Thomas BayYG_IRSC_Appendix_D_FINAL.pdf
PDF 5 MB Posted
- Attached to
- Thomas Bay YG Stewardship IRSC Federal contract opportunity
- Solicitation number
- 12363N25Q4151
- Issued by
- Department of Agriculture Forest Service
About this file
This document is Appendix D for the Thomas Bay Young-Growth Stewardship Integrated Resource Service Contract (IRSC), containing detailed road reconstruction and improvement specifications for the Tongass National Forest in Petersburg, Alaska. The appendix includes a comprehensive table of contents for road-related documents, covering road reconstruction plans, specification lists, and supplemental specifications, totaling 53 pages of technical documentation prepared by the U.S. Department of Agriculture Forest Service in April 2025.
The road package provides extensive technical details for road work, including road reconstruction plans, specification lists, and supplemental specifications. Key components include guidance for road maintenance, reconstruction of temporary roads, culvert installations, drainage system improvements, and environmental considerations. The document outlines precise technical requirements for road work within the Thomas Bay area, covering aspects such as road surface preparation, aggregate placement, erosion control, culvert installation, and specific environmental mitigation techniques like beaver deceiver analog installations and riprap placement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 001_ThomasBayYG_Attachment 1.pdf | ||
| Amendment 001_ThomasBayYG_Attachment 2_ July23 Site Visit Notes.pdf | ||
| Sol_12363N25Q4151_Amd_001_ThomasBayYG.pdf | ||
| ThomasBayYG_IRSC_Appendix_A_FINAL.pdf | ||
| ThomasBayYG_IRSC_Appendix_C_FINAL.pdf | ||
| 25002 Thomas Bay YG Stewardship IRSC Cruise of Record.pdf | ||
| GeoRef_Map_181-183.pdf | ||
| 12363N25Q4151_ThomasBayYB_IRSC_Solicitation-1.pdf | ||
| ThomasBayYG_IRSC_Appendix B_Tree_Measurement_FINAL.pdf | ||
| GeoRef_Map_181-183_color.pdf | ||
| GeoRef_Map_141_145_146.pdf | ||
| GeoRef_Map_141_145_146_color.pdf | ||
| Thomas_Bay_YG_Stew_IRSC_VicinityMapInset.pdf | ||
| Thomas_Bay_YG_Stew_IRSC_VicinityMap.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX D
THOMAS BAY YOUNG-GROWTH
STEWARDSHIP IRSC
ROAD PACKAGE – TABLE OF CONTENTS
ITEM DESCRIPTION NUMBER OF PAGES
TABLE OF CONTENTS 1
ROAD RECONSTRUCTION
PLANS 13
SPECIFICATION LIST FOR
ROADS 4
PROJECT FS SUPPLEMENTAL
SPECIFICATIONS 53
U.S.D.A. FOREST SERVICE
TONGASS NATIONAL FOREST
Petersburg Supervisors Office 123 Scow Bay Loop Road
Petersburg, AK 99901
April 2025
VICINITY MAP
United States Department of Agriculture Forest Service
THOMAS BAY YOUNG-GROWTH STEWARDSHIP
INTEGRATED RESOURCE SERVICE CONTRACT (IRSC)
4/2 5/2
5 1 0:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
REGION 10 (ALASKA REGION)
TONGASS NATIONAL FOREST
PETERSBURG RANGER DISTRICT
PLANS FOR PROPOSED FOREST DEVELOPMENT PROJECT
PROJECT LOCATION MAP
JUNEAU
CRAIG
YAKUTAT
SKAGWAY
KETCHIKAN
WRANGELL
PETERSBURG
HOONAH PROJECT
LOCATION
SHEET OF01 13
RECOMMENDED BY:
APPROVED:
FOREST ENGINEER
TONGASS NATIONAL FOREST
DATE
FOREST SUPERVISOR
TONGASS NATIONAL FOREST
DATE
INDEX OF SHEETS
SHEET SHEET TITLE DATE
1 TITLE SHEET 04/2025
2-3 SCHEDULE OF QUANTITIES & GENERAL NOTES 04/2025
4 PROJECT AREA 04/2025
5 ROAD WORK LISTS 04/2025
6-7 LOG CULVERT DETAILS 04/2025
8 TYPICAL BEAVER DAM ANALOG & TYPICAL CULVERT
CATCH BASIN 04/2025
9 TYPICAL BRUSHING 04/2025
10 TYPICAL CULVERT DETAILS 04/2025
11 TYPICAL EROSION CONTROL DEVICES 04/2025
12 TYPICAL OVERLAY SECTION 04/2025
13 TYPICAL PIT & QUARRY DEVELOPMENT 04/2025
MATERIAL SOURCES
CONTRACTOR FURNISHED
CRUSHED AGGREGATE
RIPRAP
UNCLASSIFIED BORROW
GOVERNMENT FURNISHED
WASTE SITE
ALL OTHER MATERIALS ARE CONTRACTOR FURNISHED
RECOMMENDED BY:
DISTRICT RANGER
PETERSBURG RANGER DISTRICT
DATE
NOT TO SCALE
USGS QUAD, PETERSBURG D-2 & D-3 SE, ALASKA
PROJECT
LOCATION
AutoCAD SHX Text
KEY MAP
AutoCAD SHX Text 140%%d
AutoCAD SHX Text 142%%d
AutoCAD SHX Text 58%%d
AutoCAD SHX Text 138%%d
AutoCAD SHX Text 136%%d
AutoCAD SHX Text
SITKA
AutoCAD SHX Text 132%%d
AutoCAD SHX Text 134%%d
AutoCAD SHX Text 136%%d
AutoCAD SHX Text 138%%d
AutoCAD SHX Text 140%%d
AutoCAD SHX Text 142%%d
AutoCAD SHX Text 60%%d
AutoCAD SHX Text
CANADA
AutoCAD SHX Text
ALASKA
AutoCAD SHX Text 62%%d
AutoCAD SHX Text 56%%d
AutoCAD SHX Text 54%%d
AutoCAD SHX Text 132%%d
AutoCAD SHX Text 134%%d
AutoCAD SHX Text 128%%d
AutoCAD SHX Text 130%%d
AutoCAD SHX Text 60%%d
AutoCAD SHX Text 58%%d
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 9:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
SCHEDULE OF ITEMS &
GENERAL NOTES
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
02 13
GENERAL NOTES
DISPOSAL: All materials designated for removal become the property of the contractor & will be disposed of by removing from the forest in an environmentally safe manner in accordance with all local, state & federal requirements. Dispose of excess or unsuitable material at the location designated in FSSS Section 105. Hauling of excess or unsuitable material is incidental to associated work.
EQUIPMENT STORAGE: Storage of all equipment on government lands will be at a location approved by the CO.
IN-STREAM WORK: All in-stream work for the LOG CULVERT will be done between June 01st and September 15th. All in-stream work for cleaning the CULVERT CATCH BASIN & installing the BEAVER DECEIVER ANALOG will be done between July 18th and August 15th. Allowance shall be given to the Forest Service to capture & remove fish & other aquatic organisms from within the construction work area prior to & during work activities.
ROAD WORK: Depths of all materials are given as final compacted depths. Remove all berms, existing or created, unless designated to remain, to allow drainage of water from the traveled way.
ROCK MATERIAL: All Road & Stream Rock Material is in-place quantity not adjusted for shrink & swell or compaction.
SEEDING: Seed and mulch all disturbed soil that is not within travel way or stream channel. Use Tongass Seed Mix. See FSSS Subsection 625.07
SPECIFICATIONS: Construct the project in compliance with Federal Highway Administration Standard Specifications for Construction of Road and Bridges on Federal Highway Projects (FP-14) and applicable Forest Service Supplemental Specifications.
TEMPORARY TRAFFIC CONTROL: Submit a temporary traffic control plan to the Contracting Officer for approval at least 30 days prior to intended use.
