A001_CottonwoodFuelsBreak IRSC_SiteVisitQ_A.pdf
PDF 35 KB Posted
- Solicitation number
- 12363N26Q4110
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Questions and Answers document from a site visit conducted on July 22, 2026, for the Cottonwood Fuels Break IRSC contract opportunity. The document addresses six key clarifications regarding project execution and environmental compliance.
The Q&A clarifies operational procedures for the fuels reduction work, including requirements for stream crossings in ephemeral streams at right angles and permission to briefly exit and re-enter the contract boundary (up to a couple hundred feet) when necessary for slope, stream crossing, or accessibility reasons, provided the contractor notifies the agency for specialist review of any potential disturbances. Regarding vegetation removal, contractors may need to employ both mechanical and manual cutting methods to meet specifications for cutting 3-foot tall pine/fir up to specified diameters. For debris management, machine piling specifications require all slash and down woody debris at least 3 inches in diameter and 3 feet in length to be piled at minimum heights of 8 feet and diameters of 12 feet. The document confirms that all Whitebark Pine will be flagged prior to contract start to ensure protection, and clarifies that some level of soil disturbance is acceptable during project execution.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cottonwood Fuels Break IRSC
Site Vits Q&A – 7/22/2026
Q1. Can we cross RHCAs?
A1. In Ephemeral streams, stream crossings will be at right angles.
Q2. To access some areas, can we go outside the boundary a couple hundred feet and come back in? Due to slope/ stream crossings/ accessibility.
A2. Yes, we will allow that. However, letting us know where so we can reach out to specialists for ATPs that may fall outside the boundary to make sure we won’t disturb anything.
Q3. Is it your intention to have mechanical cutting as well as manual cutting, in regard to the stipulation to cut 3 foot tall pine/fir up to 8.9” and 6.9”?
A3. To meet specs you may have to do some manual cutting.
Q4. What are the specs on the grapple piling?
A4. Machine pile all slash and down woody debris at least 3 inches in diameter on the small end and at least 3 feet in length. Piles will be a minimum of 8 feet in height and 12 feet in diameter.
Q5. Will Whitebark Pine be marked?
A5. Yes, all Whitebark Pine will be flagged prior to contract start.
Q6. Is some soil disturbance okay?
A6. Yes some soil disturbance is okay.