This document is a federal specification section (Section 156) detailing requirements for Public Traffic management during construction projects. The specification provides comprehensive guidelines for controlling and protecting public traffic adjacent to and within a project site, requiring contractors to accommodate traffic safely according to the Manual on Uniform Traffic Control Devices (MUTCD) and an approved traffic control plan. Key requirements include submitting a traffic control plan 30 days prior to project start, maintaining existing roads for traffic, limiting traffic delays to no more than 30 minutes at a time, and ensuring all traffic control devices are installed, maintained, and removed appropriately.

The specification outlines detailed provisions for temporary traffic control, including requirements for installing and maintaining traffic control devices, using certified flaggers, handling temporary road closures, and ensuring public safety throughout the construction process. While the document includes a table for potential road closures, in this instance the table is blank (marked with "NA"), suggesting the specific road closure details will be determined during the project planning phase. The section also specifies that public traffic work will be evaluated under a specific subsection and that payment for these services is provided indirectly within the overall contract.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

156 - Public Traffic 156.00_National_2_5_2019

Delete Section 156 in its entirety and replace with the following:

Section 156. – PUBLIC TRAFFIC Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Permanent Traffic Control 633

Traffic Signing and Marking Material 718

Concrete Barriers and Precast Guardwalls 618

Temporary plastic fence 710.11

Construction Requirements

156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section.

Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 30 minutes at any one time followed by an open period of no less than 5 minutes. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection 106.07(b).

Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.

Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM 7100-15.

All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 14 days in advance.

Table 156-1 Temporary Road Closures

Road Number From Terminus To Terminus

Maximum Consecutive Days of Closure

Minimum Consecutive Days Open

NA NA NA NA NA

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly. See Subsection 109.05.

All_National_FSSS_12-11-19.pdf
Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms.
101.01 Meaning of Terms.
101.03 Abbreviations.
101.04 Definitions.
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102.
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04.
104.03 Specifications and Drawings.
104.06 Use of Roads by Contractor.
105 - Control of Material
105.02(a) Government-provided sources.
105.02(c) Contractor-located sources.
105.02 (a) Government-provided sources.
106 - Acceptance of Work
106.01 Conformity with Contract Requirements.
106.02 Visual Inspection.
106.07 Partial and Final Acceptance.
107 - Legal Relations and Responsibility to the Public
107.02 Protection and Restoration of Property and Landscape.
Delete Subsection 107.05.
107.08 Sanitation, Health, and Safety.
108 - Prosecution and Progress
Delete Section 108.
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.01 Measurement of Work.
109.02 Measurement Terms and Definitions.
109.03 Weighing Procedures and Devices.
152 - Construction Survey and Staking
152.04 General.
152.05 Survey and Staking Requirements.
Table 152-1 Construction Survey and Staking Tolerances
153 - Contractor Quality Control
153.02 Qualifications.
153.03 Quality Control Plan.
153.07 Records and control charts.
155 - Schedules for Construction Contracts
Delete Section 155.
156 - Public Traffic
Section 156. – PUBLIC TRAFFIC
157 - Soil Erosion and Sediment Control
157.04 General.
201 - Clearing and Grubbing
201.04 Clearing.
201.04 Clearing
201.06 Disposal.
201.06 Disposal.
203 - Removal of Structures and Obstructions
203.04 (b) General.
203.05 Disposing of Material.
204 - Excavation and Embankment
Section 204. — EXCAVATION AND EMBANKMENT
205 - Rock Blasting
205.03 Regulations
205.06 Preblast condition survey and vibration monitoring and control.
205.07 Test Blasting.
205.08 Blasting.
207 - Earthwork Geotextiles
207.04(c)(1) First layer placement and compaction.
208 - Structure Excavation and Backfill for Selected Major Structures
208.07 Dewatering.
209 - Structure Excavation and Backfill
209.09 Backfill.
209.10 Compacting.
213 - Subgrade Stabilization
213.05 General.
301 - Untreated Aggregate Courses
301.03 General.
301.05 Compacting.
302 - Minor Crushed Aggregate
302.04 Placing Crushed Aggregate.
303 - Road Reconditioning
303.07 Roadway Reconditioning.
314 - Stockpiled Aggregates
314.01 Description.
314.04 Stockpile Site.
407 - Chip Seal
407.01 Description.
407.07 Weather Limitations.
407.08 Production Start-Up Procedures.
407.09 Asphalt Application.
407.11 Placing and Finishing. Table 407-1.
407.12 Double and Triple Course Chip Seal.
407.12 Double and Triple Course Chip Seal. Table 407-2.
407.12 Double and Triple Course Chip Seal. Table 407-2a.
407.15 Payment.
409 - Micro Surfacing
409.07 Weather Limitations.
411 - Asphalt Prime Coat
411.05 Weather Limitations.
411.08 Maintenance.
Delete the second sentence of Subsection 411.09 and replace with the following:
411.09 Acceptance.
412 - Asphalt Tack Coat
412.05 Weather Limitations.
413 - Asphalt Pavement Milling
413.01 Description.
413.03 Milling.
413.05 Measurement.
413.06 Payment.
602 - Culverts and Drains
602.05 Laying Metal Pipe.
603 - Structural Plate Structures
603.03 General.
603.04 Erecting.
625 - Turf Establishment
Section 625. — TURF ESTABLISHMENT
633 - Permanent Traffic Control
633.02 Material.
633.03 General.
633.05 (a) Fabrication.
648 - Stream Simulation
Section 648. — STREAM SIMULATION
701 - Cement
701.02 Masonry and Mortar Cement.
703 - Aggregate
703.05 (c) Surface course aggregate. (3) Plastic Index
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
703.09 Chip Seal Aggregate.
704 - Soil
704.02 Bedding Material.
704.08 Select Granular Backfill.
704.08 Select Granular Backfill. (a) Quality requirements. (2)
704.08 Select Granular Backfill. Table 704-2
705 - Rock
705.02 Riprap. Table 705-1.
705.08 Streambed Simulation Rock.
725 - Miscellaneous Material
725.04 Pozzolans.
725.19 Bentonite.

File details come from the government source that posted it. Updated .