BASE BID
ITEM
NO. ITEM DESCRIPTION UNIT QUANTITYREMARKS
A 151 MOBILIZATION LUMP SUM ALL LSQ
TRAFFIC CONTROL, FIRE PROTECTION, EQUIPMENT CLEANING, AND
ANY MAINTENANCE OF EXISTING NFS ROADS FOR CONTRACTOR
ACCESS IS INDIRECT TO THIS PAY ITEM.
SCHEDULE OF QUANTITIES, SHEET 1 OF 2
CQ= CONTRACT QUANTITY (SEE SECTION 109.02(B) OF THE STANDARD SPECIFICATIONS);
BASE BID
ITEM
NO. ITEM DESCRIPTION UNIT QUANTITYREMARKS
A T-811 BLADING, COMPACTION METHOD B,
PRE-HAUL MILE 3.33 AQ SEE APPENDIX C, T-SPEC T-811.
B T-811 BLADING, COMPACTION METHOD B,
POST-HAUL MILE 3.33 AQ SEE APPENDIX C, T-SPEC T-811.
C T-842 BRUSHING, METHOD A, POST-HAUL MILE 3.33 AQ SEE APPENDIX C, T-SPEC T-842 & SHEET 09.
D T-839 MAINTENANCE FOR PROJECT USE,
POST-HAUL MILE 3.33 LSQ SEE APPENDIX C, T-SPEC T-839.
ITEM 4: ROAD WORK MOBILIZATION
ITEM 5: PRE-HAUL & POST-HAUL MAINTENANCE
BASE BID
ITEM
NO. ITEM DESCRIPTION UNIT QUANTITYREMARKS
A 572 LOG CULVERT - BRIDGE STRINGERS NOT
ADJACENT TO SITE LUMP SUM ALL LSQ SEE GENERAL NOTES FOR CONSTRUCTION TIMING WINDOW & FSSS
639 & SHEETS 6-7 FOR SPECIFIC REQUIREMENTS.
B
832 REMOVAL OF 100' OF TEMPORARY ROAD
PRISM TO RESTORE FISH HABITAT, INCLUDES
REMOVAL OF LOG CULVERT & SIDECAST OF
EXCESS MATERIAL, APPROXIMATELY 100 CUBIC
YARDS
LUMP SUM ALL LSQ SEE SHEET 05 FOR MORE INFORMATION.
C 303 ROAD RECONDITIONING, COMPACTION
PLACEMENT METHOD 2 MILE 1.63 AQ
D
625 SEEDING, EDGE OF ROAD TO CUT SLOPES,
DRY METHOD (WITHOUT MULCH) MILE 1.63 AQ USE TONGASS SEED MIX. SEE FSSS SUBSECTION 625.07.
E
204 UNCLASSIFIED BORROW, COMPACTION
PLACEMENT METHOD 2, INCLUDES HAUL CUBIC YARD 500 CQ CONTRACTOR FURNISHED.
ITEM 6: TEMPORARY ROAD DEVELOPMENT & DECOMMISSIONING
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
E
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
SCHEDULE OF ITEMS &
GENERAL NOTES
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
03 13
BASE BID
ITEM
NO. ITEM DESCRIPTION UNIT QUANTITYREMARKS
A 834 CLEAN CULVERT CATCH BASIN, 60"
DIAMETER EACH 1 AQ SEE GENERAL NOTES FOR CONSTRUCTION TIMING WINDOW & FSSS
838 & SHEET 8 FOR SPECIFIC REQUIREMENTS.
B 639 INSTALL CULVERT BEAVER DAM ANALOG LUMP SUM ALL LSQ
CONTRACTOR FURNISHED. SEE GENERAL NOTES FOR
CONSTRUCTION TIMING WINDOW & FSSS 639 & SHEET 8 FOR
SPECIFIC REQUIREMENTS.
C
302 REGRADE & RESURFACE EXISTING PARKING
AREA USING CRUSHED AGGREGATE,
COMPACTION PLACEMENT METHOD 2
LUMP SUM 100 CQ CONTRACTOR FURNISHED.
D
708 24" POLY PIPE, BELL/SPIGOT DOUBLE WALL,
2 23" X 12" CORRUGATIONS
LINEAR
FOOT 60 AQ CONTRACTOR FURNISHED.
E
302 RESURFACING USING CRUSHED
AGGREGATE, COMPACTION PLACEMENT METHOD
CUBIC YARD 900 CQ CONTRACTOR FURNISHED.
F 705 RIPRAP CLASS 4 PLACEMENT TO REINFORCE
FAILING ROAD FILL CUBIC YARD 100 CQ CONTRACTOR FURNISHED.
G 303 ROAD RECONDITIONING, COMPACTION
PLACEMENT METHOD 2 MILE 1.1 AQ
H
202 REMOVE APPROXIMATELY 20 EXISTING
TREES, INCLUDES FELLING DELIMBING,
BUCKING & END HAUL <= 2 MILES
LUMP SUM ALL LSQ
GOVERNMENT FURNISHED. MERCHANTABLE TREES SHALL BE
FLAGGED BY THE COR & LOGS STOCKPILED AT A LOCATION
DESIGNATED BY THE COR. UNMERCHENTABLE TREES TO BE
DISPOSED OF AS DESIGNATED BY THE COR.
SCHEDULE OF QUANTITIES, SHEET 2 OF 2
CQ= CONTRACT QUANTITY (SEE SECTION 109.02(B) OF THE STANDARD SPECIFICATIONS);
OPTION ITEM 1
ITEM
NO. ITEM DESCRIPTION UNIT QUANTITYREMARKS
I
638 REMOVAL & EXCESS OF 5 ABANDONED
VEHICLES OFF USFS LAND (INCLUDES CLEAN-UP
OF HAZARDOUS MATERIALS)
LUMP SUM ALL LSQ GOVERNMENT FURNISHED. SEE FSSS 638 & SHEET 5 FOR SPECIFIC
REQUIREMENTS.
ITEM 7: ROAD IMPROVEMENTS
ITEM 7: ROAD IMPROVEMENTS
OPTION ITEM 2
ITEM
NO. ITEM DESCRIPTION UNIT QUANTITYREMARKS
J
302 RESURFACING USING CRUSHED
AGGREGATE, COMPACTION PLACEMENT METHOD
CUBIC YARD 900 CQ CONTRACTOR FURNISHED.
ITEM 7: ROAD IMPROVEMENTS
GENERAL NOTES
DISPOSAL: All materials designated for removal become the property of the contractor & will be disposed of by removing from the forest in an environmentally safe manner in accordance with all local, state & federal requirements. Dispose of excess or unsuitable material at the location designated in FSSS Section 105. Hauling of excess or unsuitable material is incidental to associated work.
EQUIPMENT STORAGE: Storage of all equipment on government lands will be at a location approved by the CO.
IN-STREAM WORK: All in-stream work for the LOG CULVERT will be done between June 01st and September 15th. All in-stream work for cleaning the CULVERT CATCH BASIN & installing the BEAVER DECEIVER ANALOG will be done between July 18th and August 15th. Allowance shall be given to the Forest Service to capture & remove fish & other aquatic organisms from within the construction work area prior to & during work activities.
ROAD WORK: Depths of all materials are given as final compacted depths. Remove all berms, existing or created, unless designated to remain, to allow drainage of water from the traveled way.
ROCK MATERIAL: All Road & Stream Rock Material is in-place quantity not adjusted for shrink & swell or compaction.
SEEDING: Seed and mulch all disturbed soil that is not within travel way or stream channel. Use Tongass Seed Mix. See FSSS Subsection 625.07
SPECIFICATIONS: Construct the project in compliance with Federal Highway Administration Standard Specifications for Construction of Road and Bridges on Federal Highway Projects (FP-14) and applicable Forest Service Supplemental Specifications.
TEMPORARY TRAFFIC CONTROL: Submit a temporary traffic control plan to the Contracting Officer for approval at least 30 days prior to intended use.
