Appendix 4 WORK SCHEDULE TEMPLATE.pdf

PDF 162 KB Posted

Attached to
Hazard Tree Removal Rogue Rive Siskiyou, Oregon Federal contract opportunity
Solicitation number
1240BF26Q0035
Issued by
Department of Agriculture Forest Service

About this file

This is an example work schedule template for pre-commercial thinning (PCT) services under a federal Indefinite Delivery Indefinite Quantity (IDIQ) contract vehicle.

The document illustrates how contractors should structure and present their project schedules for PCT work. The example details a contract with Rip and Tear Reforestation (Contract Number 0120109C180001) for the Cuttem Down Creek PCT project, specifying a crew composition of 10 personnel plus 1 foreman with an estimated productivity rate of 10 acres per day. The contractor plans to establish camp on May 13, 2018, and commence cutting operations on May 15, 2018. The work schedule itemizes four thinning tasks with sequential start and completion dates spanning May 15 through July 20, 2018, with a planned site departure date of July 25, 2018. Item 0002(b) includes a notation indicating additional time requirements due to lack of driving access to that thinning area. This template serves as guidance for contractors responding to PCT IDIQ solicitations to demonstrate their capability to plan, schedule, and execute forest management work within realistic timeframes.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit 5: Work Schedule “Example”

Pre-commercial Thinning Work Schedule

Date Prepared: _May 1, 2018

Contract Number:_0120109C180001 Contract Name: Cuttem Down Creek PCT

Contractor: _Rip and Tear Reforestation

Crew Size: _10 Ten Crew & 1 One Forman

Estimated number acres crew can thin per day: _10 acres per day

Date contractor plans to set-up camp: _May 13, 2018

Date contractor plans to start cutting: _May 15, 2018

Thinning items in order of anticipated completion:

Item Number

Estimated Start Date

Estimated Completion Date

Notes

0001(a) May 15, 2018 June 3, 2018 0002(b) June 3, 2018 June 17, 2018 Additional time is required do to no driving access to thinning item 0001(c) June 17, 2018 July 2, 2018 0001(d) July 2, 2018 July 20, 2018

Estimated date work will be completed and contractor will leave job site: _July 25, 2018

APPENDIX 6 - WORK SCHEDULE TEMPLATE

PCT IDIQ PWS

C.01 PROJECT LOCATION AND DESCRIPTION
C.01.1 GENERAL ACCESSABILITY
C.01.2 OVERALL PHYSICAL DESCRIPTION OF GROUND CONDITIONS
C.01.3 ITEM(S) SITE ACCESSABILITY
C.01.4 LOCAL SERVICES
C.01.5 CUT AND LEAVE TREE LIMITS
C.01.6 SPACING OF LEAVE TREES
C.01.7 TREES TO FAVOR FOR LEAVE TREES
Exhibit 1: DETAILED ITEM INFORMATION
Exhibit 5: Work Schedule “Example”
Exhibit 6: Diagram of 12 x 12 Spacing Per Tree Method.
Exhibit 7: Diagram of 14 x 14 Spacing Per Tree Method
Exhibit 8: Diagram of 16 x 16 Spacing Per Tree Method
Exhibit 9: Diagram of 18 x 18 Spacing Per Tree Method
Exhibit 10: Mechanical Girdling Diagra

File details come from the government source that posted it. Updated .