1240BE26Q0033 Attachment 2 Schedule of Items.pdf
PDF 687 KB Posted
- Solicitation number
- 1240BE26Q0033
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a pricing schedule and quotation form for tree planting and seedling protection services at Ochoco National Forest in Oregon. The solicitation number is 1240BE26Q0033, issued February 26, 2026, with quotes due March 17, 2026 at 2 p.m. PST. The contract covers work at the Paulina Ranger District and Lookout Mountain Ranger District, with a period of performance from date of award through December 31, 2026.
The base items (Items 0001–0005) total 2,722 acres of spring 2026 conifer hand planting across four fire recovery areas: Crazy Creek (725 acres), Rail Ridge (897 acres), Wiley Flat (1,028 acres), and Lake Post-Harvest (36 acres), all using 17' x 17' spacing with 18" x 18" scalp specifications. Item 0005 includes flex netting installation for Lake Post-Harvest seedlings (36 acres). Optional items (Items 1001–1011) may be awarded based on funding availability and include up to 250 acres of fall 2026 planting, additional spring planting up to 518 acres, flex netting installation up to 3,168 acres, rigid mesh tube installation up to 3,168 acres, tree shade installation up to 1,925 acres, and riparian planting restoration up to 5,500 plants across seven creeks. All pricing must be submitted in exact dollars and cents with no rounding. Quoters must submit copies of MSPA licensing, Oregon BOLI license, and H2B Temp Employment certificates if applicable, with the same documentation required for all subcontractors. The estimated contract time is 53 calendar days total (24 days for spring planting, 2 days for riparian grubbing, and 27 days for seedling protection installation). Offerors must hold their quotes firm through September 30, 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 2
Ochoco NF 2026 Spring and Fall Tree Planting and Seedling Protection
Business Name: ____________________________
Address: __________________________________
Phone/Email: ____________________________ Solicitation #: 1240BE26Q0033 Date: February 26, 2026
UEI: ______________________ Quote Due: March 17, 2026, 2 p.m. PST UEI # from www.sam.gov (required)
FOR: Ochoco National Forest, Paulina Ranger District and Lookout Mountain Ranger District
SCHEDULE OF ITEMS
ITEM
NO. SCHEDULE OF SUPPLIES/SERVICES
ESTIMATED
QUANTITY
UNIT
UNIT PRICE
TOTAL
AMOUNT
BASE ITEMS
0001 Spring 2026 Conifer Planting – Crazy
Creek Fire: Paulina RD. Hand planting by the acre. 17’ x 17’ spacing, 18” x 18” scalp.
Units: C64, C65, C66, C68, C70, C71, C74, C75, C76, and C79.
725 Acre $ $
0002 Spring 2026 Conifer Planting – Rail Ridge Fire: Paulina RD. Hand planting by the acre.
17’x 17’ spacing, 18” x 18” scalp. Units:
R11, R15, R18, R19, R20, R21, R22, R23, R25, R26, R28, R30, R31, R37, R42, R44, R45, R49, and R50.
897 Acre $ $
0003 Spring 2026 Conifer Planting – Wiley Flat Fire: Lookout Mountain RD. Hand planting by the acre. 17’ x 17’ spacing, 18” x 18” scalp. Units: W11, W45, W48, W49, W50, W52, W58, W59, W60, W64, W65, W67, W68, W69, W71, W73, W123, W130, and W155.
1028 Acre
0004 Spring 2026 Conifer Planting – Lake Post- Harvest: Lookout Mountain RD. Hand planting by the acre: Variable spacing, 18” x 18” Scalp. Units: 2A, 2B, and 2C.
36 Acre $ $
0005 Spring 2026 Flex Netting Installation for Planted Seedlings – Lake Post-Harvest:
Lookout Mountain RD. Units: 2A, 2B, and 2C.
36 Acre $ $
Total Base Items $
1240BE26Q0033
ITEM
NO. SCHEDULE OF SUPPLIES/SERVICES
ESTIMATED
QUANTITY UNIT UNIT PRICE
TOTAL
AMOUNT
OPTIONAL ITEMS
OPTIONAL ITEMS MAY BE AWARDED IN
EXISTING GROUPING(S) OR AS A STAND-
ALONE UNIT, BASED ON FUNDING
AVAILABILITY.
Quote maximum quantity shown.
1001 Fall 2026 Conifer Planting – Crazy Creek, Paulina RD. Hand planting by the acre: 17’ x 17’ spacing, 18“ x 18” scalp. Units: C41, C42, C43, C44, C45, C47, C59, C62, C144, and C744.