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
18-3
18-2
18-1
14-1
14-5
14-6
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 7:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
PROJECT AREA
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
04 13
LEGEND:
NATIONAL FOREST SYSTEM ROAD IMPROVEMENT WORK
TEMPORARY ROAD RECONSTRUCTION
OTHER ROADS
CUTTING BOUNDARY
POTENTIAL FOREST SERVICE MATERIAL SOURCE (ROCK QUARRY)
6252_1.20R
6252_1.38R
6100_0.67L
MP 5.528 - CLEAN EXISTING
CULVERT CATCH BASING, 60"
DIAMETER CULVERT & INSTALL NEW
CULVERT BEAVER DAM ANALOG
MILEPOST 3.149-4.249 - POINT AGASSIZ
ROAD & PARKING AREA IMPROVEMENTS
MILEPOST 0.0 - THOMAS BAY LOG
TRANSFER FACILITY (LTF); SHOWN
FOR REFERENCE ONLY
THOMAS BAY
NATIONAL FOREST SYSTEM
ROADS THIS CONTRACT
PRE & POST HAUL ROUTES
ROAD # ROAD NAME DISTANCE (MILES)
6100 MUD 0.95
6252 POINT AGASSIZ 1.38
6256 NORTH BLIND
RIVER 1.00
TEMPORARY ROADS THIS
CONTRACT
TEMPORARY ROAD RECONSTRUCTION
ROAD # ROAD NAME DISTANCE (MILES)
6100_0.67L N/A 0.55 6252_1.20R N/A 0.55 6252_1.38R N/A 0.53
END PRE &
POST HAUL
MAINTENANCE
BEGIN PRE &
POST HAUL
MAINTENANCE
END PRE &
POST HAUL
MAINTENANCE
NATIONAL FOREST SYSTEM
ROADS THIS CONTRACT
SYSTEM ROAD IMPROVEMENTS
ROAD # ROAD NAME DISTANCE (MILES)
6252 POINT AGASSIZ 1.10
6256 NORTH BLIND
RIVER
SEE WORK ITEM
AT MILE POST
5.528 IN PROJECT
MAP BELOW FOR
WORK LOCATION
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text
SCALE IN MILES
AutoCAD SHX Text
AutoCAD SHX Text 1/4
1/2
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
ROAD WORK LISTS
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
05 13
NFS ROAD 6256: NORTH BLIND RIVER
PRE & POST HAUL MAINTENANCE
MP DESCRIPTION OF WORK
0.0
BEGIN ROAD WORK AT THE THOMAS BAY LTF.
BEGIN ROAD BLADING COMPACTION METHOD B.
BEGIN BRUSHING METHOD A.
BEGIN MAINTENANCE FOR PROJECT USE.
1.0
END ROAD WORK AT JUNCTION WITH NFS ROAD
6252.
END ROAD BLADING COMPACTION METHOD B.
END BRUSHING METHOD A.
END MAINTENANCE FOR PROJECT USE.
NFS ROAD 6252: POINT AGASSIZ
CONNECTION
PRE & POST HAUL MAINTENANCE
MP DESCRIPTION OF WORK
0.0
BEGIN ROAD WORK AT JUNCTION WITH NFS
ROAD 6256.
BEGIN ROAD BLADING COMPACTION METHOD B.
BEGIN BRUSHING METHOD A.
BEGIN MAINTENANCE FOR PROJECT USE.
1.38
END ROAD WORK AT THE END OF UNIT 14-1.
END ROAD BLADING COMPACTION METHOD B.
END BRUSHING METHOD A.
END MAINTENANCE FOR PROJECT USE.
NFS ROAD 6100 : MUD
PRE & POST HAUL MAINTENANCE
MP DESCRIPTION OF WORK
0.0
BEGIN ROAD WORK AT JUNCTION WITH NFS
ROAD 6252.
BEGIN ROAD BLADING COMPACTION METHOD B.
BEGIN BRUSHING METHOD A.
BEGIN MAINTENANCE FOR PROJECT USE.
0.95
END ROAD WORK AT THE END OF UNIT 18-3.
END ROAD BLADING COMPACTION METHOD B.
END BRUSHING METHOD A.
END MAINTENANCE FOR PROJECT USE.
ROAD 6252_1.38R
TEMPORARY ROAD RECONSTRUCTION
MP DESCRIPTION OF WORK
0.0
BEGIN ROAD WORK AT JUNCTION WITH NFS ROAD 6252.
BEGIN ROAD RECONDITIONING, COMPACTION PLACEMENT METHOD 2.
BEGIN SPOT SURFACING AS DESIGNATED BY ENGINEER USING 150
CUBIC YARDS OF UNCLASSIFIED BORROW, COMPACTION PLACEMENT
METHOD 2, INCLUDES HAUL.
BEGIN SEEDING, DRY METHOD (WITHOUT MULCH).
0.53
END ROAD RECONDITIONING, COMPACTION PLACEMENT METHOD 2.
END SPOT SURFACING AS DESIGNATED BY ENGINEER USING 150
CUBIC YARDS OF UNCLASSIFIED BORROW, COMPACTION PLACEMENT
METHOD 2, INCLUDES HAUL.
END SEEDING, DRY METHOD (WITHOUT MULCH).
END ROAD WORK ABOUT MIDWAY INTO UNIT 14-5.
ROAD 6252_1.20R
TEMPORARY ROAD RECONSTRUCTION
MP DESCRIPTION OF WORK
0.0
BEGIN ROAD WORK AT JUNCTION WITH NFS ROAD 6252.
BEGIN ROAD RECONDITIONING, COMPACTION PLACEMENT METHOD 2.
BEGIN SPOT SURFACING AS DESIGNATED BY ENGINEER USING 150
CUBIC YARDS OF UNCLASSIFIED BORROW, COMPACTION PLACEMENT
METHOD 2, INCLUDES HAUL.
BEGIN SEEDING, DRY METHOD (WITHOUT MULCH).
0.55
END ROAD RECONDITIONING, COMPACTION PLACEMENT METHOD 2.
END SPOT SURFACING AS DESIGNATED BY ENGINEER USING 150
CUBIC YARDS OF UNCLASSIFIED BORROW, COMPACTION PLACEMENT
METHOD 2, INCLUDES HAUL.
END SEEDING, DRY METHOD (WITHOUT MULCH).
END ROAD WORK ABOUT MIDWAY INTO UNIT 14-6.
ROAD 6100_0.67L
TEMPORARY ROAD RECONSTRUCTION
MP DESCRIPTION OF WORK
0.0
BEGIN ROAD WORK AT JUNCTION WITH NFS ROAD 6100.
BEGIN ROAD RECONDITIONING, COMPACTION PLACEMENT METHOD 2.
BEGIN SPOT SURFACING AS DESIGNATED BY ENGINEER USING 200 CUBIC
YARDS OF UNCLASSIFIED BORROW, COMPACTION PLACEMENT METHOD 2,
INCLUDES HAUL.
BEGIN SEEDING, DRY METHOD (WITHOUT MULCH).
0.42
INSTALL NEW LOG CULVERT - BRIDGE STRINGERS NOT ADJACENT TO SITE.
REMOVAL OF 100' OF TEMPORARY ROAD PRISM TO RESTORE FISH
HABITAT, INCLUDES REMOVAL OF THE LOG CULVERT & SIDECAST OF
EXCESS MATERIAL, APPROXIMATELY 100 CUBIC YARDS
0.55
END ROAD RECONDITIONING, COMPACTION PLACEMENT METHOD 2.
END SPOT SURFACING AS DESIGNATED BY ENGINEER USING 200 CUBIC
YARDS OF UNCLASSIFIED BORROW, COMPACTION PLACEMENT METHOD 2,
INCLUDES HAUL.
END SEEDING, DRY METHOD (WITHOUT MULCH).
END ROAD WORK ABOUT MIDWAY INTO UNIT 18-3.
NFS ROAD 6256: NORTH BLIND RIVER
ROAD IMPROVEMENTS
MP DESCRIPTION OF WORK
5.52
CLEAN CULVERT CATCH BASIN, 60" DIAMTER CULVERT.
INSTALL CONTRACTOR FURNISHED CULVERT BEAVER
DAM ANALOG.
NFS ROAD 6252: POINT AGASSIZ CONNECTION
ROAD IMPROVEMENTS
MP DESCRIPTION OF WORK
3.149
4.249
BEGIN ROAD WORK AT ROAD 6252 T-INTERSECTION.
BEGIN ROAD RECONDITIONING, COMPACTION
PLACEMENT METHOD 2 AT MP 3.149.
END ROAD RECONDITIONING, COMPACTION PLACEMENT
METHOD 2 AT MP 4.249.
INSTALL 2 24" POLY PIPES, BELL/SPIGOT DOUBLE WALL, 2
3" X 12" CORRUGATIONS,CONTRACTOR FURNISHED AT MPS
3.870 & 4.169.
PLACE 100 CUBIC YARDS OF RIPRAP CLASS 4 TO
REINFORCE FAILING ROAD FILL, CONTRACTOR
FURNISHED AS DESIGNATED BY THE COR.
RESURFACE THE ROAD USING 900 CUBIC YARDS OF
CONTRACTOR FURNISHED CRUSHED AGGREGATE,
COMPACTION PLACEMENT METHOD 2, AS DESIGNATED
BY THE COR.
REMOVE APPROXIMATELY 20 EXISTING TREES, INCLUDES
FELLING, DELIMBING, BUCKING & END HAUL<=2 MILES TO
A LOCATION DESIGNATED BY THE COR.
END ROAD WORK AT POINT AGASSIZ PARKING AREA.
4.249
REGRADE & RESURFACE THE EXISTING POINT AGASSIZ
PARKING AREA USING 100 CUBIC YARDS OF
CONTRACTOR FURNISHED CRUSHED AGGREGATE,
COMPACTION PLACEMENT METHOD 2.
NFS ROAD 6252: POINT AGASSIZ CONNECTION
ROAD IMPROVEMENTS
OPTION ITEM 1
MP DESCRIPTION OF WORK
4.249
REMOVE & EXCESS 5 ABANDONED VEHICLES FROM THE
POINT AGASSIZ PARKING AREA (INCLUDES CLEAN-UP OF
HAZARDOUS MATERIALS). VEHICLES SHALL BE DISPOSED
OFF THOMAS BAY. ALTERNATIVE DISPOSAL LOCATIONS IN
THOMAS BAY SHALL BE OFF USFS LAND & NEED TO BE
APPROVED BY THE COR PRIOR TO USE.
NFS ROAD 6252: POINT AGASSIZ CONNECTION
ROAD IMPROVEMENTS
OPTION ITEM 2
MP DESCRIPTION OF WORK
4.249
RESURFACE THE ROAD USING 900 CUBIC YARDS OF CONTRACTOR
FURNISHED CRUSHED AGGREGATE, COMPACTION PLACEMENT
METHOD 2, AS DESIGNATED BY THE COR.
ABBREVIATIONS:
· LTF = LOG TRANSFER FACILITY
· MP = MILE POST
· NFS = NATIONAL FOREST SYSTEM
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
Existing Streambed
Notes:
1. All tree diameters are small end diameters
2. All alternative trees must be approved by the CO, before felling down.
3. Haul all excess timber to a location identified by the Engineer. Deck logs so that they're piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, & will not roll.
SECTION VIEW
NOT TO SCALE
2 Sill Logs 20"-24" Diameter 36' in Length, Typ.
0%-2% Slope
Polypropylene Fabric Blanket, Type II-A Separation Geotextile or Similar Per Section 714 FP-14 27 Deck Logs 16"-18" Diameter 12' in Length, Typ.
3%3% 1.5H 1V
14'-0" Road Width or Match Existing
2.0' Min. Height of Cover
36'-0" Sill Log Length, Typ.
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
LOG CULVERT DETAILS
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
06 13
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
1. CULVERT LENGTHS, AS SHOWN ON THE PLANS, ARE APPROXIMATE
AND ARE SUBJECT TO REVISION BY THE ENGINEER.
2. MINIMUM LOG CULVERT SPAN SHALL BE GREATER THAN OUTSIDE
BANKFULL WIDTH. SPAN MEASURED FROM THE INSIDE FACE
3. RIP RAP, WHEN DESIGNATED ON THE PLANS, SHALL EXTEND A
MINIMUM OF ONE FOOT BEYOND THE SIDES OF THE CULVERT.
CULVERTS SHALL BE CONSTRUCTED IN ACCORDANCE WITH LINES,
GRADES, AND DIMENSIONS SHOWN ON DRAWINGS AND/OR AS
STAKED ON THE GROUND.
GENERAL NOTES
4. WHEN REBAR IS USED TO CONNECT STRINGERS TO SILL LOG,
A CABLE WRAP AT MIDSPAN WILL BE USED ALONG THE FULL
LENGTH OF THE LOG CULVERT.
5. CABLE WRAPS SHALL BE STAPLED ON EACH STRINGER.
6. DO NOT PLACE EXCESS AND/OR UNSUITABLE MATERIAL EXCAVATED
DURING CULVERT CONSTRUCTION ON THE SLOPES ADJACENT TO
THE STREAM OR IN THE STREAM CHANNEL.
MAXIMUM FILL DEPTHS FOR ROADWAY MATERIAL OVER LOG CULVERT (IN)
MINIMUM
STRINGER Ø
(IN.)
SPAN LENGTH (FT)
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
240 240 240 240 240 240 240 240 240 240 230 196 168 144240
240 240 240 240 240 240 240 240 240 208 172 144 122 102240
240 240 240 240 240 240 240 226 182 146 120 96 78 62240
240 240 240 240 240 240 196 152 116 88 68 50 36 24240
240 240 240 240 240 224 114 80 54 32160
240 240 240 199 146 116 36 0 070
240 150 77 38 18 0 0 0 0 00 0 0 00
28 240 240 240 240 240 240 240 240 240 240 240 240 214 186240
30 240 240 240 240 240 240 240 240 240 240 240 240 240 240240
32 240 240 240 240 240 240 240 240 240 240 240 240 227 197240
0 0 0 00
0 000 TO THE INSIDE FACE OF EACH SILL LOG.
NOT TO SCALENOT TO SCALE
NOT TO SCALE NOT TO SCALE
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
LOG CULVERT TYPICAL
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
07 13
AutoCAD SHX Text
MIN.
AutoCAD SHX Text
EMBANKMENT
AutoCAD SHX Text
MIDSPAN CABLE WRAP, " MIN. CABLE38" MIN. CABLE
AutoCAD SHX Text
24"MIN. SILL LOGS
AutoCAD SHX Text
SEE NOTE 2
AutoCAD SHX Text
EXISTING GROUND
AutoCAD SHX Text
#4 REBAR, 18"-24" LONG (DEPENDING ON STRINGER )OR FIGURE-EIGHT CABLE WRAP
AutoCAD SHX Text POLYPROPYLENE FABRIC BLANKET, TYPE II-A SEPARATION GEOTEXTILE OR SIMILAR PER SECTION 714 FP-14
AutoCAD SHX Text
16" MIN. DECK LOGS
AutoCAD SHX Text
TRAVELED WAY
AutoCAD SHX Text
TRAVELED WAY
AutoCAD SHX Text
DOWNHILL LOG TIED INTO BANK TO DIVERT WATER INTO CULVERT
AutoCAD SHX Text
ROAD SURFACE
AutoCAD SHX Text
CULVERT SLOPE 2% GREATER THAN SLOPE OF ROAD. MAXIMUM OF 6%
AutoCAD SHX Text
MIN.
AutoCAD SHX Text
MIN.
AutoCAD SHX Text
EXISTING GROUND
AutoCAD SHX Text
SILL LOG
AutoCAD SHX Text
TRAVELED WAY
AutoCAD SHX Text
POLYPROPYLENE FABRIC BLANKET
AutoCAD SHX Text
NOTCH SILL LOG 4" MIN. AT ENDS TO FIT OUTSIDE DECKING LOGS
AutoCAD SHX Text
6" MIN. DECKING LOGS,CABLE-WRAPPED AND CLAMPED
AutoCAD SHX Text FIGURE-EIGHT WRAP DECKING LOGS AT ENDS OF CULVERT W/ " MIN. CABLE TO AT LEAST 38" MIN. CABLE TO AT LEAST A POINT VERTICALLY BELOW THE SHOULDER OF THE ROADWAY
AutoCAD SHX Text
16" MIN. LOG
AutoCAD SHX Text
0-2% SLOPE
AutoCAD SHX Text
EXISTING STREAMBED,TYP.
AutoCAD SHX Text
2' MIN. SILL LOG
AutoCAD SHX Text
CONSTRUCT SLOPE AS STAKED
AutoCAD SHX Text
OUTLET AT STAKED ELEVATION
AutoCAD SHX Text
DECK LOGS TO EXTEND 12"MIN. BEYOND END OF SILL LOGS, TYP.
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
DITCH SECTION AA
Not to Scale
CULVERT
AREA TO BE CLEANED
10'
10'
CULVERT
COMMON FILL
DITCH PLUG CATCH BASIN
AREA TO BE
CLEANED
FORESLOPE
EDGE OF ROAD
PATH VIEW ALONG DITCH
Not to Scale
DITCH CROSS SECTION VIEW
Not to Scale
FLOWLINE
MATERIAL TO BE REMOVED
FORESLOPE
CULVERT
ORIGINAL BACKSLOPE
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
BEAVER DAM ANALOG &
CULVERT CATH BASIN
TYPICALS
04/2025
F.BECERRA
F.BECERRA
J.ANDERSON
08 13
BEAVER DAM ANALOGUE DETAILS
FLO
W
FLOW
3'
APPROX
BEAVER DAM ANALOGUE NOTES:
1. CONSTRUCT BEAVER DAM ANALOGUE THE FULL WIDTH OF THE
STREAM CHANNEL WITH AT LEAST TWO POLES EXTENDING UP ONTO
THE STREAM BANKS.
2. CONSTRUCT WITHIN 12 FEET OF THE INLET OF THE NEW STRUCTURE.
3. INTERWEAVE ALDER BRANCHES BETWEEN TIMBER POLES AS SHOWN
IN THE PICTURE. IF ALDER IS NOT AVAILABLE NEAR THE CULVERT, IT
CAN BE SUBSTITUTED WITH OTHER SIMILAR BRUSH OR TREE
SPECIES.
4.CONTRACTOR SHALL PROVIDE 4” DIAMETER ROUND UNTREATED
TIMBER POLES.
ELEVATIONS TO
BE DETERMINED
IN THE FIELD
NOTE: EXTEND POLES UP ONTO
EXISTING STREAM BANKS
4" DIA. X 6' LONG
UNTREATED TIMBER
POLES, TYP.
PLAN
NOT TO SCALE
*EXAMPLE PHOTO SHOWING POLE PLACEMENT.
ELEVATION VIEW
NOT TO SCALE
TYPICAL SECTION
NOT TO SCALE
6'
AP
PR
O
X
CULVERT CATCH BASIN DETAILS
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
TYPICAL BRUSHING
04/2025
R.SCHMOHL
R.SCHMOHL
F.BECERRA
09 13
MADE ALL TEXT MTEXT 04/2025
GENERAL NOTES:
1. Cut all brush within treatment area which is less than or equal to 6 inches in diameter measured 6 inches above the ground.
2. For Method A, cut brush back 5 feet slope distance beyond bottom of ditch or 15 feet slope distance from road shoulder, whichever is less, & 10 feet slope distance beyond the edge of the road shoulder on the fill slope.
3. For Method B, cuall all brush within 5 feet of culvert inlets
4. Cut brush to provide overhead clearance of 14 feet on the road surface.
5. Remove debris from the road surface, ditches & cut slope above the road. Scatter to fill slopes below the road, no debris piles allowed at culvert outlets.
6. Clear ditches of woody debris. Clean culvert inlets & outlets of debris a minimum of 2 culvert diameters.
7. Cut brush to provide sufficient sit distance on the inside of sharp curves to eliminate blind corners and intersections.
DITCH LINE
10'5'
5'
METHOD A TREATMENT AREA:
FROM 5' SLOPE DISTANCE BEYOND TOE OF DITCH
TO 10' SLOPE DISTANCE ON FILL SLOPE
CLEARING LIMITS METHOD A
CLEARING
HEIGHT
14 feet
ROADBED
SHOULDERS
CUT SLOPE
METHOD B TREATMENT AREA:
FROM TOE OF DITCH TO 5' SLOPE DISTANCE ON FILL SLOPE
CLEARING LIMITS METHOD B
DITCH LINE
CUT SLOPE
FILL SLOPE
FILL SLOPE
ROADBED
SHOULDERS
CLEARING
HEIGHT
14 feet
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
TYPICAL CULVERT INSTALLATION AT LIVE STREAMS
SELECT BACKFILL MATERIAL AND DEPTH FOR
BEDDING REFER TO FP-14 SECTIONS 602 AND 209.09
2 PIPE Ø
SUBGRADE
GRADE OF CMP SHALL BE SAME AS EXISTING
STREAM CHANNEL UNLESS OTHERWISE SHOWN
ON DRAWINGS
EXISTING
STREAMBED
1' MIN
4" MIN
1.25
RIP RAP
SEE NOTE 7
TYPICAL CULVERT INSTALLATION FOR DITCH RELIEF
SELECT BACKFILL MATERIAL AND DEPTH FOR
BEDDING REFER TO FP-14 SECTIONS 602 AND 209.09
2 PIPE Ø
SUBGRADE
GRADE OF CMP SHALL BE SAME AS EXISTING
STREAM CHANNEL UNLESS OTHERWISE SHOWN
ON DRAWINGS
1' MIN
1.25
EXISTING GROUND
VARIABLE SLOPE
2' MIN DEPTH
MINIMUM WIDTH OF
APRON IS 2 PIPE Ø
NOTES
1. PLACE CULVERT IN ALIGNMENT WITH THE NATURAL
STREAM CHANNEL. WHERE NO CHANNEL IS
APPARENT, INSTALL CULVERTS AT SKEWS SHOWN
ON THE DRAWINGS OR AS DIRECTED BY THE CO.
2. MINIMUM CULVERT GRADES SHALL BE 5% OR 12 OF
THE TRIBUTARY DITCH GRADE.
3. CAMBER WILL DEPEND ON SITE CONDITIONS.
MAXIMUM CAMBER IS 2% (STEEL OR ALUMINUM
CULVERTS) OR 1% (POLYETHYLENE CULVERTS) OF
CULVERT LENGTH BY NO MORE THAN 2.5" AT
CENTER.
4. CATCH BASIN CONSTRUCTION IS REQUIRED WHEN
SHOWN ON THE DRAWINGS AND AT ALL
INSTALLATIONS WHERE THE INLET IS LOWER THAN
NATURAL GROUND.
5. CULVERT INLETS AND OUTLETS SHALL EXTEND 24"
BEYOND THE TOE OF THE FILL UNLESS AGREED TO
BY THE CO.
6. MINIMUM COVER OVER CULVERTS UNLESS
OTHERWISE SHOWN ON THE DRAWINGS IS 12".
7. PLACE RIPRAP AT SITES SHOWN ON THE DRAWINGS
OR AS DIRECTED BY THE CO. MINIMUM WIDTH OF
RIPRAP IS 1.5 PIPE Ø. MINIMUM RIPRAP SIZE IS
CLASS 4.
8. THE CONTRACTOR SHALL PROVIDE THE CO A LIST
OF AS-SLOPE STAKED CULVERT LENGTHS AND
CULVERT SKEW DIAGRAM
BEGIN PROJECT ℄ END PROJECT
120°
TYPICAL CATCH BASIN WITH DITCH BLOCK
CONSTRUCT DITCH BLOCK OF ROCK
WITH 12" MAX AVERAGE DIAMETER.
