This document is a Questions and Answers (Q&A) file related to a technical contract or project involving a control system and boiler integration. The document contains one specific question and answer addressing the scope of work. The questioner sought clarification about whether the existing boiler would need to be connected to the new control system, as this was not explicitly mentioned in the original scope. The government representative confirmed that the boiler will indeed need to be connected to the new system, noting that one of the four programmable controllers listed in the Statement of Work (SOW) is specifically designated for the boiler.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&As

Q1: The scope does not mention integration to the existing boiler on site. The current controls are connected to the boiler. Will the existing boiler need connected to the new control system?

A1: Yes, the boiler will need to be connected to the new system. One of the four programable controllers listed in the SOW is for the boiler.