Appendix 4 WORK SCHEDULE TEMPLATE.pdf
PDF 162 KB Posted
- Attached to
- Hazard Tree Removal Rogue Rive Siskiyou, Oregon Federal contract opportunity
- Solicitation number
- 1240BF26Q0035
- Issued by
- Department of Agriculture Forest Service
About this file
This is an example work schedule template for pre-commercial thinning (PCT) services under a federal Indefinite Delivery Indefinite Quantity (IDIQ) contract vehicle.
The document illustrates how contractors should structure and present their project schedules for PCT work. The example details a contract with Rip and Tear Reforestation (Contract Number 0120109C180001) for the Cuttem Down Creek PCT project, specifying a crew composition of 10 personnel plus 1 foreman with an estimated productivity rate of 10 acres per day. The contractor plans to establish camp on May 13, 2018, and commence cutting operations on May 15, 2018. The work schedule itemizes four thinning tasks with sequential start and completion dates spanning May 15 through July 20, 2018, with a planned site departure date of July 25, 2018. Item 0002(b) includes a notation indicating additional time requirements due to lack of driving access to that thinning area. This template serves as guidance for contractors responding to PCT IDIQ solicitations to demonstrate their capability to plan, schedule, and execute forest management work within realistic timeframes.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C05 1240BF26Q0035 Slater Fire Haz Tree Removal PWS v3.pdf | ||
| Sol_1240BF26Q0035_Amd_0003.pdf | ||
| C05 1240BF26Q0035 Questions and Response to solicitation.pdf | ||
| Sol_1240BF26Q0035_Amd_0002.pdf | ||
| Sol_1240BF26Q0035_Amd_0001.pdf | ||
| Sol_1240BF26Q0035 RRS Haz Tree Removal.pdf | ||
| Attachment 2 Slater Roadside Danger Tree Removal Contracts 1 and 2 Contract Map.pdf | ||
| Attachment 5 WD 1977-0079 Rev 82 20260513.pdf | ||
| Appendix 3 REQUEST FOR INSPECTION.docx | DOCX document | |
| Attachment 1 Slater Fire Haz Tree Removal PWS.pdf | ||
| Attachment 4 Slater Fire Option Items Maps.pdf | ||
| Attachment 6 Schedule of Items Price Sheet.xlsx | XLSX spreadsheet | |
| Appendix 1 Fire Supression.pdf | ||
| Attachment 3 Slater Roadside Danger Tree Removal Contracts 1 and 2 Roads Vicinity Map.pdf | ||
| Appendix 2 CAMPSITES CAMPGROUND.docx | DOCX document | |
| Appendix 5 Hazard-tree-field-guide.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit 5: Work Schedule “Example”
Pre-commercial Thinning Work Schedule
Date Prepared: _May 1, 2018
Contract Number:_0120109C180001 Contract Name: Cuttem Down Creek PCT
Contractor: _Rip and Tear Reforestation
Crew Size: _10 Ten Crew & 1 One Forman
Estimated number acres crew can thin per day: _10 acres per day
Date contractor plans to set-up camp: _May 13, 2018
Date contractor plans to start cutting: _May 15, 2018
Thinning items in order of anticipated completion:
Item Number
Estimated Start Date
Estimated Completion Date
Notes
0001(a) May 15, 2018 June 3, 2018 0002(b) June 3, 2018 June 17, 2018 Additional time is required do to no driving access to thinning item 0001(c) June 17, 2018 July 2, 2018 0001(d) July 2, 2018 July 20, 2018
Estimated date work will be completed and contractor will leave job site: _July 25, 2018
APPENDIX 6 - WORK SCHEDULE TEMPLATE
PCT IDIQ PWS
| C.01 PROJECT LOCATION AND DESCRIPTION |
| C.01.1 GENERAL ACCESSABILITY |
| C.01.2 OVERALL PHYSICAL DESCRIPTION OF GROUND CONDITIONS |
| C.01.3 ITEM(S) SITE ACCESSABILITY |
| C.01.4 LOCAL SERVICES |
| C.01.5 CUT AND LEAVE TREE LIMITS |
| C.01.6 SPACING OF LEAVE TREES |
| C.01.7 TREES TO FAVOR FOR LEAVE TREES |
| Exhibit 1: DETAILED ITEM INFORMATION |
| Exhibit 5: Work Schedule “Example” |
| Exhibit 6: Diagram of 12 x 12 Spacing Per Tree Method. |
| Exhibit 7: Diagram of 14 x 14 Spacing Per Tree Method |
| Exhibit 8: Diagram of 16 x 16 Spacing Per Tree Method |