HEIGHT OF DITCH BLOCK SHALL BE NO
GREATER THAN THE TOP OF THE CULVERT
25' TAPER EACH SIDE
ALUMINUM & STEEL CULVERT CORRUGATIONS
SHALL CONFORM TO THE FOLLOWING:
PIPE SIZE MINIMUM (IN./GAGE) CORRUGATIONS
(IN) STEEL ALUMINUM
18 TO 36 0.064"/16 0.060" / 16 2 23" X 0.5"
48 0.079" / 14 0.075" / 14 2 23" X 0.5"
60 0.079" / 14 0.075" / 14 5" X 1"
72 0.109" / 12 0.105" / 12 5" X 1"
POLYETHYLENE (PE) CULVERT
PER ASTM D 3350
CORRUGATED
PIPE SIZE MIN COVER CELL CLASS CELL CLASS
Ø NO. 315412C NO. 324420C
MAX FILL HEIGHT IN FEET
18" 12" 12' 10'
24" 12" 12' 10'
30" 12" 12' 10'
36" 12" 11' 10'
POLYETHYLENE (PE) CULVERT
PER ASTM D 3350
RIBBED
PIPE SIZE MIN COVER CELL CLASS CELL CLASS
Ø NO. 334433C NO. 335434C
MAX FILL HEIGHT IN FEET
18" 12" 18' 24'
24" 12" 22' 28'
30" 12" 22' 28'
36" 12" 25' 31'
40" 12" 21' 27'
48" 12" 21' 26'
DIRECTION
OF FLOW
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
TYPICAL CULVERT
DETAILS
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
10 13
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
50' TYP
10' TYP
STRAW BALES, CENTERED IN DITCH LINE
SILT FENCE TYP
DITCH FLOW
PLACE SILT FENCE ALONG WATERWAY
TERMINATE AT END OF CUT TYP
SILT FENCE, SECURE AROUND INLET
TO KEEP DEBRIS OUT OF STREAM
SILT FENCE TYP 50' TYP
FILL SLOPE
EDGE OF ROAD TYP
CENTERLINE OF ROAD CULVERT
TYPICAL SEDIMENT CONTROL AT CULVERTS
EDGE OF STREAM TYP
DIRECTION
OF FLOW
NOTES
1. SILT FENCE CONSISTS OF WOVEN WIRE FENCE FABRIC
WITH A MPS.
2. MAXIMUM 6" MESH, MINIMUM HEIGHT 30".
3. THE CO MAY REQUIRE ADJUSTMENTS TO ACTUAL
LENGTHS OR LOCATIONS TO FIT FIELD CONDITIONS.
4. INSPECT SILT FENCES AFTER EACH RUNOFF EVENT
AND IMMEDIATELY REPAIR ALL EROSION ALONG EDGES
AND BOTTOM.
5. ACCUMULATED DEPTH OF SEDIMENT SHALL NOT
EXCEED ONE HALF OF THE ORIGINAL HEIGHT OF THE
SILT FENCE.
6. IN AREAS DESIGNATED FOR BRUSH BARRIERS, LIMIT
CLEARING TO TREES, SHRUBS AND PLANTS LESS THAN
4" IN DIAMETER. GRUBBING SHALL NOT BE PERFORMED
IN THOSE AREAS.
7. BRUSH BARRIER SHALL BE CONSTRUCTED
APPROXIMATELY PARALLEL TO ORIGINAL GROUND
CONTOUR. USE WELL-INTERMINGLED MASS OF BRUSH,
TRESS, TRIMMINGS ETC. BARRIER SHALL BE POROUS
ENOUGH TO ALLOW WATER TO FILTER THROUGH.
SECURE BY PLACING MATERIAL (TREES, LOGS ETC) ON
TOP OF AND THROUGHOUT THE BRUSH.
8. ADJOIN BRUSH BARRIER WITH ROADWAY SLOPE ON
THE LOW END AS NEEDED TO CONTAIN SEDIMENTS.
POST
WOVEN WIRE FENCE FABRIC
GEOTEXTILE FABRIC FILTER CLOTH
SECURE TO TOP OF POSTS
DITCH FLOW
2.5'
4'
SECURE EACH BALE WITH
AT LEAST 2 STAKES BURIED
AT MIN 12" DEPTH
BOTTOM OF SILT FENCE BURIED
IN TRENCH MIN 6" DEPTH
TYPICAL SILT FENCE INSTALLATION FOR DITCHES
APPROX 6'
TYPICAL
APPROX 6'
CENTER ON DITCH
135°
135°
STRAW BALES (2)
DITCH FLOW
GEOTEXTILE
ROAD FILL SLOPE
EXISTING
GROUND
GEOTEXTILE FABRIC
BURY BOTTOM EDGE ± 6"
VARIES 5' TO 10'
VARIES 3' TO 5'
BRUSH BARRIER
SEE NOTES
TYPICAL BRUSH BARRIER
APPROX 10' TYP
GEOTEXTILEWOVEN WIRE FABRIC POST
TYPICAL SEDIMENT CONTROL AT CULVERTS
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
TYPICAL EROSION
CONTROL DEVICES
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
11 13
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
2%2%
3-5%
DESIGN ROADWAY WIDTH
EXISTING GROUND
RECONDITIONED SUBGRADE
COMPACTED DEPTH AGGREGATE LIFT
EXISTING
DESIGN ROADWAY WIDTH
EXISTING GROUND
RECONDITIONED SUBGRADE
COMPACTED DEPTH AGGREGATE LIFT
TYPICAL OVERLAY SECTION - CROWNED
OUTSLOPED SECTION
INSLOPED SECTION
SEE NOTE
NOTE: IN THOSE AREAS WHERE THE EXISTING
ROAD, AFTER RECONDITIONING IS WIDER THAN
THE DESIGNED WIDTH OF AGGREGATE, CENTER
THE LIFT OF AGGREGATE ON ROAD SURFACE
AND FEATHER TO EXISTING SHOULDERS. WHEN
PLACING THE ADDITIONAL XXXX WIDTH OF
AGGREGATE IN TURNOUT AREAS AND SECTIONS
REQUIRING CURVE WIDENING, PLACE ADJACENT
TO CENTERLINE LIFT AND COMPACT TOGETHER.
NOTE: OUTSLOPED ROADS SHOULD BE USED
WHEN ROAD GRADES ARE GENTLE TO MODERATE
(0% TO 8%) AND WHERE CUTSLOPES ARE DRY.
OUTSLOPED ROADS SHOULD BE CONSTRUCTED
WITH ROLLING DIPS FOR DRAINAGE. THERE
SHOULD BE NO DITCH ON THE INBOARD SIDE OF
THE OUTSLOPED ROAD.
NOTE: INSLOPED ROADS SHOULD BE USED WHEN
ROAD GRADES ARE MODERATE TO STEEP (6%
AND UP) AND WHERE TERRAIN MAY BE STEEP OR
SLIPPERY. INSLOPED ROADS ARE ALSO IDEAL
FOR HIGHLY ERODIBLE AREAS. EXTRA
ATTENTION SHOULD BE PAID TO ESTABLISHING
DITCHES AND DRAINAGE FOR INSLOPED ROADS.
3-5%
DESIGN ROADWAY WIDTH
EXISTING GROUND
RECONDITIONED SUBGRADE
COMPACTED DEPTH AGGREGATE LIFT
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 5/2
5 1 0:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
ROAD OVERLAY TYPICAL
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
12 13
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
NOTES
1. ALL PITS AND QUARRIES SHALL BE APPROVED IN WRITING BY THE CO PRIOR TO
EXPLORATION, CLEARING OR DEVELOPMENT.
2. REMOVE ALL OVERBURDEN TO SOLID ROCK FOR A MINIMUM DISTANCE OF 15' FROM
THE WORKING FACE.
3. SLOPE THE CUT BANK OF THE OVERBURDEN TO THE NATURAL ANGLE OF REPOSE BUT
IN NO CASE STEEPER THAN 1:1.
4. WITHIN THE CLEARING LIMITS:
4.1. MAXIMUM STUMP HEIGHT SHALL BE IN ACCORDANCE WITH SPECIFICATIONS.
4.2. STABLE TREES UP TO 6" (DBH) NEED NOT BE CUT IF THEY WILL NOT INTERFERE
WITH BACK SLOPE STABILITY.
4.3. STUMPS AND BRUSH MAY BE LEFT IN PLACE, EXCEPT THAT ALL STUMPS THAT
PROTRUDE FROM EXCAVATED BANKS OR THAT HAVE THE POTENTIAL TO BECOME
DISLODGED AT ANY LATER DATE SHALL BE REMOVED.
