Excerpt_DRAFT_RFP_Phase1_102924.pdf

PDF 552 KB Posted

Attached to
BCLH Stewardship IRSC Phase 1 Federal contract opportunity
Solicitation number
12363N25R4001
Issued by
Department of Agriculture Forest Service

About this file

This document is a draft Request for Proposals (RFP) for the BCLH Stewardship IRSC Phase 1 project. The project, located 2-12 miles east of Detroit, OR, aims to reduce the risk of hazardous fuels along important access routes within the 2020 fire-affected road system. Key requirements include:

Cut and remove fire-killed timber within 100 ft of roads (349.2 mandatory acres, 221.7 optional acres), fall and leave non-commercial hazard trees within 100 ft of roads (325.5 mandatory acres, 145.1 optional acres), fall and leave hazard trees that can strike the road outside the 100-ft fuels removal area (41.22 mandatory acres, 12.93 optional acres), perform small fuels treatment within 30 ft of roads (30 mandatory acres, 30 optional acres), and reconstruct roads during the dry season (54 miles mandatory, 27 miles optional). Timber volume estimates are provided.

The RFP will be issued around January 15, 2025 with award planned for March 21, 2025. It will be awarded using a best value source selection method as a firm fixed price contract. Construction bonding is required. A site visit for interested offerors is scheduled for October 4, 2024. The Forest Service is the procuring agency.

View the file

Other files for this federal contract opportunity

Other files attached to BCLH Stewardship IRSC Phase 1, newest first.
File Type Posted
SiteVisitNotes_110424.pdf PDF
DRAFT_Phase1_Appendix B_103024.docx DOCX document
DRAFT_Phase1_Appendix A_103024.docx DOCX document
DRAFT Slope Table_102924.xlsx XLSX spreadsheet
DRAFT_Phase 1_AppendixC_102924.pdf PDF
DRAFT Phase1 Burn Severity Map_102924.pdf PDF
DRAFT_ConstructionTypicals_102924.pdf PDF
DRAFT Burn Severity Table_102924.xlsx XLSX spreadsheet
DRAFT_BCLH_Phase 1 CAM_101924.pdf PDF
DRAFT_Phase1_Construction_FSSS_102924.pdf PDF
Attachment2_ProjectAreaAccessInstructions.docx DOCX document
Attachment1_VICINITY MAPS.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No: 12363N25R4001 DRAFT Project Name: BCLH Stewardship IRSC Phase 1

FAC 2024-05 May 22, 2024

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

BCLH STEWARDSHIP IRSC PHASE 1

DETROIT RANGER DISTRICT

WILLAMETTE NATIONAL FOREST

MARION COUNTY, OREGON

B.1 SCHEDULE OF ITEMS

MANDATORY WORK ACTIVITIES:

ITEM

NO.

DESCRIPTION OF

MANDATORY WORK ACTIVITIES UNIT EST

QTY

UNIT

PRICE TOTAL

Cut and Remove Fire Killed Timber within 100ft of the Road Prism (Units, LH-11, LH-

11A, LH-11B, LH-11BA, LH-56, LH-56A,

LH-57, LH-58, LH-59, LH-60, LH-61, LH-67)

Acre 349.2 $ $

Required Cost Data:

Total Logging Cost of Item 1 (cut, yard, process, haul, profit, etc.) Do not include the Road Maintenance or Road Reconstruction costs priced separately under Item 5 and 6(a-t): $_____________________________ Total Delivered Value of Item 1 (combined value of all products removed): $___________________________ **Item 1 total price shall equal Total Logging Cost minus Total Delivered Value

Non-Commercial Hazard Tree Felling within 100 feet From Road Edge (Units, LH-11, LH-

11A, LH-11B, LH-11BA, LH-56, LH-56A,

LH-57, LH-58, LH-59, LH-60, LH-61, LH-67)

Acre 325.5 $ $

Fall & Leave Hazard Trees >100' from Road (Units, LH-11, LH-11A, LH-11B, LH-11BA, LH-

56A, LH-57, LH-58, LH-59, LH-67)

Acre 41.22 $ $

Small Fuels Treatment <16” DBH 0-30 Feet from Road Edge (Units, LH-11, LH-11A, LH-

11B, LH-11BA, LH-56, LH-56A, LH-57, LH-

58, LH-59, LH-60, LH-61, LH-67)

Acre 314.7 $ $

Road Maintenance – Prehaul, During Haul and Post Haul NFSR: 2231000, 2231701, 2231810, 2231840, 2231850, 2231870, 4685000, 4685310, 4685312, 4685330

Miles 66.18 $ $

Road Reconstruction of Haul Routes NFSR: 2231000, 2231701, 2231810, 2231840, 2231850, 2231870, 4685000, 4685310, 4685312, 4685330

6(a): Mobilization - 15101 Lump Sum 1 XXXX $

FAC 2024-05 May 22, 2024

6(b): Soil Erosion and Pollution Control – 15713

Lump Sum 1 XXXX $

6(c): Removal of Culvert, Disposal Method (a)

