About this file

This is an appendix containing a contractor inspection request and certification form for a Indefinite Delivery Indefinite Quantity (IDIQ) Performance Work Statement (PWS) contract related to hazard tree removal and fuels management services on the Rogue River Siskiyou National Forest in Oregon and California.

The form serves as a template for contractors to formally request inspection of completed work for payment purposes. Contractors must certify that specified acreage has been thinned and is ready for inspection, that inspection plots are physically marked on the ground with colored flagging, that inspection results have been recorded using the required Thinning Inspection Report, and that all work meets the Prosecution of Work clause requirements. The request requires contractors to submit the contract number, identify the specific item/sub-item/block number being inspected, provide estimated acres completed, include a map showing the location of the area ready for inspection, and provide remarks as needed. This inspection request and certification process appears to be a critical quality assurance mechanism within the contract to ensure hazardous tree removal and fuels reduction work meets specified standards before payment authorization.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX 5 – REQUEST FOR INSPECTION

PCT IDIQ PWS

CONTRACTOR INSPECTION/ REQUEST/CERTIFICATION

Contractor Contract Number

I hereby request inspection for payment purposes on the following:

Item / Sub-item / Block #:Estimated Acres Completed:
_

I certify that:

1) acres indicated above have been inspected for compliance with the specifications indicated in Section E Inspection

2) acres are thinned and ready for inspection and meet the completed inspection block requirement

3) a map of the item/sub-item showing the location of the area ready to be inspected is included with this request

4) inspection plots are identified on the ground with colored flagging in plot center

5) inspection results have been recorded and provided with this request utilizing the Thinning Inspection Report provided in Exhibit 1.

6) all work to be inspected meets the requirements of the Prosecution of Work clause in Section G. Remarks:

Contractor or Contractor’s Rep