Up to 250 Acre $ $
1002 Spring 2026 Conifer Planting – Crazy Creek Fire: Paulina RD. Hand planting by the acre: 17’ x 17’ spacing, 18“ x 18” scalp.
Units: C1, C4, C82, C83, C84, C85, C86, C88, C89, and C90.
Up to 518 Acre $ $
1003 Spring 2026 Flex Netting Installation for Planted Seedlings – Crazy Creek Fire:
Paulina RD. Units:C1, C4, C64, C65, C66, C68, C70, C71, C74, C75, C76, C79, C82, C83, C84, C85, C86, C88, C89, and C90.
Up to 1,243
Acre $ $
1004 Spring 2026 Flex Netting Installation for Planted Seedlings – Rail Ridge Fire:
Paulina RD. Units: R11, R15, R18, R19, R20, R21, R22, R23, R25, R26, R28, R30, R31, R37, R42, R44, R45, R49, and R50.
Up to 897 Acre $ $
1005 Spring 2026 Flex Netting Installation for Planted Seedlings – Wiley Flat Fire:
Lookout Mountain RD. Units: W11, W45, W48, W49, W50, W52, W58, W59, W60, W64, W65, W67, W68, W69, W71, W73, W123, W130, and W155.
Up to 1,028
Acre $ $
1006 Spring 2026 Rigid Mesh Tube Installation for Planted Seedlings – Crazy Creek Fire:
Paulina RD. Units:C1, C4, C64, C65, C66, C68, C70, C71, C74, C75, C76, C79, C82, C83, C84, C85, C86, C88, C89, and C90.
Up to 1,243
Acre $ $
1007 Spring 2026 Rigid Mesh Tube Installation for Planted Seedlings– Rail Ridge Fire:
Paulina RD. Units: R11, R15, R18, R19, R20, R21, R22, R23, R25, R26, R28, R30, R31, R37, R42, R44, R45, R49, and R50.
Up to 897 Acre $ $
1008 Spring 2026 Rigid Mesh Tube Installation for Planted Seedlings – Wiley Flat Fire:
Lookout Mountain RD. Units: W11, W45, W48, W49, W50, W52, W58, W59, W60, W64, W65, W67, W68, W69, W71, W73, W123, W130, and W155.
Up to 1,028
Acre $ $
1240BE26Q0033
ITEM
NO. SCHEDULE OF SUPPLIES/SERVICES
ESTIMATED
QUANTITY UNIT UNIT PRICE
TOTAL AMOUNT
1009 Spring 2026 Tree Shade Installation for Planted Seedlings – Rail Ridge Fire:
Paulina RD. Units: R11, R15, R18, R19, R20, R21, R22, R23, R25, R26, R28, R30, R31, R37, R42, R44, R45, R49, and R50.
Up to 897 Acre $ $
1010 Spring 2026 tree shade installation for planted seedlings – Wiley Flat Fire:
Lookout Mountain RD. Units: W11, W45, W48, W49, W50, W52, W58, W59, W60, W64, W65, W67, W68, W69, W71, W73, W123, W130, and W155.
Up to 1028 Acre $ $
1011 Spring 2026 Riparian Planting – post-fire riparian restoration – Wiley Flat Fire:
Lookout Mountain RD. Planting in the following drainages: Drake Creek, Florida Creek, Maury Creek, Pine Creek, Sherwood Creek, Shotgun Creek and Wildcat Creeks.
Hand planting of hardwood trees and riparian plants, by the plant (Each), typically within 50 feet from stream/riparian edge.
Up to 5,500
Each $ $
Total Optional Items $
Grand Total $
CO Enter Award Below:
Base Items: $
Option Items Awarded: $
Total Award: $
No rounding off unit pricing or totals. Unit price and totals shall be in exact dollars and cents (two decimals).
To be considered for award, Quoter shall submit copies of licensing with quote: MSPA licensing, Oregon BOLI license, and H2B Temp Employment certificate, if applicable. The same documents shall be included for all Subcontractors.
Quoter Signature: ________________________________ Date:__________________ Any combination of Optional Items may be awarded based on funding availability in single or multiple unit configurations. If funds are available, some Option Item(s) will be ordered at time of award such as shade and seedling protection and riparian restoration. Fall planting is expected to be awarded in a separate modification following successful spring operations. Offeror agrees to hold its offer firm through September 30, 2026.
Period of Performance: Date of Award - December 31, 2026 Work Item: Contract Time(Estimated Calendar Days):
2026 Spring Conifer Planting 24 days Riparian Planting Grubbing 2 days Seedling protection installation 27 days
1240BE26Q0033
File details come from the government source that posted it. Updated .