– 20302 Each 38 $ $

6(d): Removal of Asphalt, Disposal Method

(a) – 20304 SY* 60 $ $

6(e): Keyed Riprap, Class 4 – 25104 CY* 5 $ $

6(f): Mechanically Stabilized Earth Wall, Type (b) – 25501 SY* 5,140 $ $

6(g): Reinforced Soil Slope, Type IV – 26101 SF* 37,303 $ $

6(h): Wet Weather Operational Rock - Subbase, Grading A, Compaction Method (b), Government-Source – 30109

NFSR: 4685000, 4685310, 4685312, 4685330

CY* 7,000 $ $

6(i): Wet Weather Operational Rock - Aggregate Surface Course, Grading F, Compaction Method (b), Government-Source

– 30115A

NFSR: 4685000, 4685310, 4685312, 4685330

CY* 4,500 $ $

6(j): Aggregate Surface Course, Grading F, Compaction Method (b), Government-Source

– 30115B

CY* 1,570 $ $

6(k): Ditch Reconditioning - 30301 Mile 7.01 $ $

6(l): Roadway Reconditioning – 30315 Mile 46.55 $ $

6(m): Full Depth Reclamation, Compaction Method 2 – 30401 Mile 4.49 $ $

6(n): Asphalt Concrete, Type 1, Grading 1/2”

- 40301 Ton 9,753.05 $ $

6(o): 24-inch Corrugated Aluminized Steel Pipe, 0.064-inch Thickness, Method 2 – 60201A

FT 434 $ $

6(p): 36-inch Corrugated Aluminized Steel Pipe, 0.079-inch Thickness, Method 2 – 60201B

FT 506 $ $

6(q): 48-inch Corrugated Aluminized Steel Pipe, 0.109-inch Thickness, Method 2 – 60202C

FT 308 $ $

6(r): 60-inch Corrugated Aluminized Steel Pipe, 0.138-inch Thickness, Method 2 – 60202D

FT 308 $ $

FAC 2024-05 May 22, 2024

6(s): 24-inch Spillway Pipe, Corrugated Aluminized Steel Pipe, 0.064-inch Thickness, Method 2 – 60605A

FT 20 $ $

6(t): Temporary Traffic Control - 63501 Lump Sum 1 XXXX $

7 Yard and Deliver Noncommercial Fish Logs to Deck Locations

Lump Sum 1 XXXX $

8 Remove Hazardous Fuels (>16” DBH) from 0-100 feet from Road (Unit LH-62) Acres 30 $ $

Total All Mandatory Service Items $

OPTIONAL WORK ACTIVITIES:

ITEM

NO.

DESCRIPTION OF

OPTIONAL WORK ACTIVITIES UNIT

ESTIM

ATED

QUANT

ITY

UNIT

PRICE TOTAL

Cut and Remove Included Fire Killed Timber within 100ft of the Road Prism Units LH-12, LH-12A, LH-12B, LH-56B, LH-56C, LH-56D, LH-56E, LH-57A, LH-58A, LH-58B, LH-58C, LH-59A, LH-60A, LH-65, LH-9, LH-9A)

Acre 221.7 $ $

Required Cost Data:

Total Logging Cost of Item 9 (cut, yard, process, haul, profit, etc.) Do not include the Road Maintenance or Road Reconstruction costs priced separately under Item 13 and 14(a-g), and 15(a-b): $____________________ Total Delivered Value of Item 9 (combined value of all products removed): $___________________________ **Item 9 total price shall equal Total Logging Cost minus Total Delivered Value

Non-Commercial Hazard Tree Felling within 100 feet From Road Edge (Units LH-12, LH-

12A, LH-56B, LH-56C, LH-56D, LH-56E,

LH-57A, LH-58A, LH-58B, LH-60A, LH-65,

LH-9, LH-9A)

Acre 145.1 $ $

Fall & Leave Hazard Trees >100' from Road (Units LH-12, LH-56C, LH-56D, LH-56E, LH-

LH-58B, LH-9, LH-9A)

Acre 12.93 $ $

Small Fuels Treatment <16” DBH 0-30’ from Road Edge (Units LH-12, LH-12A, LH-12B, LH-56B, LH-56C, LH-56D, LH-56E, LH-57A, LH-58A, LH-58B, LH-58C, LH-59A, LH-60A, LH-65, LH-9, LH-9A)

Acre 158.3 $ $

Road Maintenance – Prehaul, During Haul and Post Haul NFSR: 2231518, 2231721, 2231730, 4600030, 4688000, 4688133, 4688240, 4693000, 4693640

Miles 49.88 $ $

FAC 2024-05 May 22, 2024

Road Reconstruction of Haul Routes NFSR: 2231518, 2231721, 2231730, 4600030, 4600033, 4688000, 4688133, 4688240, 4693000, 4693640

14(a): Mobilization - 15101 Lump Sum 1 XXXX $

14(b): Soil Erosion and Pollution Control – 15713

Lump Sum 1 XXXX $

14(c): Removal of Culvert, Disposal Method

(a) – 20302 Each 1 $ $

14(d): Subbase, Grading A, Compaction Method (b), Government-Source – 30109 CY* 15 $ $

14(e): Roadway Reconditioning – 30315 Mile 26.77 $ $

14(f): 24-inch Corrugated Aluminized Steel Pipe, 0.064-inch Thickness, Method 2 – 60201A

FT 40 $ $

14(g): Temporary Traffic Control - 63501 Lump Sum 1 XXXX $

Wet Weather Operational Rock for NFSR:

4600030, 4600033, 4688000, 4688240, 4693000, 4693640 15(a) Subbase, Grading A, Compaction Method (b), Government-Source – 30109 CY* NTE

9,000 $ $

15(b): Aggregate Surface Course, Grading F, Compaction Method (b), Government-Source

– 30115A

CY* NTE

6,000 $ $

16 Fall and Leave Individual Hazard Trees >100’ from the road Each NTE

1,500 $ $

Total All Optional Service Items $

MANDATORY TIMBER/PRODUCT REMOVAL PRICE SCHEDULE (Items 1 and 8 Product):

OPTIONAL TIMBER/PRODUCT REMOVAL PRICE SCHEDULE (Item 9 Product):

SPECIES PRODUCT QUANTITY UNIT OF

MEASURE

MINIMUM

ACCEPTABLE

OFFER

OFFER

(FLAT)

TOTAL

OFFER

All Species Grn Bio CV 53,708 Ton $0.40 $ $

Total – All Products $

SPECIES PRODUCT QUANTITY UNIT OF

MEASURE

MINIMUM

ACCEPTABLE

OFFER

OFFER

(FLAT) TOTAL OFFER

B.2 SCHEDULE NOTES

GENERAL INFORMATION:

All Contractors must be actively registered in the System for Award Management (SAM) at https://SAM.gov to be eligible for award under this solicitation. Registration in SAM is a free service – you do not need to pay to register in this system. If your registration is not active, you will not be considered for award.

PRICING INFORMATION: These schedules are for pricing/payment purposes. Refer to Section L, Instructions to Offerors for business proposal requirements. Evaluation criteria used by the Forest Service for proposals is in Section M of this solicitation.

Price Proposals MUST be provided on ALL Items in ALL Schedules: Mandatory Work Activities, Optional Work Activities, and Timber or Other Products Removal Price Schedules.

All timber products designated for removal have been determined to be deficit by the FS after deducting the costs to cut, yard, process, and haul products from the estimated delivered value;

therefore, this work has been priced as a service item. A per ton offer amount (flat) that equals or exceeds the minimum acceptable offer and a total offer shall be provided within the Timber/Product Removal Price Schedule. Road maintenance and road reconstruction costs are considered separately as priced service items.

**Offerors shall provide cost data associated with Mandatory Item 1 and Optional Item 9. This data shall be used for government review purposes only, is considered proprietary and will not be made public and will not be incorporated into the awarded contract as a material term/condition.

For Item 7, the unit of measurement is a Lump Sum, however partial payments may be made by a rough percentage of fish logs and woody debris delivered. Final payment for this Item shall not be approved until all 525 logs greater than 8-inch DBH and 350 CY of woody debris less than 8-inch DBH are delivered.

Wet Operational Rock: In order to operate heavy equipment or haul logs over Forest roads outside of the dry season (May 15 – October 15), placement of operational rock is required.

Even with rock installed, if heavy rainfall occurred, road use would need to be suspended to protect water quality and road condition. To allow for year-round work while economizing and reducing construction costs, the Forest has identified roads (haul routes) that may be treated with operational rock under Mandatory and Optional road reconstruction pay items. Please note that the estimated quantities are just that, estimates. Locations requiring rock placement would be determined by the CO based on specific road conditions.

Hazard trees within Units accessed by roads not identified for operational rock could be hand fallen and small fuels could be treated but no road use for log haul or heavy equipment operation

All Species Grn Bio CV 24,770 Ton $0.40 $ https://sam.gov/

FAC 2024-05 May 22, 2024 would be allowed between October 16 – May 14 unless the contractor met the requirements detailed in Appendix B, C5.12# for conditional use; generally speaking, rock would be laid at the contractor’s expense.

Award of Optional Work: Optional Items and corresponding timber removal may be awarded at time of contract award or by modification. If funding dictates and it is in the best interest of the government, optional work items may be awarded by Unit or Road and for amounts less than the total estimates based on the unit prices quoted. Unit prices prevail.

The lump sum prices for road reconstruction Items 14(a) Mobilization, 14(b) Soil Erosion and Pollution Control and 14(g) Temporary Traffic Control shall be awarded based on the percentage Item 14(e) Road Reconditioning miles awarded. Award quantities shall be based on expected need for Items 15(a) Subbase, 15(b) Surface Course and 16 Fall and Leave Individual Hazard Trees with NTE quantities and payment based on the actual quantity of work performed.

Quantities listed in Timber/Product removal schedules are estimates only. Refer to solicitation G.13, Timber Product Volume Estimation for the methodology used.

The following apply to Road Reconstruction work items only:

A. The construction work required within Mandatory Items 6(a-u) and Optional Items 14(a-

g) and 15(a-b) is subject the the Construction Wage Rate Requirements (see Wage Decision in Section J) and related regulations, formerly referred to as Davis-Bacon (i.e.

certified payroll submission).

