Statement of Work Summary: Marshfield Parking Lot Repair and Sealcoat
This Statement of Work describes a parking lot rehabilitation project at the USDA-ARS EIDMRU Lab located at 2615 Yellowstone Drive, Marshfield, WI 54449. The project requires replacement of 900 square yards of asphalt parking lot, crack filling and sealcoating of the remaining parking lot in good condition, and parking space striping of the entire lot. The asphalt replacement areas require excavation and removal of existing asphalt and 18 inches of subgrade material, followed by installation of 10 inches of breaker run and 8 inches of compacted base course, then paving with WisDOT spec type MT58-28S asphalt mix compacted to 3.5 inches in two lifts with a tack coat applied prior to the surface course. For areas in good condition, all cracks must be routed and filled, seams between concrete and asphalt routed and filled, and two coats of sealcoat applied using a bio-based product such as BioSealcoat (Aexcel Corp.).
All work must be conducted during normal business hours of 7 a.m. to 5 p.m., Monday through Friday, with contractors required to notify the USDA technical points of contact (Matt Akins at 715-391-3246 and Joe Hattamer) at least one week before anticipated start. Contractors must provide quotes that comprehensively describe all materials and services, including labor, travel, deliveries, and bid bonding; quotes omitting items deemed necessary per the technical specifications will not be reviewed. Following completion of asphalt replacement and sealcoating, parking areas must be paint striped to match pre-existing patterns, including two handicapped areas in the front lot, using a bio-based striping paint such as BioStripe (Aexcel Corp.). No government property or equipment will be furnished, and no special security requirements apply since all work occurs outside the building.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) Project: Marshfield Parking Lot Repair and Sealcoat
GENERAL INFORMATION
1.0 Scope of Work:
Replacement of 900 square yards of asphalt parking lot, and crack filling and sealcoating of remaining parking lot which in good condition, and parking space striping of entire parking lot at the USDA-ARS EIDMRU Lab in Marshfield, WI.
2.0 Background:
The EIDMRU Lab building parking lot is in need of crackfilling and sealcoating for the majority of the parking lot with replacement of some areas (900 square yards total) due to sinking and cracking.
The areas needing replacement will require excavation of those areas to remove and dispose of the existing asphalt and 18 inches of subgrade material prior to installation of 10 inches of new subgrade breaker run and 8 inches of compacted base course. The lot will be paved with WisDOT spec type MT58-28S asphalt mix compacted to 3.5 inches in two lifts. A tack coat will be used prior to the surface course.
The areas in good condition to be seal-coated will have all cracks routed and filled, and seams between concrete and asphalt routed and filled.
After the asphalt replacement and sealcoating is completed, the parking areas will be paint striped to match the pre-existing parking area strips.
CONTRACTOR REQUIREMENTS
3.0 Technical Requirements/Tasks:
Asphalt lot replacement area = 900 square yards Replacement incudes:
-Saw cutting of asphalt replacement area -Removal and disposal of removed asphalt -Removal and disposal of 18 inches subgrade material -Furnish and install 10 inches breaker run and 8 inches base course -Fine grading, watering, and compaction of base course material -Pave with WisDOT spec type MT58-28S asphalt mix compacted to 3.5 inches in two lifts. A tack coat must be used prior to installation of surface course.
Parking lot crackfilling and sealcoating -Route and fill asphalt cracks -Clean out and fill seams between asphalt and concrete -Apply 2 coats of sealcoat to entire area except replacement area -Sealcoat shall be a bio-based product such as BioSealcoat (Aexcel Corp.)
Parking lot paint striping -After replacement and sealcoating is complete, paint stripe parking areas similar to pre-existing parking lots including 2 handicapped areas in front lot -Striping paint shall be a bio-based product such at BioStripe (Aexcel Corp.)
-Quote must include a description of all materials and services to be provided as part of the package, including materials, labor, travel/deliveries, and bid bonding. If items deemed necessary in the above technical specifications are not included in the quote, the quote may not be reviewed.
4.0 Government Furnished:
No government property or equipment will be provided
5.0 Deliverables / Schedule:
The site of this work is at the USDA-ARS EIDMRU lab and office located at 2615
Yellowstone Drive, Marshfield, WI 54449.
All work at the site must be conducted during normal business hours of 7am and
5pm Monday through Friday unless scheduled in advance with facility staff.
Contractors must notify the USDA technical POCs (Matt Akins-715-391-3246) and
Joe Hattamer at least 1 week before anticipated start of the package implementation to ensure the plans work with the staff’s schedule, and coordinate work schedules around other building projects.
6.0 Travel:
Worksite location is the USDA-ARS EIDMRU lab and office located at 2615
Yellowstone Drive, Marshfield, WI 54449. All travel and delivery of materials to the site must be included in the quote.
7.0 Contractor’s Key Personnel:
Key personnel for the contractor include the technical representative to determine the correct materials, and the staff in charge of implementation.
8.0 Security Requirements:
No special security requirements will be needed for vendors working on the project at this location since all work will be completed outside the building.
Overhead pictures of work areas:
Crack filling and seal coating area
Asphalt repair area, approximate (yellow areas)
Asphalt replacement areas
Pictures of existing parking lot: