICAL SPECIFICATIONS

"Standard Specifications for Construction of Roads & Bridges of Federal Highway Projects" (FP-14, U.S. Customary Units) are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract. Bidders are cautioned to carefully review these standard specifications prior to submission of bids. The FP-14 can be found at the following website:

https://highways.dot.gov/federal-lands/specs

Note: The referenced specifications are presented in U.S. Customary units.

The Forest Service has supplemental specifications to the FP-14 which can be found in the Willow Creek Bridge Replacement Forest Service Supplemental Specifications section of this contract. The supplemental specifications for this project include:

FSSS 101 Terms, Format, and Definitions FSSS 102 Bids, Award, and Execution of Contract FSSS 103 Scope of Work FSSS 104 Control of Work FSSS 105 Control of Material FSSS 106 Acceptance of Work https://highways.dot.gov/federal-lands/specs

FSSS 107 Legal Relations and Responsibility to the Public FSSS 108 Prosecution and Progress FSSS 109 Measurements and Payment FSSS 151 Mobilization FSSS 152 Construction Survey and Staking FSSS 153 Contractor Quality Control FSSS 155 Schedules for Construction Contracts FSSS 156 Public Traffic FSSS 157 Soil Erosion and Sediment Control FSSS 171 Weed and Disease Prevention FSSS 201 Clearing and Grubbing FSSS 203 Removal of Structures and Obstructions FSSS 204 Excavation and Embankment FSSS 205 Rock Blasting FSSS 208 Structure Excavations and Backfill for Selected Major Structures FSSS 322 Minor Aggregate Courses FSSS 552 Structural Concrete FSSS 556 Bridge Railing FSSS 557 Timber Structures FSSS 571 Prefabricated Bridges FSSS 703 Aggregate FSSS 705 Rock

The Willow Creek and South Fork of the Boise River has ESA listed fish, (bull trout). No in-stream work or stream crossings will be allowed other than adjacent to the stream to remove the existing timber abutments.

The South Fork of the Boise River Road leads to some private land and houses, the road closure will be kept to a minimum with no more than two weeks.

Pump intake screens shall meet NMFS screening criteria (NMFS 2008). For example, they will have openings not exceeding 3/32-inch diameter and a surface area proportionate to the pump intake capacity. The objective is to provide a positive barrier to fish entrainment and maintain a velocity of no more than 0.4 feet per second at the surface of the intake screen to avoid impingement.

Technical Requirements All items shown or noted on the drawings, which are not specifically bid items, are considered incidental items. The cost of furnishing and installing all incidental items will not be paid for separately but shall be included in the unit price bid for other items unless noted otherwise.

C.8 452.211-72 Statement of Work/Specifications (FEB 1988) The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C.9 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

SECTION D--PACKAGING AND MARKING

D-1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D-2 PROJECT LABELING FOR OFFICIAL COORESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.211-13 Time Extensions (SEP 2000) 52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 01 September 2022. The time stated for completion shall include final cleanup of the premises.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

452.215-73 Post Award Conference (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within TBD days after the date of contract award. The conference will be held at TBD.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel: Project Manager and Job Superintendent

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.

Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses: https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses: https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at: https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-13 Contractor Code of Business Ethics and Conduct (JUN 2020) 52.203-14 Display of Hotline Poster(s) (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights & Requirements to Inform Employees of Whistleblower

Rights (JUN 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) 52.204-2 Security Requirements (MAR 2021) Alternate II (APR 1984) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-15 Service Contract Reporting Requirements for Indefinite Delivery Contracts (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky

Lab and Other Covered Entities (JUL 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or

Equipment (AUG 2020) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or

Proposed for Debarment (JUN 2020) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.210-1 Market Research (JUN 2020) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.215-8 Order of Precedence—Uniform Contract Format (OCT 1997) 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data (AUG 2011) 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data-Modifications (JUN 2020) 52.215-12 Subcontractor Certified Cost or Pricing Data (JUN 2020) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.215-13 Subcontractor Certified Cost or Pricing Data (JUN 2020) 52.215-14 Integrity of Unit Prices (JUN 2020) Alt 1 (OCT 1997) 52.215-15 Pension Adjustments and Asset Reversions (OCT 2010) 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions (JUL 2005) 52.215-19 Notification of Ownership Changes (OCT 1997) 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data

(OCT 2010)

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data –

Modifications (JUN 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-14 Limitations on Subcontracting (SEP 2021)

[Contracting Officer check as appropriate.] ☒ By the end of the base term of the contract and then by the end of each subsequent option period; or ☐ By the end of the performance period for each order issued under the contract.