B. A bid Guarantee is required in an amount equal to 20% of the total price offered for the Mandatory and Optional Construction Items only. Forestry services for fuels reduction and road maintenance work is not subject to bonding requirements. BID BONDS MUST BE PROVIDED WITH THE INITIAL OFFER. See FAR 52.228-1 Bid Guarantee (SEP 1996) (DEVIATION MAY 2020) in Section I.

C. Payment and Performance Bonds shall be required in an amount equal to 100% of the awarded value of road reconstruction work. See Section I. FAR 52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION APR 2020). Bonding costs shall be included the prices quoted for Mobilization. No separate payment for bond premiums shall be made.

D. Service Contract Act minimum wages applies to all fuels management work and road maintenance work. See Wage Determination in Section J.

***A Draft Small Business Subcontracting Plan is required with any proposal from a large business. Refer to FAR 52.219-9 Small Business Subcontracting Plan for requirements. USFS small business goals shall be supplied in the final solicitation.***

B.3 LAND MANAGEMENT ACTIVITIES

The Forest Service is executing this procurement under the stewardship contracting authority

FAC 2024-05 May 22, 2024 provided under Section 8205 of Public Law 113-79, the Agricultural Act of 2014 as amended under Section 204 & 207 of the Consolidated Appropriations Act (Omnibus Bill 2018).

Stewardship authority grants the Forest Service the authority to aggregate stewardship work activity requirements and solicit those requirements utilizing full and open competition.

Performance of land management activities shall be in accordance with the Project Description and Work Specifications. Payment for Land Management Work Activities in Schedule of Items will be made in Stewardship Credits and Appropriated Funds.

All Base Work Activities (Mandatory) shall be performed. Optional activities are listed in order of planned priority. Award may be made for optional items in any order that the Contracting Officer determines is in the best interest of the Government.

FAC 2024-05 May 22, 2024

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

The objectives of this project are to reduce the risks of hazardous fuels that have fallen across or remain standing along important access routes of the 2020 fire-affected road system so that access to and through the burned area can be restored. Fire severity varied across the treatment areas; burn severity maps and tables are included for planning purposes.

Activities include performing mitigation of risk along road from fire killed/damaged trees, reduction of roadside fuel accumulation and essential maintenance and reconstruction of roads.

This will be done by accomplishing the following:

• Cut and remove fire killed timber within 100 feet of roads from the Contract Area.

Hazard trees to be cut are Designated by Prescription.

• Fall and leave non-commercial hazard trees within Special Measure Areas (SMAs).

SMAs may include Riparian Reserves, cultural resource areas, wildlife habitat protection areas or other areas that requires special protections. This work is located within 100 feet of the road. SMAs do not overlap acres that require the cutting and removal of fire killed trees.

• Within unit polygons, fall and leave hazard trees that can strike the road outside of the 100-foot fuels removal area.

• Perform small fuels treatment within 30 feet of roads.

• Perform road reconstruction within the Contract Area during the dry season (May 15-

October 15).

• Perform pre-haul, during-haul and post-haul road maintenance within the Contract

Area.

• Yard and deliver non-commercial fish logs to specified deck locations.

• Remove hazardous fuels greater than 16” from Unit LH-62 that are within 100 feet of the road.

• Fall and leave individual hazard trees that are outside of units but within striking distance of the road.

Ground based hazard tree work shall be permitted year-round and must comply with required protections for wet season operations and Industrial Fire Precaution Level (IFPL). Mechanized equipment may be used for harvesting in units with slopes less than 30% during the dry season.

Any resultant contract will be a construction contract with service requirements and requirements for timber removal. Under this contract, “Contractor’s Operations” shall include activities of or use of equipment of Contractor, Contractor’s employees, agents, Subcontractors, or their employees or agents, acting in the course of their employment in operations hereunder on National Forest lands or within Forest Service protection boundary (unless acting under the immediate supervision of Forest Service). Contractor’s Operations shall be conducted in a workmanlike and orderly manner. The timing of required Forest Service designation of work on

Project Name: BCLH Stewardship IRSC Phase 1 the ground and the performance of other Forest Service work shall not be such as to cause unnecessary delay to Contractor.

C.2 PROJECT LOCATION

The BCLH Stewardship IRSC Phase 1 project is located approximately 2 to 12 miles east of Detroit, OR within the burn scars of the Beachie Creek Fire and Lionshead Fire, both of which occurred in 2020. The total project area is within the Detroit Ranger District of the Willamette National Forest. This Contract Area of 1,612 acres is located approximately in Sec 31-36, T09S, R06E; Sec 3, 4, 8-10,15-17,19,36 T09S, R06E; Sec 20,22-29, T10S, R06E; Sec 1-11, T10S, R07E; Sec 18,19, 1-5,19 T10S, R08E; Willamette Meridian, Surveyed & Unsurveyed, Marion County, Oregon. See maps included as attachments to the solicitation

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

For Road Reconstruction work requirements, the total estimated price for all Mandatory Items is between $5,000,000-$10,000,000. The total estimated price for all Optional Items is between $500,000-$1,000,000.

