OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

12344V18R0002

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

07/17/2018

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

Mt. Hood National Forest 16400 Champion Way Sandy, Oregon 97055

Mt. Hood National Forest Attention: Leslie Solberg 16400 Champion Way Sandy, Oregon 97055

9. FOR INFORMATION

CALL:

A. NAME

Leslie Solberg, lsolberg@fs.fed.us

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) 503-668-1667

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

In accordance to FAR 36.204(Price Range): The Government's estimate is: between $500,000 and $1,000,000 with each FSR range being:

FSR 44-MP 2.49 between $100,00 and $150,000 FSR 44-MP 6.80 between $50,000 and $100,000 FSR 32-MP 0.35 between $50,000 and $100,000 FSR 70-MP 3.30 between $200,000 and $300,000

Total Small Business Set-Aside, NAICS Code: 237310, Contractor must be registered in SAM

This project, solicitation and resultant contract will include 2 schedules as follows:

Chatt-Oconee ERFO Reconstruction: SCHEDULE A (FSR 44-MP 2.49 & FSR 44– MP 6.80)

SCHEDULE B (FSR 32C-MP 0.35 & FSR 70 - MP 3.30)

The intent is to award a single contract that includes both schedules.

Proposal Due Date: 08/16/2018 – Estimate Start Date: Schedule A & B is October 2018

11. The Contractor shall begin performance within 14 calendar days and complete it within 120 total calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable.

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Offers in original and 1 copies to perform the work required are due at the place specified in Item 8 by 4:00pm (PST) (hour) local time 08/16/2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 10 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated

Prescribed by GSA

FAR (48 CFR) 53.236-1(e) OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

DUNS:_____________ EMAIL_______________________

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE 20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE 30C. DATE 31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

Solicitation 12344V18R0002

PART 1, SECTION B – THE SCHEDULE

Schedule of Items--A

Project: Chatt-Oconee ERFO Reconstruction FSR 44-MP 2.49 Item No. Item Description Method of

Measure Est Qty

Pay Unit Unit Price Amount

15101 Mobilization L.S.Q. 1 L.S. XXXX $_____________

15713 Soil Erosion & Pollution Control, Type Silt Fence & Sediment Traps

L.S.Q. 1 L.S. XXXX $_____________

20701 Earthwork Geosynthetics, Type Separation Class 1 Woven, Type D

A.Q. 370 S.Y. _________ $_____________

21201 Linear Grading C.Q. 0.06 Mile _________ $_____________

25102 Placed Riprap, Class 3 A.Q. 346 Ton _________ $_____________

25105 Keyed Riprap, Class 3 A.Q. 193 Ton _________ $_____________

30202 4-Inch Minus Aggregate Base, Georgia DOT Gradation #4, Compaction Method 1

A.Q. 346 Ton _________ $_____________

30208 1-Inch Minus Surface Aggregate, Georgia DOT, GAB Gradation, Compaction Method 1

A.Q. 129 Ton _________ $_____________

60201 24" Pipe Culvert, Type Galvanized Steel, 0.064" Thickness, Compaction Method 2

A.Q. 108 L.F. _________ $_____________

Total Base Items: $_____________

Project: Chatt-Oconee ERFO Reconstruction FSR 44-MP 6.80 Item No. Item Description Method of

Meaure Est Qty Pay Unit Unit Price Amount

15101 Mobilization L.S.Q. 1 L.S. XXXX $____________

15713 Soil Erosion & Pollution Control, Type Silt Fence & Sediment Traps

L.S.Q. 1 L.S. XXXX $____________

20425 Drainage Excavation, Type Rolling Drain Dip & Site Finish Grading

A.Q. 2 Each _________ $____________

21201 Linear Grading C.Q. 0.08 Mile _________ $____________

30202 4-Inch Minus Aggregate Base, GeorgiaDOT Gradation #4, Compaction Method 1

A.Q. 438 Ton _________ $____________

30208 1-Inch Minus Surface Aggregate, Georgia DOT, GAB Gradation, Compaction Method 1

A.Q. 218 Ton _________ $____________

Total Base Items: $_____________

Total Schedule A: $_____________

Schedule of Items--B Project: Chatt-Oconee ERFO Reconstruction FSR 32C-MP 0.35

Item No. Item Description Method of Measure

Est Qty

Pay Unit Unit Price Amount

15101 Mobilization L.S.Q. 1 L.S. XXXX $_____________

15713 Soil Erosion & Pollution Control, Type Silt Fence & Sediment Traps

L.S.Q. 1 L.S. XXXX $_____________

20425 Drainage Excavation, Type Rolling Drain Dip & Site Finish Grading

A.Q. 1 Each XXXX $_____________

20426 Drainage Excavation, Type Blind Drain Site Preparation

L.S.Q. 1 L.S. _________ $_____________

20701 Earthwork Geosynthetics, Type Separation Class 1 Woven, Type D

A.Q. 366 S.Y. _________ $_____________

25102 Placed Riprap, Class 4 A.Q. 329 Ton _________ $_____________

30202 4-Inch Minus Aggregate Base, Georgia DOT Gradation #4, Compaction Method 1

A.Q. 165 Ton _________ $_____________

30208 1-Inch Minus Surface Aggregate, Georgia DOT, GAB Gradation, Compaction Method 1

A.Q. 92 Ton _________ $_____________

61805 Keyed-In-Place Precast Concrete Barriers (Jersey Barriers) for Stabilization/Protection of Streambank

A.Q. 8 Each _________ $_____________

Total Base Items: $_____________

Project: Chatt-Oconee ERFO Reconstruction FSR 70-MP 3.30 Item No. Item Description Method of

Meaure Est Qty Pay Unit Unit Price Amount

15101 Mobilization L.S.Q. 1 L.S. XXXX $____________

15713 Soil Erosion & Pollution Control, Type Silt Fence & Sediment Traps

L.S.Q. 1 L.S. XXXX $____________

20417 Embankment Construction, Compaction Method A (1)

C.Q. 260 C.Y. _________ $____________

21201 Linear Grading C.Q. 0.14 Mile _________ $____________

25105 Keyed Riprap, Class 4 A.Q. 1389 Ton _________ $____________

30208 1-Inch Minus Surface Aggregate, Georgia DOT, GAB Gradation, Compaction Method 1

A.Q. 300 Ton _________ $____________

60708 Cleaning Culverts In Place A.Q. 1 Each XXXX $____________

Total Base Items: $_____________

Total Schedule B: $_____________

Schedule Total

Total of Schedule A: ______________

Total of Schedule B: ______________

Contract Total A + B: ______________

NOTE: The government intends to award 1 contract for both Schedules. Vendors MUST quote both schedules

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed- Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under

151.01 Mobilization.

Payment will be made on actual work performed as described in FP-14 109.01 unless otherwise noted.

PROVIDE THE FOLLOWING WITH YOUR PROPOSAL:

• Page 2 of the solicitation

• Pages 3,4,5 (schedule of items)

• Page 18 (SB certification, SAM verification)

• Technical evaluation proposal (Experience and Relevant Past Performance)

• Bid Bond

Proposals due on 08/16/18 at 4:00 pm (PST). Email to lsolberg@fs.fed.us and mail one hard copy to:

Mt. Hood National Forest Service Attention: Leslie Solberg (AQM) 16400 Champion Way Sandy, Oregon 97055

Solicitation 12344V18R0002 mailto:lsolberg@fs.fed.us

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 Statement of Work

SCHEDULE A: FSR 44 – MP 2.49 & FSR 44 – MP 6.80 – Statement of Work is listed in Section J Attachment 1

SCHEDULE B: FSR 32C – MP 0.35 & FSR 70 – MP 3.30 – Statement of Work is listed in Section J Attachment 4

SECTION D--PACKAGING AND MARKING - NONE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov/far

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996) 52.246-13 Inspection—Dismantling, Demolition, or Removal of Improvements (AUG 1996)

E.2 AGAR 452.246-70 INSPECTION AND ACCEPTANCE (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at the project site.

E.3 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

Solicitation 12344V18R0002 https://www.acquisition.gov/far

SECTION F--DELIVERIES OR PERFORMANCE

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.acquisition.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work (APR 1984)

FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within _10_ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than _120 Days Total for both Schedule A & B_after the effective date of the notice to proceed. The time stated for completion shall include final cleanup of the premises.

Work Timing Delays due to normal adverse weather, weekends, and holidays have been included in the calculation of contract time.

Winter Shutdown When winter weather sets in and the continuation of work is impractical, the Contracting Officer may authorize a total suspension until such time as work can proceed. During the period of total suspension, the calendar days elapsed will not be charged against the contract time specified.

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 GOVERNMENT-FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause contained elsewhere in the contract.

N/A There is No Government-Furnished Property.

G.2 Invoices Contract Pay Estimates/Invoices in an approved format prepared by the Contractor, will be submitted for review, approval, and processing to the Contracting Officer. Form FS-6300-30, Contract Pay Estimate and Invoice, is available for the Contractor’s use/choice, if needed for submitting invoices.

Solicitation 12344V18R0002 http://www.arnet.gov/far/

G.3 Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP)

(a) Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is:

https://www.ipp.gov

The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fms.treas.gov or phone (866) 973-3131.

(b) Final Payment. The final invoice must be accompanied by a release of claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically accepted from the operation of the release. Final payment will not be approved without a properly executed Contract Release, Form 6300-16.

(c) In addition, when submitting the invoice, the Contractor shall submit payrolls, subcontractor payment information and a spreadsheet detailing the payment breakdown in accordance with the Pay Items in the Schedule of Items, Section B.1 (either electronically in IPP, hard copy, or via fax) to the Contracting Officer (see FAR 52.232-5 Payments Under Fixed Price Construction Contracts).

G.4 Payment for Materials Off Site In accordance with Clause 52.232-5, progress payments may include payment for materials stored off site. Contractor shall provide a copy of the paid invoice; provide evidence that the material will be included in the finished project; and identify the location where the materials are stored, so that the government may make visual inspection if the Contracting Officer deems it necessary. The Contractor shall be liable for loss, damage, or destruction of the materials until such time as the materials are physically in the possession and control of the government. The Contractor will not be held liable to the extent that the Contracting Officer determines that the loss, damage, or destruction occurred through the fault or negligence of the government or its agents.

G.5 Incidental Items The intent of the contract is to provide for the completion of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials, including hardware, will be considered as incidental to and included in the payment of items shown.

G.6 AGAR 452.215-73 Post Award Conference (NOV 1996) A post award or pre-construction conference will be scheduled by the COR. (See also Section I, Clause 52.236-26.)

https://www.ipp.gov/ mailto:IPPCustomerSupport@fms.treas.gov

G.7 Contract Administration This contract will be administered by the Contracting Officer located at:

Pacific Northwest Region Attn: CO, Leslie Solberg lsolberg@fs.fed.us

All matters related to the performance of this contract shall be coordinated through the Contracting Officer.

G.8 Designation of Contracting Officer's Representative The Contracting Officer designates the Contracting Officer's Representative(s) (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)

On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

G.9 Contractor’s Designated Representative It is required that the Contractor have a designated representative available on the project during the entire project and that the representative be able to speak and understand English. When designating a representative, the Contractor shall furnish a copy of the designation in writing to the Contracting Officer. Such designation shall clearly indicate the name and limitations (if any) of authority of the representative. If the Contractor intends to designate a representative prior to the pre-work meeting, the representative is strongly encouraged to attend that meeting.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,

EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984)

(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work sites, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workman, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by Contracting Officer.

(b) The Contractor shall protect from damage all existing improvements and utilities (1) at or near the work site and (2) on adjacent property of a third party, the location of which are made know to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.dm.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.202-1 Definitions (NOV 2013) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (MAY 2014)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)

52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower Rights (APR 2014)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreement or Statements (JAN 2017)

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper |

(MAY 2011)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(OCT 2016)

52.204-13 System for Award Management Maintenance (OCT 2016) 52.204-14 Service Contract Reporting Requirements (OCT 2016)

52.204-15 Service Contract Reporting Requirements for Indefinite-Delivery Contracts

(OCT 2016)

52.204-22 Alternative Line Item Proposal (JAN 2017) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors

Debarred, Suspended, or Proposed for Debarment (OCT 2015)

Solicitation 12344V18R0002 http://www.dm.usda.gov/procurement/policy/agar.html

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters

(JULY 2013)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (OCT 2010) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011)

52.219-8 Utilization of Small Business Concerns (NOV 2016) 52.219-9 Small Business Subcontracting Plan Alternate II (NOV 2016)

52.219-14 Limitations on Subcontracting (JAN 2017) 52.219-28 Post-Award Small Business Program Representation (JULY 2013) 52.222-3 Convict Labor (JUNE 2003) 52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation

(MAY 2014)

52.222-6 Construction Wage Rate Requirements (MAY 2014)

52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JULY 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000

(MAY 2014)

52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEPT 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (OCT 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (JULY 2014)

52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-40 Notification of Employees Rights Under the National Labor Relations Act

(DEC 2010)

52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015)

52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007)

52.223-18 Encouraging Contractor Policies to Ban Test Messaging While Driving

(AUG 2011)

52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-1 Authorization and Consent (DEC 2007)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997)

52.228-5 Insurance—Work on a Government Installation (JAN 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds – Construction (OCT 2010) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014)

52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management

(JULY 2013)

52.232-39 Unenforceability of Unauthorized Obligations (JUNE 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)

52.233-1 Disputes (MAY 2014) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991)

52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (APR 1984)

52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997)

52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JULY 1995) 52.243-4 Changes (JUNE 2007) 52.244-6 Subcontracts for Commercial Items (NOV 2017)

52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2015)

52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)-- Alternate I (SEP 1996)

52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, Or Removal of Improvements (APR 2012)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts

(NOV 1996)

452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

I.2 FAR 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER

SERVICE AND CONSTRUCTION CONTRACTS (SEPT 2013)

(a) In the performance of this contract, the contractor shall make maximum use of biobased products that are United States Department of Agriculture (USDA)-designated items unless—

(1) The product cannot be acquired—

(i) Competitively within a time frame providing for compliance with the contract performance schedule;

(ii) Meeting contract performance requirements; or

(iii) At a reasonable price.

(2) The product is to be used in an application covered by a USDA categorical exemption (see 7 CFR 3201.3(e)). For example, all USDA-designated items are exempt from the preferred procurement requirement for the following:

(i) Spacecraft system and launch support equipment.

(ii) Military equipment, i.e., a product or system designed or procured for combat or combat-related missions.

(b) Information about this requirement and these products is available at http://www.biopreferred.gov.

(c) In the performance of this contract, the Contractor shall—

(1) Report to http://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any USDA-designated biobased products purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and

(2) Submit this report no later than—

(i) October 31 of each year during contract performance; and

(ii) At the end of contract performance.

I.3 FAR 52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. As used in this clause—

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

Solicitation 12344V18R0002 http://www.biopreferred.gov/ http://www.sam.gov/

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR

Solicitation 12344V18R0002 https://acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 http://uscode.house.gov/ http://uscode.house.gov/ http://uscode.house.gov/

12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: None

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material.

However, when the basis for the exception is the unreasonable price of a domestic construction

Solicitation 12344V18R0002 https://acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123 material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON

Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

Item 2: _______ _______ _______ Foreign construction material _______ _______ _______ Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

I.4 FAR 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.5 AGAR 452.228-70 ALTERNATIVE FORMS OF SECURITY (NOV 1996)

If furnished as security, money orders, drafts, cashier's checks, or certified checks shall be drawn payable to: USDA Forest Service.

I.6 ORDER OF PRECEDENCE—CONSTRUCTION

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The Schedule (excluding the specifications)

(2) Representations and Other Instructions

(3) Contract Clauses

(4) Other Documents, Exhibits, and Attachments

(5) The Specifications

(6) Drawings

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

The following attachments are made a part of this solicitation and any resultant contract.

Title Pages Attachment 1 - Schedule A: Section C - FSR 44-MP 2.49 & FSR 44-MP 6.80 4

Attachment 2 - Schedule A - FP 14 Supplemental Specifications 56 Attachment 3 - Schedule A - Plan Sheets 15 Attachment 4 - Schedule B: Section C – FSR 32C-MP 0.35 & 70-MP 3.30 4 Attachment 5 - Schedule B - FP 14 Supplemental Specifications 52

Attachment 6 - Schedule B Plan Sheets 16 Attachment 7 - Schedule A & B: Wage Determination GA180225 01/05/2018 GA225 – Rabun, Towns, and White Counties 5

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER

STATEMENTS OF OFFERORS OR RESPONDENTS

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

FAR 52.204-8 Annual Representations and Certifications (JAN 2018) (a)

(1) The North American Industry classification System (NAICS) code for this acquisition is 237310.

(2) The small business size standard is $36.5 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)

(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certification in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[_] (i) Paragraph (d) applies.

[_] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)

(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer: None

(d) The offeror has completed the annual representations and certifications electronically via the SAM Web site accessed through https://www.acquisition.gov . After reviewing the SAM database information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

Solicitation 12344V18R0002 https://www.acquisition.gov/

FAR Clause Title Date Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

52.204-16 Commercial and Government Entity Code reporting (JUL 2016)

AGAR 452.219-70 Size Standard and NAICS Code Information (SEP 2001)

The North American Industrial classification System Code(s) and business size standard(s) describing the products and/or services to be acquired under this solicitation are listed below:

Contract line item(s): ALL --NAICS Code 237310 --Size Standard $36.5 Million

The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

FAR 52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998) This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

www.acquisition.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1)

52.204-7 System for Award Management (OCT 2016) 52.204-16 Commercial and Government Entity Code Reporting (JUL 2016)

52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 2014)

(a) (1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

Solicitation 12344V18R0002 http://www.acquisition.gov/far/ http://www.usda.gov/procurement/policy/agar.html

(b) (1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered are, are as follows:

Goals for minority participation for each trade Goals for female participation for each trade 6.2% 6.9% These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative actions obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4.

Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U. S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the--

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Georgia.

52.225-10 Notice of Buy American Act Requirement--Construction Materials (MAY 2014)

(a) Definitions. “Commercially available off-the-shelf-(COTS) item,” "Construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American Act--Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American Act should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American Act before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy…