This is a Request for Quotation (RFQ) issued by the United States Department of Agriculture (USDA) Forest Service for a furnace replacement project located at 421 Black Avenue in Big Piney, Wyoming. The solicitation is a total small business set-aside for decommissioning, removal, and replacement of a non-functional natural gas furnace at a Forest Service residential facility. The government seeks a Coleman 79ES100C20SMPS1 furnace or equivalent, with specific requirements including 100,000 BTU minimum input, 96% Annual Fuel Utilization Efficiency, an ECM motor, and single-stage operation. Quotes are due by 10:00 AM Mountain Time on January 20, 2026, with questions accepted until January 14, 2026. The contract will be a firm-fixed price award, with evaluation based on lowest price technically acceptable criteria, considering technical capability, past performance, and price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Black Avenue Furnace Replacement

1240LS26Q0003

This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in FAR Part 12. This announcement constitutes the only solicitation; offers are being requested, and a separate written solicitation will not be issued.

Solicitation number 1240LS26Q0003 is issued as a Request for Quotation (RFQ) for decommissioning, removal, and replacement of non-functional natural gas furnace.

This acquisition is set-aside for small business concerns. This solicitation incorporates provisions and clauses by reference. The full text of provisions and clauses may be accessed electronically at www.acquisition.gov.

The applicable North American Industry Classification Standard Code is 811310. The small business size standard is $12.5 Million This acquisition is a Total Small Business Set-Aside. All responsible sources may submit a quotation which will be considered by the agency.

Statement of Requirement

Decommissioning, removal and replacement of a non-functional natural gas furnace at a Forest

Service owned residential facility. Project location is at 421 Black Avenue, Big Piney, WY, 83113.

See Attachment 2 – Statement of Work.

Concerns having the expertise and required capabilities to provide these items are invited to submit offers in accordance with the requirements stipulated in this solicitation. Alternate Parts will be authorized if they are an approved alternate part that satisfies all form, fit, and function requirements of the original parts and conform to the approved configuration. All parts shall be NEW approved parts.

Technical Data -

Technical data and supporting documentation associated with this solicitation are available through the following sources:

1. Solicitation Attachments

The following documents are included as attachments to this solicitation and can be accessed via the “Attachments/Links” section of the posting.

• Attachment 1 – Solicitation Terms and Conditions.

• Attachment 2 – Statement of Work.

• Attachment 3 – Schedule of Items.

• Attachment 4 – Wage Determination.

• Exhibit #1 – Past Performance and Equipment Questionnaire.

• Exhibit #2 – SF-1413 Subcontractor Form (If Applicable).

Delivery Information

F.o.b. destination, is requested as the F.O.B. point for all deliverables.

All offers will be considered F.O.B. Destination unless F.O.B. origin is specified AND estimated shipping costs are included.

http://www.acquisition.gov/

The USDA requires completion of all items by 04/15/2026. Early completion will be accepted.

Shipping Instructions:

Items shall be shipped to the following address:

421 Black Avenue, Big Piney, 83113

Award Type

It is anticipated that a firm-fixed price contract will be awarded as a result of this synopsis/solicitation. The Government intends to make one award from this solicitation. Therefore, to be considered responsive, contractors must submit pricing for all items.

Evaluation and Basis for Award

The provision at FAR 52.212-2, Evaluation—Commercial Products and Commercial Services is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR 12.203 based on the criteria listed below. Award will be made to the offeror representing the best value to the Government.

Evaluation Criteria

The provision at FAR 52.212-2, Evaluation—Commercial Products and Commercial Services is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR 12.203 based on the criteria listed below. Award will be made to the offeror representing the best value to the Government.

Price: Any quantity price discounts and discounts for prompt payment should be included in this section. The offeror shall provide pricing as requested in the attached table titled “Attachment 3 -

Schedule of Items”. Any quantity price discounts and discounts for prompt payment should be included in this section. The offeror’s quotation will be evaluated in accordance with FAR 12.204, to determine if it is fair and reasonable.

Technical Acceptability: The United States Department of Agriculture (USDA), Forest Service

(FS) has a requirement for the following items on a brand name or equal basis.

Item Part Number Nomenclature Manufacturer

1 79ES100C20SMPS1

Coleman 79ES100C20SMPS1

Furnace 96% Efficient ECM Drive

Motor Coleman

➢ The salient characteristics of the Coleman 79ES100C20SMPS1 Furnace are as follows:

• Input BTUs: 100,000 BTU minimum

• Annual Fuel Utilization Efficiency (AFUE): 96% minimum

• Motor: ECM (Electronically Commutated Motor)

• Stage: Single Stage.

Other important considerations are that the furnace be rated to heat the area (square footage) of the house listed in the statement of work, and that the unit is able to fit in the crawl space.

Offeror’s providing “or equal” items shall include in their quotation descriptive literature such as illustrations, drawings, or a clear reference, such as a web site to information readily available to the

Contracting Officer showing that the items being quoted meets all salient characteristics. Merely stating that the items meet is not acceptable. The Contracting Officer is not responsible for locating or obtaining any information not identified in the offer.

The Technical capability will be evaluated to determine an overall rating of “acceptable” or

“unacceptable”. To be considered technically acceptable, the quoted product must:

1. Meet or exceed all salient characteristics of the brand name product as specified in the solicitation.

2. Be clearly identified by brand name, make, and model number, or identified as an “equal” product.

3. Include sufficient descriptive literature or documentation (e.g., product specifications, datasheets, or brochures) to demonstrate how the proposed product meets or exceeds the required salient characteristics.

4. Be available for delivery within the timeframe specified in the solicitation.

Failure to provide adequate documentation or to meet the required salient characteristics will result in a determination of technical unacceptability, and the quotation will not be considered for award.

Past Performance:

The Government may utilize any references provided by the Contractor, along with information available from past contracts/orders with the USDA and any information found using sources such as Federal Government sources or the Contractor Performance Assessment Reporting System

(CPARS) to determine if the Contractor has acceptable or neutral Past Performance. Past

Performance will be evaluated using the following rating system:

• Acceptable: The contractor shows a demonstrated ability to meet contract requirements in prior or current contracts, including quality of work, timeliness, cost control, business relations, and adherence to contract terms.

• Neutral: Offeror does not have a past performance record.

• Unacceptable: The contractor has a documented history of failing to meet contract requirements, including poor quality, missed deadlines, cost overruns, lack of responsiveness, or unethical behavior.

Evaluation Method:

The Government will evaluate quotations based on the lowest price technically acceptable criteria.

Only the lowest priced offer will be evaluated for Technical Acceptability. Should the lowest priced offer not receive an acceptable technical or past performance rating, the process will continue in order of lowest priced offer until the lowest price, technically acceptable offer with acceptable or neutral past performance is identified.

Federal Acquisition Regulation (FAR) and United States Department of Aquiculture

Acquisition Regulation (AGAR) Clauses and Provisions

The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.

Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.

As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The

System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

52.252-2 Clauses Incorporated by Reference Feb 1998

This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025)

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(Jan 2017)

52.222-50 Combating Trafficking in Persons (Nov 2025)

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023)

52.233-3 Protest After Award (Sep 2025)

52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025)

52.240-91 Security Prohibitions and Exclusions (Nov 2025)

52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)

The following clauses are applicable if checked:

☒ 52.204-13 System for Award Management—Maintenance (Nov 2025)

☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025)

☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025)

☒ 52.222-3 Convict Labor (June 2003)

☒ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022)

☒ 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air

Conditioners (Nov 2025)

☒ 52.223-23 Sustainable Products and Services

☒ 52.225-1 Buy American-Supplies (Nov 2025)

☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018)

The Contractor shall comply with the following FAR Clauses for Commercial Services.

☒ 52.222-41 Service Contract Labor Standards (Aug 2018)

☒ 52.222-42 Statement of Equivalent Rates for Federal Hires (May 2014)

This Statement is for Information Only:

It is not a Wage Determination

Employee Class Monetary Wage -- Fringe Benefits

GS - 7 Step – 4 $26.33--$5.55

Other Applicable Clauses

52.247-34 F.O.B. Destination (Jan 1991)

AGAR Clauses

452.222-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec

2025)

(a) By entering into this contract, the Contractor certifies that:

(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal

Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.

(2) Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the

U.S. Constitution, and the Contractor and any subcontractor or teaming partner will not do so for the duration of the contract.

(b) If the Contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the Contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from

Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and

Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based

Opportunity.

(c) The Contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the

Contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to Contractor’s compliance with the above requirements and/or eligibility for the contract may subject the Contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18

U.S.C. §§ 287 and 1001.

(f) The Contractor must include the provisions of this clause in all subcontract solicitations.

(g) Failure on the part of the Contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.

(End of Clause)

452.204–70 Modification for Contract Closeout (Nov 2025)

(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the

Contracting Officer (Contracting Officer) shall issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but will not be required to provide a signature. The Contracting Officer shall immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(b) Upon contract closeout for contracts utilizing SAP: if unliquidated funds of more than

$1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and will be required to provide a signature. (The Contracting Officer may also request a “Contractor Release of

Claims” be completed by the contractor, although not required for contracts and orders using

SAP.) If the bilateral modification and Release of Claims are not returned to the Contracting

Officer within 60 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(c) Upon contract closeout for contracts utilizing anything other than cost reimbursement, if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and a ‘‘Contractor Release of Claims’’ and will be required to provide a signature on both forms. If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 120 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(End of Clause)

52.252-1 Solicitation Provisions Incorporated by Reference Feb 1998

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-1 Instructions to Offerors - Commercial Products and Commercial Services (Nov

2025)

FAR 52.212-1 is amended as follows:

AT A MINIMUM, QUOTERS SHALL SUBMIT THE FOLLOWING DOCUMENTS BACK

WITH THEIR RESPONSE TO THIS SOLICITATION:

1. Schedule of Items (including Quoter’s Company Information)

2. Certification that repairs can be completed by the date listed in the SOW, and in the

Delivery Information Section. See Exhibit #1.

3. Any Amendment that may be issued.

4. Exhibit #1 Past Performance and Equipment Questionnaire.

5. Exhibit #2 SF-1413 Subcontractor Form (If Applicable).

6. Technical Response as Identified in Evaluation and Basis for Award, Evaluation

Criteria, Price, Technical Acceptability, and Past Performance.

Period for acceptance of offers.

The Offeror agrees to hold the prices in its offer firm for 90 calendar days from the date specified for receipt of offers.

Questions

Questions shall be submitted via email to arlen.fausett@usda.gov and are due no later than January

14, 2026, at 10:00 AM Mountain Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email. Quotes are due at the email address above by 10:00 AM MT on January 20, 2026.

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality

Agreements or Statements-Representation (Jan 2017)

52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Nov 2025)

The following provisions are applicable if checked:

☒ 52.204-7 System for Award Management—Registration (Nov 2025)

☒ 52.222-18 Certification Regarding Knowledge of Child Labor for Listed End Products (Feb

2021)

☒ 52.225-2 Buy American Certificate (Oct 2022)

AGAR Provisions

452.203-70 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Certification

(Dec 2025)

(a) By submission of its offer, the offeror certifies that:

(1) It is compliant with all applicable Federal anti-discrimination laws and the Equal

Protection principles of the U.S. Constitution.

(2) Neither it nor any proposed subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the

U.S. Constitution.

(b) If the offeror participates in, facilitates, or funds programs that implicate Title VI of the

Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, mailto:arlen.fausett@usda.gov non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, by submission of its offer, the offeror certifies that it is compliant with those laws, including the requirements set forth in Executive Order

14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and

Restoring Merit-Based Opportunity.

(c) The offeror affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the offeror will not be eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to offeror’s compliance with the above requirements and/or eligibility for the contract may subject the offeror to liability under the

False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§

287 and 1001.

(f) Failure on the part of the offeror or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate the contract for default.

(End of Provision)

452.211-70 Brand Name or Equal (Sep 2025)

(a) If an item in this solicitation is identified as "brand name or equal," the purchase description reflects the characteristics and level of quality that will satisfy the Government’s needs. The salient physical, functional, or performance characteristics that "equal" products must meet are specified in the solicitation.

(b) To be considered for award, offers of "equal" products, including "equal" products of the brand name manufacturer, must-

(1) Meet the salient physical, functional, or performance characteristics specified in this solicitation;

(2) Clearly identify the item by-

i. Brand name, if any; and ii.Make or model number;

(3) Include descriptive literature such as illustrations, drawings, or a clear reference to previously furnished descriptive data or information available to the

Contracting Officer; and

(4) Clearly describe any modifications the offeror plans to make to a product to make it conform to the solicitation requirements. Mark any descriptive material to clearly show the modifications.

(c) The Contracting Officer will evaluate "equal" products on the basis of information furnished by the offeror or identified in the offer and reasonably available to the Contracting

Officer. The Contracting Officer is not responsible for locating or obtaining any information not identified in the offer.

(d) Unless the offeror clearly indicates in its offer that the product being offered is an "equal" product, the offeror shall provide the brand name product referenced in the solicitation.

(End of provision)

NOTICE FOR FILING AGENCY PROTESTS

United States Department of Agriculture (USDA) Ombudsman Program

The USDA is committed to issuing solicitations and awarding contracts in a fair and prompt manner.

The Ombudsman Program for Agency Protests (OPAP) was established to address protest issues within the agency, providing an alternative to costly and time-consuming litigation. Operating independently, OPAP offers relief comparable to that granted by the Government Accountability

Office (GAO). Interested parties are encouraged to resolve concerns through USDA’s internal

Alternative Dispute Resolution (ADR) process before pursuing external forums such as the GAO.

Concerns may be addressed informally or through a formal agency protest filed with either the

Contracting Officer or the Ombudsman.

Informal Forum with the Ombudsman

1. Initial Point of Contact: Interested parties who believe a specific USDA procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting

Officer.

2. Escalation: If the Contracting Officer is unable to address their concerns, interested parties are encouraged to contact the USDA Ombudsman for Agency Protests. Under this informal process, the agency is not required to suspend contract award performance. Utilization of the informal forum does not suspend any time requirement for filing a formal protest with the agency or other forums.

3. Required Information: To ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).

Formal Agency Protest with the Ombudsman

1. Effort to Resolve: Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions.

2. Independent Review: If the protester’s concerns remain unresolved, an Independent Review is available by the Ombudsman. The protester may file a formal agency protest with either the

Contracting Officer or, alternatively, with the Ombudsman under the OPAP program. Contract awards or performance will be suspended during the protest period unless justified in writing for urgent and compelling reasons or determined in writing to be in the best interest of the

Government.

3. Resolution Timeline: The agency’s goal is to resolve protests within 35 calendar days from the date of filing.

4. Required Information: Protests shall include the information set forth in FAR 33.104(a)(3).

Failure to submit the required information may result in a delay or dismissal of the protest.

5. Timeliness: Protests must be filed within the timeframes specified in FAR 33.104.

6. Submission: Formal protests under the OPAP program should be submitted electronically to SPE.inquiry@usda.gov and the Contracting Officer.

Election of Forum. By initiating a protest with the USDA, the protester agrees not to pursue the same matter with the Government Accountability Office (GAO) or any other external forum while the agency protest is pending. If a protest is filed externally, the agency protest will be dismissed.

mailto:SPE.inquiry@usda.gov