C.4 TECHNICAL SPECIFICATIONS

General specifications for each Contract Activity individually described by an item number in the Schedule of Service Items can be found in Appendix A. Specifications for timber removal can be found in Appendix B and associated road maintenance specifications in Appendix C for Stewardship related projects.

Standard Specifications for Construction and Bridges on Federal Highway Projects, FP-14, U.S.

Customary Units apply to the road reconstruction work and are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of the solicitation and any resultant contract. Copies of the Specifications are available by performing an internet search for the FP-14. Road reconstruction drawings, exhibits, worklists and Forest Service Supplemental Specifications (to tailor the FP-14 standard specifications) can be found in Appendix D.

AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

FAC 2024-05 May 22, 2024

C.5 CONTRACT AREA MAP

The boundaries of restoration activities identified in Appendices A, B, C, and D as well as Subdivisions or Payment Units and any cutting units thereof, are as shown on the attached "Contract Area Map’s," which is made a part hereof, and were, before solicitation, designated on the ground by Forest Service to meet the anticipated needs of the parties. The location of the Restoration Activities including Subdivisions or Payment Units and their approximate acreage are stated in Division A/. Subdivisions or Payment Units may be revised and additional ones may be established only by written agreement of both parties. Where applicable, the following are also identified on Contract Area Map:

(a) Identified claims limiting Contractor's rights

(b) Boundaries of cutting units

(c) Areas where leave trees are marked to be left uncut

(d) Roads listed

(e) Sources of base course, rock riprap and surface rock

(f) Roads where log hauling is prohibited or restricted

(g) Roads and trails to be kept open

(h) Improvements to be protected

(i) Locations of known historical sites

(j) Maximum stump heights when more than one height is listed by areas

(k) Skidding or yarding methods specified

(l) Streamcourses to be protected

(m) Other features required by Appendix B; and

(n) Boundaries of stewardship work activities.

C.6 GOVERNMENT FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause(s) contained in Section I of the contract.

The following property shall be supplied for use without charge:

• FSSS 30109 – Subbase, Grading A, Compaction Method (b), McCoy Pit (44.69266N, 122.03350W on 2233-605). This aggregate shall be available for use no later than 8/15/2025.

• FSSS 30115A and 30115B - Aggregate Surfacing, Grading F, Compaction Method (b), location: McCoy Pit (44.69266N, 122.03350W on 2233-605). This aggregate shall be available for use no later than 8/15/2025.

C.7 OPERATING PLAN AND SCHEDULE

The Contractor will provide, as part of the technical proposal, a detailed timeline of when the contract requirements will be accomplished while conforming to the requirements within Section F.5. The operating plan should indicate the sequence of activities that will take place to accomplish the tasks described within the solicitation, Appendix A, Appendix B, Appendix C, and Appendix D including proposed start and completion dates.

FAC 2024-05 May 22, 2024

C.8 SUSTAINABLE ACQUISITIONS

The Contractor shall comply with the Agricultural Act of 2014; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C.

8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and Sustainable Product Procurement,” dated February, 2012 to provide biobased products.

In compliance with FAR Part 23.4 through performance of this contract, the Contractor shall make maximum use of EPA designated and USDA designated biobased in accordance with FAR clause 52.223- 2 Affirmative Procurement of Biobased Products under Service and Construction Contracts and 52.223- 17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts

The Contractor shall utilize products and material made from biobased materials (e.g. biobased greases, biobased hydraulic fluids, biobased absorbents) to the maximum extent possible in the performance of this contract without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. Information about this requirement and a catalog of products are available at the Bio-Preferred Web Site.

The Contractor shall utilize products and material to the maximum extent possible in the performance of this contract from EPA’s list of designated products and the accompanying recommendations for post-consumer content and recovered materials content in the following eight categories: Construction products, Landscaping products, Non-paper Office Products, Paper and Paper Products, Park and Recreation products, Transportation Products, Vehicular Products, and Miscellaneous Products.

Compliance with the USDA Biobased requirements requires Contractors to report the purchase of biobased products during the previous Government fiscal year, between October 1 and September 30 under service and construction contracts through the System for Award Management at https://sam.gov/content/home and provide a copy of the report to the Contracting Officer no later than October 31 of each year during contract performance and at the end of contract performance.

7.1 Sustainable products identified for this solicitation:

The following is a list of categories for bio-preferred products and EPA products that that may be used in the performance of this contract. The list is not all inclusive; the Contractor shall research for available products.

7.1.1 Bio Preferred Products:

a Diesel Fuel Additives

(1) Any substance, other than one composed solely of carbon and/or hydrogen, that is intentionally added to diesel fuel (including any added to a motor vehicle's fuel system) and that is not intentionally removed prior to sale or use.

(2) Neat biodiesel, also referred to as B100, when used as an additive. Diesel fuel additive does not mean neat biodiesel when used as a fuel or blended biodiesel fuel (e.g., B20). 90% - Minimum Biobased Content.

b Hydraulic Fluids - Mobile Equipment Hydraulic fluids formulated for general use in nonstationary equipment, such as tractors, end loaders, or backhoes. 44% - Minimum Biobased Content.

c Penetrating Lubricants http://www.biopreferred.gov/BioPreferred/ https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program https://sam.gov/content/home http://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml

FAC 2024-05 May 22, 2024

Products formulated to provide light lubrication and corrosion resistance in close tolerant internal and external applications including frozen nuts and bolts, power tools, gears, valves, chains, and cables. 68% - Minimum Biobased Content.

d Greases - Truck Lubricants composed of oils thickened to a semisolid or solid consistency using soaps, polymers or other solids, or other thickeners. Lubricants that are designed for use on the fifth wheel of tractor trailer trucks onto which the semi-trailer rests and pivots. 71% - Minimum Biobased Content.

e Gear Lubricants Products, such as greases or oils, that are designed to reduce friction when applied to a toothed machine part (such as a wheel or cylinder) that meshes with another toothed part to transmit motion or to change speed or direction. 58% - Minimum Biobased Content.

f Fuel Conditioners Products formulated to improve the performance and efficiency of engines by providing benefits such as removing accumulated deposits, increasing lubricity, removing moisture, increasing the cetane number, and/or preventing microbial growths within the fuel system. 64% - Minimum Biobased Content.

h Erosion Control Woven or non-woven fiber materials manufactured for use on construction, demolition, or other sites to prevent wind or water erosion of loose earth surfaces, which may be combined with seed and/or fertilizer to promote growth. 77% - Minimum Biobased Content.

g 2-Cycle Engine Oils Lubricants designed for use in 2-cycle engines to provide lubrication, decreased spark plug fouling, reduced deposit formation, and/or reduced engine wear. 34% - Minimum Biobased Content.

7.1.2 EPA Designated Products:

Plastic trash bags, printer ribbons, toner cartridges, print & writing papers, Traffic Barricades, Traffic Cones, Engine Coolants, Rebuilt Vehicular Parts, Re-refined lubricating oils, retread tires, manual grade strapping, signage, sorbents.

C.9 DEFINITIONS

Acceptable Quality Level: The allowable leeway or variance from a standard before the government will reject the specific service. As long as the percent of defective performance does not exceed the AQL, the service will not be rejected by the government. The contractor, however, must re-perform the defective service when possible.

Biobased Products: See Sustainable Acquisitions Contracting Officer (CO): Individual with authority to bind the government with their signature on the contract.

Contracting Officer Representative (COR): Individual(s) designated to act on the behalf of the CO within the delegation given them in writing.

Period of performance (also Performance period or Contract time): All calendar days allowed for completion of contract work. Includes all days of the week including weekends and holidays.

Quality Assurance: Those actions taken by the government to check goods or services to determine that they meet the requirements of the Statement of Work (SOW).

Quality Assurance Surveillance Plan (QASP): An organized written document used for quality assurance surveillance. The document contains information about how the government will assess performance, checklists, and may contain decision tables.

Quality Control: Those actions taken by a contractor to control the production of goods or services so that they will meet the requirements of the Performance Work Statement. Refer to Inspection and Acceptance 52.246-4 or 52.246-12 and Contractors Quality Control Plan as described in Section E.

http://www.epa.gov/epawaste/conserve/tools/cpg/products/index.htm

FAC 2024-05 May 22, 2024

Quality Control Plan: Contractors plan for self-monitoring work prior to Government inspection and acceptance. See Section E.

Random Sampling: A method of looking at a few individual items in a lot to determine the quality of that lot against a standard.

(Acceptable) Service: A job performed to the standard and within the acceptable quality level. The contractor must do the specific job, and meet the standard, and meet the acceptable quality level before one can say that performance has been acceptable and that he/she should be paid.

Standard: An acknowledged measure of comparison.

Stewardship Contracting: An exchange of goods/products for services including construction.

Sustainable Acquisitions (FAR Part 23.4 – Use of recovered materials and biobased products)

a. Biobased Products: Managed by the U.S. Department of Agriculture (USDA), the goal of the BioPreferred program is to increase the purchase and use of biobased products. The BioPreferred program was created by the 2002 Farm Bill and reauthorized and expanded as part of the Agricultural Act of 2014 (the 2014 Farm Bill). The program's purpose is to spur economic development, create new jobs and provide new markets for farm commodities. The increased development, purchase, and use of biobased products reduce our nation's reliance on petroleum, increase the use of renewable agricultural resources, and contribute to reducing adverse environmental and health impacts. Information on biobased/bio-preferred products can be found at the BioPreferred Site . The Contractor shall comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts and the provision at FAR 52.223-1, Biobased Product Certification.

b. EPA-designated items: Products that are or can be made with recovered material.

The Comprehensive Procurement Guideline (CPG) program is part of EPA's continuing effort to promote the use of materials recovered from solid waste. Buying recycled-content products ensures that the materials collected in recycling programs will be used again in the manufacture of new products. The contractor shall comply with the clause at FAR 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts.

http://www.biopreferred.gov/BioPreferred/faces/pages/AboutBioPreferred.xhtml http://www.gpo.gov/fdsys/pkg/BILLS-113hr2642enr/pdf/BILLS-113hr2642enr.pdf http://www.biopreferred.gov/BioPreferred/ http://www.epa.gov/epawaste/conserve/tools/cpg/index.htm

FAC 2024-05 May 22, 2024

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

FAC 2024-05 May 22, 2024

SECTION E--INSPECTION AND ACCEPTANCE

E.1 52.252-2 CLAUSES INCORPROATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:

https://www.acquisition.gov/browse/index/far

FAR 52.246-4 Inspection of Services- Fixed Price (AUG 1996) FAR 52.246-12 Inspection of Construction (AUG 1996)

E.2 CONTRACTOR QUALITY CONTROL INSPECTION SYSTEM

The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contractor shall produce written inspection records in a format and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data.