5. DISPOSE OF OR STOCKPILE FOR LATER USE ALL OVERBURDEN, CLEARING,
MERCHANTABLE TIMBER AND GRUBBING DEBRIS AS SHOWN ON THE QUARRY
DEVELOPMENT PLAN.
6. FELL ALL DEAD TREES AND SNAGS WHICH ARE SUFFICIENTLY TALL TO REACH THE
WORK AREA.
7. LEAVE THE PIT/QUARRY IN A NEAT, ORDERLY AND WELL-DRAINED CONDITION.
REMOVE ALL OVERHANGS AND LOOSE ROCK.
8. AFTER EXCAVATION IS COMPLETE CLEAN THE AREA AND LEAVE AS SHOWN ON THE
QUARRY DEVELOPMENT PLAN. TREAT ANY ACCESS ROAD AS SHOWN ON THE QUARRY
DEVELOPMENT PLAN.
9. TEST SHOTS OF 1300 TO 2600 CY ARE REQUIRED AT ALL QUARRY SITES IF DESCRIBED
IN THE SPECIFICATIONS.
10. LEAVE NO MORE THAN 5% BY VOLUME OF OVERSIZE MATERIAL IN THE QUARRY.
BREAK DOWN ANY MATERIAL OVER THIS VOLUME AND USE AS SPECIFIED IN SECTIONS
651.
11. PROVISIONS FOR FUTURE QUARRY DEVELOPMENT ACCESS WILL BE PROVIDED,
UNLESS THIS REQUIREMENT IS WAVED BY THE CO.
12. INSTALL AND MAINTAIN A COMMERCIALLY AVAILABLE RAIN GAUGE MEASURING IN
UNITS OF INCHES AND FRACTIONS OF INCHES IN ACCORDANCE WITH SECTION 205.08.
13. HAUL WILL NOT BE ALLOWED BEYOND DESIGNATED SOURCES UNLESS OTHERWISE
SHOWN ON THE DRAWINGS OR AGREED TO BY THE CO.
14. SEED AND FERTILIZE ALL DISTURBED AREAS SUCH AS OVERBURDEN PILES AND BENCH
SURFACES IN ACCORDANCE WITH SECTION 625.
SAMPLE QUARRY DEVELOPMENT PLAN SAMPLE QUARRY BLASTING PLAN
QUARRY DEVELOPMENT PLAN QUARRY BLASTING PLAN
QUARRY IS LOCATED RIGHT OF STA XX+XX ON ROAD NO. XXXX
ESTIMATE OF VOLUME = XXXX CY
CMP ROAD NO. XXXX
ACCESS ROAD
STREAM
THIS AREA TO BE CLEARED
ONLY IF OVERBURDEN CANNOT
BE CONTAINED BETWEEN THE
ACCESS ROAD AND ROAD NO.
XXXX
STA XX + XX
TIMBER FROM QUARRY SITE
DECKED IN MUSKEG
CLEARING LIMIT FLAGGED
OVERBURDEN
PLAN VIEW
APPROX
ELEV XXXX
CROSS SECTION VIEW
OBD
OBD
OBD
ELEV XXXX
15' MIN
40'
15' MIN
3% SLOPE
70%
ACCESS
ROAD
ROAD
XXXX
DEVELOPMENT PLAN
1. ALL MERCHANTABLE TIMBER WILL BE REMOVED FROM THE QUARRY SITE AND DECKED IN THE
MUSKEG LEFT OF XX+XX
2. OVERBURDEN WILL NOT BE PLACED IN THE SMALL STREAM BORDERING THE QUARRY.
3. DEVELOPMENT WILL COMPLY WITH THE GENERAL NOTES SHOWN ON THE PIT & QUARRY
DEVELOPMENT TYPICAL SHEET.
4. TEST SHOT OF APPROXIMATELY XXXX CY IS PLANNED.
REHABILITATION PLAN
1. THE ACCESS ROAD WILL BE OBLITERATED BY CUTTING A DITCH AT THE JUNCTION OF THE
ACCESS ROAD WITH ROAD NO. XXXX AND BY ROUGHING UP THE ACCESS ROAD SURFACE.
2. ALL OVERSIZE ROCK WILL BE PLACED AGAINST THE SIDES OF THE QUARRY NEXT TO THE
BACKWALL BENCH.
3. A MINIMUM OF 12" OF OVERBURDEN WILL BE EVENLY SPREAD OVER THE QUARRY FLOOR.
4. ALL DISTURBED AREAS, SUCH AS OVERBURDEN PILES, BENCH SURFACES, AND ACCESS ROAD
SURFACES WILL BE SEEDED AND FERTILIZED IN ACCORDANCE WITH SPECIFICATIONS.
5. PROVISIONS FOR FUTURE QUARRY ACCESS WILL BE PROVIDED UNLESS THIS REQUIREMENT IS
WAIVED BY THE COR.
CONTRACTOR DATE COR DATE DISTRICT RANGER DATE
THIS PLAN IS FOR THE FIRST TEST SHOT IN THE QUARRY
RIGHT OF STA. XX+XX ON ROAD NO. XXXX
STA XX+XX ROAD NO. XXXX
SECOND
PRODUCTION
SHOT
XXXX CY
FIRST
PRODUCTION
SHOT
XXXX CY
EXISTING
QUARRY
FLOOR
ROCK FACE
250m s
200m s
175m s
150m s
125m s
150m s
175m s
200m s
250m s
283m s
233m s
208m s
183m s
158m s
183m s
208m s
233m s
283m s
314m s
266m s
241m s
216m s
101m s
216m s
241m s
266m s
314m s
349m s
289m s
274m s
249m s
224m s
249m s
274m s
289m s
349m s
382m s
332m s
307m s
282m s
257m s
282m s
307m s
332m s
382m s
SEQUENTIAL TIMER
FIRING SEQUENCE - SEQUENCE OF
DELAYS IS THE SAME FOR ALL 5 ROWS
ACTUAL MILLISECOND DELAY USING
SEQUENTIAL TIMER
BOREHOLE SIZE = XX"
HOLE DEPTH = XX' TO XX'
SPACING XX'
STEMMING = XX'
TYPE OF EXPLOSIVES = XX
DENSITY = XX LB/CY
TYPE OF PRIMER & LOCATION IN HOLE = XXXX
TOTAL NUMBER OF HOLES IN SHOT = XX
TOTAL POUNDS OF POWDER IN SHOT
(INCLUDING PRIMERS) = XXXX LB
NUMBER OF CY IN SHOT = XXXX CY
MAXIMUM POUNDS OF POWDER
PER 8ms DELAY = XXXX LBS
POWDER FACTOR = XX LB/CY
NAME OF BLASTER IN CHARGE = (FULL NAME)
PLANNED SHOT DATE/TIME = XXXXX AT XXXX AM/PM
5' STEMMING
3.5" DIA HOLE
TYPICAL LOADED HOLE
EXAMPLE:
'HI DRIVE' PRIMER WITH 125ms TO 205ms
DU PONT ELECTRIC BLASTING CAP
LOCATED AT BOTTOM OF HOLE WITH ONE
3" X 6" STICK OF TOVEX USED FOR CUSHION.
EXAMPLE HAUL DIAGRAM
E.O.P.
MP XX.XX
E.O.P.
MP XX.XX
MP XX.XX
MP XX.XX
ROAD XXXX ROAD XXXX
ROAD XXXX
TO XX M
.A.F
DESIGNATED
ROCK SOURCE
DIRECTION
OF HAUL
40' MAX
15' MIN 40' MAX
15' MIN
15' MIN
OVERBURDEN
CLEARING LIMITS
DRAWN
DESIGNER
STAMPS, LOGOS, AND SEALS
PROJECT NAME
DRAWING TITLE
CHECKED
ARCHIVE NO.DATE
PROJECT NO.
DRAWING SHEET NO.
DATENO.
REVISION / ISSUE
OFSHEET
United States Department of Agriculture Forest Service
4/2 3/2
5 0 6:
F
BE
CE
RR
AO
CH
OA
D :\M
Y
DO
CU
ME
NT
S\
NE
PA
\P
RD
_W
RG
\20
T
HO
MA
S
BA
Y
YG
E
A\
RO
AD
P
AC
KA
GE
\F
IN
AL
\T
HO
MA
S
BA
Y
YG
S
TE
W
AR
DS
HI
P
IR
SC
D
RA
W
IN
GS
.D
W G;
(R10)
ALASKA REGION
THOMAS BAY
YOUNG-GROWTH
STEWARDSHIP
IRSC
TONGASS NATIONAL
FOREST
PETERSBURG RANGER DISTRICT
TYPICAL PIT & QUARRY
DEVELOPMENT
04/2025
F.BECERRA
F.BECERRA
C.LAVOIE
13 13
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text R
AutoCAD SHX Text E
AutoCAD SHX Text S
AutoCAD SHX Text T
AutoCAD SHX Text S
AutoCAD SHX Text E
AutoCAD SHX Text R
AutoCAD SHX Text V
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text P
AutoCAD SHX Text A
AutoCAD SHX Text R
AutoCAD SHX Text T
AutoCAD SHX Text M
AutoCAD SHX Text E
AutoCAD SHX Text N
AutoCAD SHX Text T
AutoCAD SHX Text O
AutoCAD SHX Text F
AutoCAD SHX Text A
AutoCAD SHX Text G
AutoCAD SHX Text R
AutoCAD SHX Text I
AutoCAD SHX Text C
AutoCAD SHX Text U
AutoCAD SHX Text L
AutoCAD SHX Text T
AutoCAD SHX Text U
AutoCAD SHX Text R
Contract:
Thomas Bay Young
Growth Stewardship
IRSC
Road Number
6100_ 0.67L 6252
6252_ 1.20R
6252_ 1.38R 6256
Date Prepared: 4/23/2025 Reconstruction (R) or
Construction (c) R R R R R R
Revision Date
Parent 101 2016 X X X X X X
Supplemental 101.01, 101.03, &
101.04 2016 X X X X X X
Parent 102 2016 X X X X X X Parent 103 2016 X X X X X X Parent 104 2016 X X X X X X Parent 105 2016 X X X X X X
Supplemental 105.02(a), 105.02(c), &
105.02 (d) 2017 X X X X X X
Parent 106 2017 X X X X X X Parent 107 2017 X X X X X X Parent 108 2016 X X X X X X Parent 109 2016 X X X X X X Supplemental 109.01 & 109.02 2019 X X X X X X Parent 151 2020 X X X X X X Supplemental 151.01 & 151.06(b) 2020 X X X X X X Parent 152 2016 X X X X X X
Supplemental 152.04, 152.05, &
152.05 (e) 2016 X X X X X X
Parent 153 2016 X X X X X X
Supplemental 153.02, 153.03, &
153.07 2016 X X X X X X
Parent 155 2016 X X X X X X Parent 156 2019 X X X X X X
Supplemental
156.01, 156.02, 156.03, 156.04, 156.05, 155.06 & 156.07
2019 X X X X X X
Parent 157 2019 X X X X X X Supplemental 157.04 2019 X X X X X X Parent 201 2020 X
Specification
"X" denotes applicable specifications. All specifications not included in the specification listing, but included in the reference, are applicable.
Specification List for Roads
Growth Stewardship
IRSC
Road Number
6100_ 0.67L 6252
6252_ 1.20R
6252_ 1.38R 6256
Date Prepared: 4/23/2025 Reconstruction (R) or
Construction (c) R R R R R R
Revision DateSpecification
"X" denotes applicable specifications. All specifications not included in the specification listing, but included in the reference, are applicable.
Supplemental
201.01. 201.02, 201.03, 201.04, 201.05, 201.06, 201.07, 201.08, & 201.09
2020 X
Parent 202 2020 X
Supplemental
202.01. 202.02, 202.03, 202.04, 202.05, 202.06, 202.07, 202.08, 202.09, 202.10, & 202.11
2020 X
Parent 204 2017 X X X X
Supplemental
204.01. 204.02, 204.03, 204.04, 204.05, 204.06, 204.07, 204.08, 204.09, 204.10, 204.11, 204.12, 204.13, 204.14, 204.15, 204.16, & 204.17
2017 X X X X
Parent 208 2016 X Supplemental 208.07 2016 X Parent 209 2017 X
Supplemental 209.06, 209.09, &
209.10 2017 X
Parent 302 2020 X Supplemental 302.04 2020 X Parent 303 2016 X X X
Growth Stewardship
IRSC
Road Number
6100_ 0.67L 6252
6252_ 1.20R
6252_ 1.38R 6256
Date Prepared: 4/23/2025 Reconstruction (R) or
Construction (c) R R R R R R
Revision DateSpecification
"X" denotes applicable specifications. All specifications not included in the specification listing, but included in the reference, are applicable.
Supplemental
303.01, 303.02, 303.03, 303.04, 303.05, 303.06, 303.07, 303.08, 303.09, & 303.10
2016 X X X
Parent 572 2016 X
Supplemental
572.01, 572.02, 572.03, 572.04, 572.05, 572.06, 572.07, 572.08, & 572.09
2016 X
Parent 602 2020 X Supplemental 602.05 2020 X Parent 625 2022 X X X
Supplemental
625.01, 625.02, 625.03, 625.04, 625.05, 625.06, 625.07, 625.08, 625.09, 625.10, 625.11 & 625.12
2022 X X X
Parent 638 2025 X
Supplemental 638.01, 638.02, 638.03, 638.04, 638.05, & 638.06 2025 X
Parent 639 2025 X
Supplemental 639.01, 639.02, 639.03, 639.04, 639.05, & 639.06 2025 X
Parent 703 2019 X Supplemental 703.05 & 703.09 2019 X Parent 704 2017 X X
Supplemental 704.01, 704.02, 704.03, & 704.04 2017 X X
Parent 813 2020 X X X X
Growth Stewardship
IRSC
Road Number
6100_ 0.67L 6252
6252_ 1.20R
6252_ 1.38R 6256
Date Prepared: 4/23/2025 Reconstruction (R) or
Construction (c) R R R R R R
Revision DateSpecification
"X" denotes applicable specifications. All specifications not included in the specification listing, but included in the reference, are applicable.
Supplemental 813.01, 813.02, 813.03, 813.04, & 813.05
2020 X X X X
Parent 832 2020 X
Supplemental 832.01, 832.02, 832.03, 832.04, 832.05& 832.06
2020 X
Parent 834 2020 X X X
Supplemental 834.01, 834.02, 834.03, 834.04, & 834.05
2020 X X X
FOREST SERVICE
SUPPLEMENTAL SPECIFICATIONS
For
Thomas Bay Young-Growth Stewardship Integrated Resource Service Contract
(IRSC)
(PUBLIC WORKS)
U.S.D.A. FOREST SERVICE
TONGASS NATIONAL FOREST
Petersburg Supervisors Office 123 Scow Bay Loop Road
Petersburg, AK 99901
April 2025
Table of Contents Preface
101 - Terms¸ Format¸ and Definitions
102 - Bid¸ Award¸ and Execution of Contract
103 - Scope of Work
104 - Control of Work
105 - Control of Material
106 - Acceptance of Work
107 - Legal Relations and Responsibility to the Public
108 - Prosecution and Progress
109 - Measurement and Payment
151 - Mobilization
152 - Construction Survey and Staking
153 - Contractor Quality Control
155 - Schedules for Construction Contracts
156 - Public Traffic
157 - Soil Erosion and Sediment Control
201 - Clearing and Grubbing
202 - Additional Clearing and Grubbing
204 - Excavation and Embankment
208 - Structure Excavation and Backfill for Selected Major Structures
209 - Structure Excavation and Backfill
302 - Minor Crushed Aggregate
303 – Road Reconditioning
572 – Log Stringer Bridges, Culverts, & Bulkheads
625 - Turf Establishment
638 - Abandoned Vehicle Removal
639 - Beaver Deceiver…
This is the start of the file's text. The full file is on GovTribe.