This is a Questions and Answers document for federal contract opportunity 1240BD27Q0001 regarding road grading services in the Bonners Ferry area.
The contract requires grading services on 50.75 guaranteed named-road miles and an estimated 40.6 miscellaneous miles, with work performed twice annually—once in spring (mid-May to July 1st) and once in fall (mid to late October to mid to late November). The pricing unit is "DH" (miles). Contractors must anticipate two separate mobilizations and may have additional roads assigned based on public requests. Road segments will receive two grading treatments during the contract period. Site visits are available to assess existing conditions. Drainage ditch cleaning, culvert cleaning, and debris removal are minimal in most locations, with only occasional cut bank work required. Imported aggregate, material hauling, additional labor, and specialized equipment are not required. The contractor must supply water if needed, though the contract timing typically ensures sufficient moisture. A water truck is not required, but alternative packer/roller configurations may be submitted for government approval. Road compaction is preferred but not mandatory. Flaggers, pilot cars, and temporary road closures are not anticipated; however, signage is required. Daily operating hours are at the contractor's discretion, typically 0600 to 1700 hours. Fire-related restrictions should not be an issue, though operations will cease if fire restrictions are implemented. The Contracting Officer Representative will inspect grading operations and completed road segments at least twice weekly, sometimes daily depending on operator skills, with no minimum segment length for inspection. Progressive invoicing is permitted, preferably once after spring operations and once after fall operations are complete. No work beyond the original scope is permitted during contract performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bonners Ferry Road Grading Q&A
1240BD27Q0001
1) Work Locations and Scheduling
Specific road locations or segments associated with the 40.6 miscellaneous miles will most likely be the same roads completed on the task order. Once in the spring and once in the Fall. Some additional roads may be assigned if public has some requests.
contractors should anticipate two separate mobilizations, one in spring and one in the fall.
Yes road segments will require two grading treatments during the contract period. Once in the spring and once in the fall.
2) Pricing Units and Quantities
“DH” is the unit of issue in the contracting system for Miles.
50.75 named-road miles are guaranteed and 40.6 miscellaneous miles is estimated.
3) Road Conditions and Additional Work
Site visits can be available to help assess existing conditions.
Extent of drainage ditch cleaning, culvert cleaning, and debris removal is minimal in most locations. There may be a few lactations where the cut bank has sluffed from weather conditions and the ditch will need to be pulled.
Imported aggregate, material hauling, additional labor, or specialized equipment will not be required on this contract.
4) Water and Compaction
The contractor supply Water if it is required. This contract will be completed in the spring in fall when there is enough moisture that water will not be required. Typically mid to late October to mid to late November and mid may to July 1st are the grading windows we use for these contracts.
A water truck is not required
Yes alternative packer/roller configurations be submitted for Government approval
It is preferred to have all roads compacted but it is not a requirement.
5) Traffic Control and Fire Prevention
Flaggers, pilot cars, or temporary road closures are not anticipated. However, signage is required.
Bonners Ferry Road Grading Q&A
1240BD27Q0001
Daily operating-hours are up to the contractor most operators work 0600 to 1700, fire-related restrictions should not be an issue.
If there are fire restrictions, we will stop operations.
There will be no work beyond the original scope during the performance of this contract.
6) Inspection, Acceptance, and Payment
Contracting Officer Representative drive and inspect the grading operations and completed road segments at least twice a week sometimes on a daily basis depending on operator skills. There is no minimum segment length eligible for inspection.
Progressive invoicing will be permitted, preferably once in the spring after operations and once in the fall once operations are complete.