E.2.1 Quality Control Plan. The Contractor shall provide a general Quality Control Plan (QCP) with the technical proposal. The Contractor shall supplement the QCP within 7 days before start work based on items awarded to the Contractor and Government comments. The contractor shall conduct quality control inspections on all aspects of work. The field inspections shall be performed on each item and sub-item listed in the Schedule.

The general Quality Control Plan must demonstrate how the Contractor will assure quality meets the requirements and specifications of the contract. The Plan shall describe how quality will be monitored to assure the performance standards are met, the supervision of crew and work, and personnel that will be performing the quality control.

E.2.2 Contractor Quality Control Inspection, At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data. Inspection procedures must provide the following information:

E.3 ACCEPTANCE OF SERVICES

The Contractor shall provide a written request for inspection and submit inspection sheets in accordance with the QCP. The Government will conduct an inspection and up to one re-https://www.acquisition.gov/browse/index/far

FAC 2024-05 May 22, 2024 inspection for each unit. If the contractor fails to meet the minimum AQL, the contractor shall rework the unit. Anytime more than two inspections are required per unit, the contractor may be assessed for additional inspections, which will include mileage and hourly rate of the COR. If follow-up inspections indicate that the minimum AQL was not met, the work will be deemed unsatisfactory and a deduction in payment may result (Section G-3.4). Acceptance may be made for all or portions of work.

E.4 ACCEPTANCE OF CONSTRUCTION

Refer to FAR Clause 52.246-12 – Inspection of Construction for information on Government acceptance of construction. See also Standard FP-14 Construction Specifications, Section 106.

Acceptance of Work as supplemented (Appendix D Forest Service Supplemental Specifications).

E.5 GOVERNMENT QUALITY ASSURANCE SUREILLANCE PLAN

Quality assurance specific to individual items is found in Section IV of Appendix A. Quality assurance specifications for Road Reconstruction are found in Appendix D.

FAC 2024-05 May 22, 2024

Quality Control Plan: Contractors plan for self-monitoring work prior to Government inspection and acceptance. See Section E.

Random Sampling: A method of looking at a few individual items in a lot to determine the quality of that lot against a standard.

(Acceptable) Service: A job performed to the standard and within the acceptable quality level. The contractor must do the specific job, and meet the standard, and meet the acceptable quality level before one can say that performance has been acceptable and that he/she should be paid.

Standard: An acknowledged measure of comparison.

Stewardship Contracting: An exchange of goods/products for services including construction.

Sustainable Acquisitions (FAR Part 23.4 – Use of recovered materials and biobased products)

a. Biobased Products: Managed by the U.S. Department of Agriculture (USDA), the goal of the BioPreferred program is to increase the purchase and use of biobased products. The BioPreferred program was created by the 2002 Farm Bill and reauthorized and expanded as part of the Agricultural Act of 2014 (the 2014 Farm Bill). The program's purpose is to spur economic development, create new jobs and provide new markets for farm commodities. The increased development, purchase, and use of biobased products reduce our nation's reliance on petroleum, increase the use of renewable agricultural resources, and contribute to reducing adverse environmental and health impacts. Information on biobased/bio-preferred products can be found at the BioPreferred Site . The Contractor shall comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts and the provision at FAR 52.223-1, Biobased Product Certification.

b. EPA-designated items: Products that are or can be made with recovered material.

The Comprehensive Procurement Guideline (CPG) program is part of EPA's continuing effort to promote the use of materials recovered from solid waste. Buying recycled-content products ensures that the materials collected in recycling programs will be used again in the manufacture of new products. The contractor shall comply with the clause at FAR 52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts.

http://www.biopreferred.gov/BioPreferred/faces/pages/AboutBioPreferred.xhtml http://www.gpo.gov/fdsys/pkg/BILLS-113hr2642enr/pdf/BILLS-113hr2642enr.pdf http://www.biopreferred.gov/BioPreferred/ http://www.epa.gov/epawaste/conserve/tools/cpg/index.htm

FAC 2024-05 May 22, 2024

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

FAC 2024-05 May 22, 2024

SECTION E--INSPECTION AND ACCEPTANCE

E.1 52.252-2 CLAUSES INCORPROATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:

https://www.acquisition.gov/browse/index/far

FAR 52.246-4 Inspection of Services- Fixed Price (AUG 1996) FAR 52.246-12 Inspection of Construction (AUG 1996)

E.2 CONTRACTOR QUALITY CONTROL INSPECTION SYSTEM

The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contractor shall produce written inspection records in a format and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data.

E.2.1 Quality Control Plan. The Contractor shall provide a general Quality Control Plan (QCP) with the technical proposal. The Contractor shall supplement the QCP within 7 days before start work based on items awarded to the Contractor and Government comments. The contractor shall conduct quality control inspections on all aspects of work. The field inspections shall be performed on each item and sub-item listed in the Schedule.

The general Quality Control Plan must demonstrate how the Contractor will assure quality meets the requirements and specifications of the contract. The Plan shall describe how quality will be monitored to assure the performance standards are met, the supervision of crew and work, and personnel that will be performing the quality control.

E.2.2 Contractor Quality Control Inspection, At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data. Inspection procedures must provide the following information:

E.3 ACCEPTANCE OF SERVICES

The Contractor shall provide a written request for inspection and submit inspection sheets in accordance with the QCP. The Government will conduct an inspection and up to one re-https://www.acquisition.gov/browse/index/far

FAC 2024-05 May 22, 2024 inspection for each unit. If the contractor fails to meet the minimum AQL, the contractor shall rework the unit. Anytime more than two inspections are required per unit, the contractor may be assessed for additional inspections, which will include mileage and hourly rate of the COR. If follow-up inspections indicate that the minimum AQL was not met, the work will be deemed unsatisfactory and a deduction in payment may result (Section G-3.4). Acceptance may be made for all or portions of work.

E.4 ACCEPTANCE OF CONSTRUCTION

Refer to FAR Clause 52.246-12 – Inspection of Construction for information on Government acceptance of construction. See also Standard FP-14 Construction Specifications, Section 106.

Acceptance of Work as supplemented (Appendix D Forest Service Supplemental Specifications).

E.5 GOVERNMENT QUALITY ASSURANCE SUREILLANCE PLAN

Quality assurance specific to individual items is found in Section IV of Appendix A. Quality assurance specifications for Road Reconstruction are found in Appendix D.

FAC 2024-05 May 22, 2024

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

AGAR 452.228-71 Insurance Coverage (NOV 1996)- Alternate I (NOV 1996)

Pursuant to FAR clause FAR 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:

(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.

(b) General Liability. (1) The Contractor shall have bodily injury liability coverage written on a comprehensive form of policy of at least $500,000 per occurrence. (2) The Contractor shall have property damage liability insurance shall be required in the amount of ____*___ per occurrence.

(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.

(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(End of clause)

AGAR 452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the

FAC 2024-05 May 22, 2024

SECTION F--DELIVERIES OR PERFORMANCE

F.1 52.252-2 CLAUSES INCORPROATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:

https://www.acquisition.gov/browse/index/far.

FAR 52.211-18 Variation in Estimated Quantity (APR 1984) FAR 52.236-15 Schedules for Construction Contracts (APR 1984) FAR 52.242-14 Suspension of Work (APR 1984)

FAR 52.211.10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 10/31/2027 for the Mandatory Work Items excluding Item 7 and 10/31/2028 for the Optional Items awarded. Item 7: Yard and Deliver Noncommercial Fish Logs to Deck Locations shall be completed not later than May 1, 2026. Timber Removal activities shall be scheduled and carried out in accordance with the Timber Removal Specifications in Appendix B and C and as approved by the Contracting Officer. The time stated for completion shall include final cleanup of the premises.

(End of clause)

F.3 AGAR 452.211-74 PERIOD OF PERFORMANCE (FEB 1988)

The effective period of this contract is from date of award through 10/31/2028.

Additional clauses will be added to the final solicitation.

https://www.acquisition.gov/browse/index/far

PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
BCLH STEWARDSHIP IRSC PHASE 1
DETROIT RANGER DISTRICT
WILLAMETTE NATIONAL FOREST
MARION COUNTY, OREGON
B.1 SCHEDULE OF ITEMS
B.2 SCHEDULE NOTES
B.3 LAND MANAGEMENT ACTIVITIES
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SCOPE OF CONTRACT
C.2 PROJECT LOCATION
C.3 MAGNITUDE OF CONSTRUCTION PROJECT
C.4 TECHNICAL SPECIFICATIONS
SECTION D--PACKAGING AND MARKING
D.1 PACKING AND MARKING
D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE
SECTION E--INSPECTION AND ACCEPTANCE
SECTION F--DELIVERIES OR PERFORMANCE
F.3 AGAR 452.211-74 PERIOD OF PERFORMANCE (FEB 1988)
SECTION G--CONTRACT ADMINISTRATION DATA
G.1 CLAUSES
G.2 OTHER REQUIREMENTS
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H.1 CLAUSES
H.2 OTHER REQUIREMENTS
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I.1 CLAUSES
PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J--LIST OF ATTACHMENTS
J.1 ATTACHMENTS
PART IV--REPRESENTATIONS AND INSTRUCTIONS
SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND
OTHER STATEMENTS OF OFFERORS OR RESPONDENTS
K.1 PROVISIONS
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS
L.1 PROVISIONS
SECTION M--EVALUATION FACTORS FOR AWARD
M.1 PROVISIONS
M.2 PROPOSAL EVALUATION
M.3 TECHNICAL EVALUATION FACTORS

File details come from the government source that posted it. Updated .