52.219-28 Post Award Small Business Program Rerepresentation (SEP 2021) 52.219-29 Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women-Owned Small

Business Concerns (SEP 2021) 52.219-30 Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible

Under the Women-Owned Small Business Program (SEP 2021) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (MAY 2018) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified Pricing Method)

(AUG 2018)

52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (OCT 2020) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages under Executive Order 13658 (NOV 2020) 52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2017) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts (SEP 2013) 52.223-3 Hazardous Material Identification and Material Safety Data Alt 1 (FEB 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (Jun 2016) 52.223-15 Energy Efficiency in Energy Consuming Products (MAY 2020) 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (AUG 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) 52.223-20 Aerosols (JUN 2016)

52.223-21 Foams. (JUN 2016) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises (JUN 2000) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.229-4 Federal, State, and Local Taxes (State and Local Adjustments) (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984)

Alternate 1 (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

Alternate I (APR 1984) Alternate II (APR 1984)

52.242-5 Payments to Small Business Subcontractors (JAN 2017) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-2 Subcontracts (JUN 2020) 52.244-6 Subcontracts for Commercial Items (JUL 2021) (DEVIATION APR 2020) 52.245-1 Government Property (SEP 2021) - Alt 1 (APR 2012) 52.245-9 Use and Charges (APR 2012) 52.246-21 Warranty of Construction (MAR 1994)

Alternate I (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012) Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984)

Alternate I (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-71 Prohibition against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (May 2008)

(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”

“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(b) The Contractor, on completion of this contract, shall—

(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and

(2) Submit this estimate to information to be provided after contract award.

52.223-99 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (OCT 2021) (DEVIATION)

(a) Definition. As used in this clause - United States or its outlying areas means—

(1) The fifty States;

(2) The District of Columbia;

(3) The commonwealths of Puerto Rico and the Northern Mariana Islands;

(4) The territories of American Samoa, Guam, and the United States Virgin Islands; and

(5) The minor outlying islands of Baker Island, Howland Island, Jarvis Island, Johnston Atoll, Kingman Reef, Midway Islands, Navassa Island, Palmyra Atoll, and Wake Atoll.

(b) Authority. This clause implements Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021 (published in the Federal Register on September 14, 2021, 86 FR 50985).

(c) Compliance. The Contractor shall comply with all guidance, including guidance conveyed through Frequently Asked Questions, as amended during the performance of this contract, for contractor or subcontractor workplace locations published by the Safer Federal Workforce Task Force (Task Force Guidance) at https:/www.saferfederalworkforce.gov/contractors/.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts at any tier that exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation 2.101 on the date of subcontract award, and are for services, including construction, performed in whole or in part within the United States or its outlying areas.

52.225-9 Buy American Act-Construction Materials (FEB 2021)

(a) Definitions. As used in this clause-

Commercially available off-the-shelf (COTS) item-

(1) Means any item of supply (including construction material) that is-

(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means-

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if-

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

_____________ NONE___________________________________

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description Unit of Measure Quantity Price (dollars)* Item1:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

Item2:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

52.228-1 Bid Guarantee (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION APR 2020)

(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond

(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].

(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained— https://www.acquisition.gov/far/part-28#FAR_28_203_1

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.

(c)A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C. 3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For 90 days following final payment.

(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph (a) of this clause within the timeframe established by the Contracting Officer.

52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION APR 2020)

(a)Definitions. As used in this clause -- “Original contract price” means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity.

Original contract price does not include the price of any options, except those options exercised at the time of contract award.

(b) Amount of required bonds. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

(1) Performance Bonds (Standard Form 25, EXCEPT THAT A SEAL IS NOT REQUIRED). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bonds (Standard Form 25-A, EXCEPT THAT A SEAL IS NOT REQUIRED). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(3) Additional bond protection.

(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.

(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.

https://www.acquisition.gov/far/part-28#FAR_28_102_1

(c) Furnishing executed bonds. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.

(d) Surety or other security for bonds. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier’s check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the Federal Register or may be obtained from the:

U.S. Department of Treasury Financial Management Service Surety Bond Branch 3700 East West Highway, Room 6F01 Hyattsville, MD 20782 Or via the internet at http://www.fms.treas.gov/c570/.

(e) Notice of subcontractor waiver of protection (40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.

52.228-17 Individual Surety – Pledge of Assets (Bid Guarantee) (FEB 2021)

(a)Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b)The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228-1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c)The Contracting Officer may release the security interest on the individual surety's assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) (DEVIATION APR 2020)

(a)[(1) In accordance with 31 U.S.C. 3903 and 10 U.S.C. 2307, upon receipt of accelerated payments from the Government, the Contractor shall make accelerated payments to its small business subcontractors under this contract [in accordance with the accelerated payment date established], to the maximum extent practicable and prior to when such payment is otherwise required under the applicable contract or subcontract, [with a goal of 15 days] after receipt of a proper invoice and all other required documentation from the small business subcontractor [if a specific payment date is not established by contract.

(2) The Contractor agrees to make such payments to its small business subcontractors without any further consideration from or fees charged to the subcontractor].

(b) The acceleration of payments under this clause does not provide any new rights under the Prompt Payment Act.

(c) Include the substance of this clause, including this paragraph (c), in all subcontracts with small business concerns, including subcontracts with small business concerns for the acquisition of commercial items.

452.228-71 Insurance Coverage (NOV 1996) Alt 1 (NOV 1996) http://www.fms.treas.gov/c570/ https://www.acquisition.gov/far/part-28#FAR_28_203_1 https://www.acquisition.gov/far/part-52#FAR_52_228_1

Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract.