Questions and Answers_Amendment 0001.pdf

PDF 55 KB Posted

Attached to
Supply and Install Air Handling Unit Automatic Controls, Auburn, AL Federal contract opportunity
Solicitation number
1232SA25Q0655
Issued by
Department of Agriculture Agricultural Research Service

About this file

This document is a Questions and Answers (Q&A) file related to a technical contract or project involving a control system and boiler integration. The document contains one specific question and answer addressing the scope of work. The questioner sought clarification about whether the existing boiler would need to be connected to the new control system, as this was not explicitly mentioned in the original scope. The government representative confirmed that the boiler will indeed need to be connected to the new system, noting that one of the four programmable controllers listed in the Statement of Work (SOW) is specifically designated for the boiler.

View the file

Other files for this federal contract opportunity

Other files attached to Supply and Install Air Handling Unit Automatic Controls, Auburn, AL, newest first.
File Type Posted
Attachment 1_Provisions and Clauses_Amendment 0001.pdf PDF
Attachment 1_Provisions and Clauses.pdf PDF
Attachment 2_Building 50 HVAC Control Upgrade.pdf PDF
Attachment 4_52.225-2 Buy American Certificate.docx DOCX document
Attachment 3_Service Contract Act WD 2015-4589.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&As

Q1: The scope does not mention integration to the existing boiler on site. The current controls are connected to the boiler. Will the existing boiler need connected to the new control system?

A1: Yes, the boiler will need to be connected to the new system. One of the four programable controllers listed in the SOW is for the boiler.

File details come from the government source that posted it. Updated .