This document is a solicitation amendment for a design-build modernization project at the USDA South Building in Washington DC. The amendment provides changes to the solicitation including allowing organizational charts to be presented on 11" x 17" paper, reducing the page limit for Factor 2 to no more than six pages, deleting the requirement for resumes under Factor 2.3, revising language under Factor 3, replacing the page listing attachments to renumber and rename the attachments, and answering questions submitted by the July 6 deadline. The response due date remains July 26, 2021. The project involves modernizing Wings 6 and 7 which are each approximately 150,000 square feet. Phase II documents will be provided to the three highest rated offerors and will include drawings, specifications, programs of requirements, and renderings.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12314421R0006 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Washington DC 20024-3243
DASO-OCP-POD-AMB-DC
10th Floor, Suite 10-149A 355 E Street S.W.
Acquisition Management Branch-WDC USDA, DM/OCP/POD/AMB, POD Acq Mgmt
07/08/20210002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/24/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
USDA SOUTH BUILDING WINGS 7 & 6 DESIGN-BUILD MODERNIZATION
Solicitation # 12314421R0006
Amendment # 0002 dated 08 July 2021
This Amendment incorporates the following changes:
1. Page 57 of 81 PROPOSAL REQUIREMENTS AND FORMATTING. Organizational Chart requested under FACTOR 2 MANAGEMENT ORGANIZATION, paragraph 2.2 ORGANIZATION CHART may be provided on size 11" x 17".
2. Page 59 of 81 FACTOR 2 - MANAGEMENT ORGANIZATION. Factor 2 shall consist of no more
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
TODD LENNOX
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12314421R0006/0002 than five (5) pages long for Paragraph 1 CONTRACT TEAM ORGANIZATION - and - a one (1) page for Paragraph 2 ORGANIZATION CHART for a total of no more than six (6) pages.
3. Page 60 of 81 FACTOR 2.3 KEY PERSONNEL is deleted in its entirety.
4. Page 62 of 81 FACTOR 3 SPECIALIZED
EXPERIENCE. The following sentence is revised to read as follows: "Failure to address paragraphs
1) through 9) below may result in an incomplete submission and rejection of offer."
5. Page 63 of 81 The following sentence located at the bottom of the page is revised to read as follows: "The information regarding the projects that is required to be supplied is identified on the form entitled "ATTACHMENT 3 Specialized
Experience Form (fillable)" (See ATTACHMENT)."
6. Page 68 of 81 PHASE 1 RFP ATTACHMENTS. This page is replaced in its entirety. It renumbers and renames the attachments, as follows:
* CONTRACTOR'S PAST EXPERIENCE FORM is removed in its entirety.
* PAST PERFORMANCE QUESTIONNAIRE (PPQ) is two
(2) separate forms, as follows:
+ ATTACHMENT 2 (PART 1 of 2) USDA
CONSTRUCTION PAST PERFORMANCE QUESTIONNAIRE
(fillable).pdf
+ ATTACHMENT 2 (PART 2 OF 2) USDA
CONSTRUCTION PAST PERFORMANCE QUESTIONNAIRE -
RATINGS FORM.docx
* COMPANY SPECIALIZED EXPERIENCE -
CONSTRUCTION OR PRIME CONTRACTOR is renamed to ATTACHMENT 3 Specialized Experience Form
(fillable).docx
* COMPANY SPECIALIZED EXPERIENCE - DESIGN FIRM
OR IN-HOUSE DESIGN CAPABILITY renamed to ATTACHMENT 4 Specialized Experience Additional Information (fillable form).docx
7. Provides answers to all questions posted by Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12314421R0006/0002 the July 06, due date.
Due date for Phase I response remains unchanged to Monday July 26, 2021, 2:00PM (EST).
All other terms and conditions remain unchanged and in full force and effect.
Period of Performance: 10/12/2021 to 12/01/2025
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
USDA South Building Wings 6 & 7 Design-Build Modernization Solicitation # 12314421R0006
Amendment # 0002 dated 08 July 2021
This Amendment incorporates the following changes:
1. Page 57 of 81 PROPOSAL REQUIREMENTS AND FORMATTING. Organizational Chart requested under FACTOR 2 MANAGEMENT ORGANIZATION, paragraph 2.2 ORGANIZATION CHART may be provided on size 11” x 17”.
2. Page 59 of 81 FACTOR 2 - MANAGEMENT ORGANIZATION. Factor 2 shall consist of no more than five (5) pages long for Paragraph 1 CONTRACT TEAM ORGANIZATION – and – a one (1) page for Paragraph 2 ORGANIZATION CHART for a total of no more than six (6) pages.
3. Page 60 of 81 FACTOR 2.3 KEY PERSONNEL is deleted in its entirety.
4. Page 62 of 81 FACTOR 3 SPECIALIZED EXPERIENCE. The following sentence is revised to read as follows: “Failure to address paragraphs 1) through 9) below may result in an incomplete submission and rejection of offer.”
5. Page 63 of 81 The following sentence located at the bottom of the page is revised to read as follows: “ The information regarding the projects that is required to be supplied is identified on the form entitled “ATTACHMENT 3 Specialized Experience Form (fillable) (See ATTACHMENT).”
6. Page 68 of 81 PHASE 1 RFP ATTACHMENTS. This page is replaced in its entirety. It renumbers and renames the attachments, as follows:
• CONTRACTOR’S PAST EXPERIENCE FORM is removed in its entirety.
• PAST PERFORMANCE QUESTIONNAIRE (PPQ) is two (2) separate forms, as follows:
ATTACHMENT 2 (PART 1 of 2) USDA CONSTRUCTION PAST PERFORMANCE QUESTIONNAIRE
(fillable).pdf
ATTACHMENT 2 (PART 2 OF 2) USDA CONSTRUCTION PAST PERFORMANCE QUESTIONNAIRE -
RATINGS FORM.docx
• COMPANY SPECIALIZED EXPERIENCE – CONSTRUCTION OR PRIME CONTRACTOR is renamed to
ATTACHMENT 3 Specialized Experience Form (fillable).docx
• COMPANY SPECIALIZED EXPERIENCE – DESIGN FIRM OR IN-HOUSE DESIGN CAPABILITY renamed to
ATTACHMENT 4 Specialized Experience Additional Information (fillable form).docx
7. Provides answers to all questions posted by the July 06, 2:00PM due date.
Following answers questions posted to date:
1. Based on the Solicitation published, the anticipated period of performance is stated to be 9/21/2021 to 11/09/2025. With the Phase 1 response due 7/15/2021, there is strong concern with the anticipated Phase 2 timeframe. Please clarify the Governments current into for Phase 2 release, Phase 2 response due, and Anticipated Award date. For a project of this scale and complexity, all Offerors will need adequate time to review the bridging documents to finalize the Phase 2 response.
ANSWER TO QUESTION # 1 USDA anticipates releasing the Phase II RFP on or about the middle of August 2021 with a deadline for Phase II responses 30 calendar days thereafter. The Anticipated Award date will be on or about the middle of October 2021.
2. Will the Government allow for a 2 week extension in order to allow enough time to create a more complete response and factoring the timeframes it takes to receive PPQs?
ANSWER TO QUESTION # 2 Refer to posted Amendment # 0001 dated June 29, 2021, extending the due date for Phase I responses to Monday July 26, 2021 2:00 PM (EST).
3. Will the Government allow a 1 week extension for questions to be asked (with the understanding of a
Phase 1 response extension)?
ANSWER TO QUESTION # 3 Refer to posted Amendment # 0001 dated June 29, 2021, extending the due date for questions to July 6, 2021 2:00PM (EST).
4. General: A complete Phase I technical proposal is required. Would the government consider extending the submission deadline to around 07/24, to provide interested firms with the customary 30 days (from solicitation issuance) to respond?
ANSWER TO QUESTION # 4 Refer to ANSWER TO QUESTION # 2.
5. [Page 59 of 81] Factor 2 MANAGEMENT ORGANIZATION (TEAM ORGANIZATION & KEY PERSONNEL) (1 and 2): Both sections 1 and 2 of Factor 2 require descriptions of subcontractor management. Would the government consider omitting this requirement from the chart (section 2)?
ANSWER TO QUESTION # 5 No.
6. [Page 60 of 81] Factor 2.3 Key personnel: Field key personnel, such as superintendents, safety managers, and quality control managers are not typically selected until the Phase II stage, at which point an award date can be better anticipated. Would the government consider omitting these positions in favor of key design personnel, which can be anticipated at the Phase I stage?
ANSWER TO QUESTION # 6 Amendment # 0002 revises Factor 2 and deletes paragraph 2.3.
7. [Page 60 of 81] Factor 2.3 Key personnel: Can the government confirm that resumes are not required for the Key Personnel section, and that instead, the government is looking to confirm personnel identity and availability only?
ANSWER TO QUESTION # 7 See language in Amendment # 0002 and refer to ANSWER TO
QUESTION # 6.
8. [Page 61 of 81] Factor 3 SPECIALIZED EXPERIENCE: Projects must be relevant in scope, size, magnitude, and complexity. Can the government confirm the size and magnitude standards required for relevant projects?
ANSWER TO QUESTION # 8 The size of Wings 6 & 7 is approximately 150,000 sf each. The magnitude of this project is as described in the RFP. Relevant projects are projects of similar size and magnitude to Wings 6 & 7.
9. [Page 64 of 81] Factor 4 PAST PERFORMANCE OF DESIGN-BUILD CONTRACTS: Bullet point 1 notes design/build and design/bid/build projects in excess of $60M. This Factor requires design/build past performance. Must projects submitted in this Factor be design/build projects, or may they be design/bid/build projects?
ANSWER TO QUESTION # 9 Offerors may submit design/bid/build projects; however, preference be given to design/build projects over design/bid/build projects.
10. Page 61 of the RFP states, “Incorporating or highlighting the information requested under paragraphs 1) through 10), below into the six (6) project examples[…] Failure to address paragraphs 1) through 10) below may result in an incomplete submission and rejection of offer.” The owner has only provided paragraphs 1 through 9. Please confirm there are only nine required paragraphs to address or update the list to include the 10th item.
ANSWER TO QUESTION # 10 See language in Amendment # 0002. Confirmed - only nine (9) paragraphs to address.
11. Page 63 of the RFP indicates that Factor 3 Specialized Experience will be given a rating of High Confidence, Some Confidence, or Low Confidence that the, “vendor understands the requirement, proposes a sound approach, and will be successful in performing the contract.” This evaluation appears to be related to a Management or Technical Approach rather than descriptions of the contractor’s specialized experience. The evaluation criteria for Factor 4 seems to be more appropriate. Please review these criteria and advise.
ANSWER TO QUESTION # 11 Technical Confidence Ratings are the ratings that will be utilized.
12. Factor 4 is defined as “Past Performance on Design-Build Contracts” and page 64 states “The offer shall provide the Offeror’s assigned performance evaluations for the submitted projects that demonstrate the Offeror’s performance on recent and relative Design-Build projects.” However, the first bullet on page 64 states “Design-Build and/or Design-Bid Build Projects in excess of $60M.” Please confirm that projects submitted under Factor 4 may only be design-build projects.
ANSWER TO QUESTION # 12 Refer to ANSWER TO QUESTION # 9.
13. Please confirm that the offeror is allowed to expand and modify Attachments 1, 2, and 3 to provide the details needed for evaluators to verify the relevance and similarity of the submitted projects to the USDA Wings 6 & 7 project.
ANSWER TO QUESTION # 13 Offerors shall only use the pdfs / word documents provided as attachments and may not edit them; however, add all the relevant information in the fillable fields which are expandable.
14. Page 57 states that proposals shall be written in “portrait mode on letter size paper; except charts and matrices may be displayed in landscape mode.” Please confirm the Organizational Chart can be provided on size 11” x 17” landscape paper.
ANSWER TO QUESTION # 14 See language in Amendment # 0002. Yes, the Organizational Chart may be provided on size 11” x 17” landscape paper.
15. [Page 56 of 81] In the phase 2 evaluation process, is price weighed heavier than all other factors combined? Ie is the final award based on primarily evaluation of low price?
ANSWER TO QUESTION # 15 Refer to Page 56 of 81, paragraph E. Basis of Award.
16. What level of design/engineering bridging documents will be provided in phase 2?
ANSWER TO QUESTION # 16 General details about the design are provided beginning of Page 12 of 81 – additional information will be provided during Phase II.
17. Page No. 59 / Factor 2 - Management Organization / Request for Information/Clarification - Please provide if there is a page limit to the Factor 2 Management Organization.
ANSWER TO QUESTION # 17 See language in Amendment # 0002. Factor 2 shall consist of no more than five (5) pages long for Paragraph 1 CONTRACT TEAM ORGANIZATION – and – a one (1) page for paragraph 2 ORGANIZATIONAL CHART for a total of no more than six (6) pages.
18. Page No. 61-65 / Factor 3 - Specialized Experience and Factor 4 - Past Performance of Design-Build
Contracts. / Request for Information/Clarification - Please confirm that the project experience sheets provided in Factor 3 are not the same as the project experience sheets to be provided in Factor 4.
ANSWER TO QUESTION # 18 See Page 68 of 81 has been replaced as part of Amendment # 0002 and the Past Experience form provided in reference in Factor 4 has been deleted. The form referenced in Factor 4 has been changed as indicated in Amendment # 0002.
19. Page No. 64 / Factor 4 - Past Performance of Design-Build Contracts / Request for Information /
Clarification - Page 65 states that Offerors may use PPQs filled out previously without having them re-accomplished for this specific solicitation. Can CPARS past performance information be provided for completed projects in lieu of PPQs?
ANSWER TO QUESTION # 19 No. Offerors should provide completed PPQs. Separately, the government may review CPARS and any other sources of information for evaluating Past Performance for the proposed team members.
20. Page No. 11 / General Instruction / Request for Information/Clarification - Please confirm that affiliate experience can be allowed provided meaningful involvement is provided.
ANSWER TO QUESTION # 20 Yes, as long as it meets the requirements in Paragraph 4 on Page 11 of 81.
21. Are the required cover page and table of contents for each volume included in volume page limits, where applicable?
ANSWER TO QUESTION # 21 No, the cover page & table of contents don’t count towards the page limits.
22. The RFP references drawings created by AECOM for this project. Will the government please provide these drawings to offerors?
ANSWER TO QUESTION # 22 The three (3) offerors that advance to Phase II will receive the referenced drawings.
Due date for Phase I response remains unchanged to Monday July 26, 2021, 2:00PM (EST).
END OF AMENDMENT # 0002
RFP ATTACHMENTS
PHASE 1 ATTACHMENTS
1. ATTACHMENT 2 (PART 1 of 2) USDA CONSTRUCTION PAST PERFORMANCE QUESTIONNAIRE (fillable).
2. ATTACHMENT 2 (PART 2 OF 2) USDA CONSTRUCTION PAST PERFORMANCE QUESTIONNAIRE - RATINGS FORM.
3. ATTACHMENT 3 Specialized Experience Form (fillable).
4. ATTACHMENT 4 Specialized Experience Additional Information (fillable form).
5. DOL DAVIS BACON WAGE DETERMINATION
PHASE II ATTACHMENTS
6. WING 7 DRAWING SET (PROVIDED AT PHASE II)
7. WING 6 DRAWING SET (PROVIDED AT PHASE II)
8. WINGS 6 & 7 PROGRAM OF REQUIREMENTS (POR) (ONE DOCUMENT ADDRESS BOTH WINGS) (PROVIDED AT
PHASE II)
9. WINGS 6 & 7 SPECIFICATION (ONE DOCUMENT ADDRESS BOTH WINGS) (PROVIDED AT PHASE II)
10. 12 RENDERINGS (PROVIDED AT PHASE II)
11. SID BINDER (PROVIDED AT PHASE II)
12. SID BOARD (PROVIDED AT PHASE II)
13. CURRENT AS-BUILTS, THESE DRAWINGS ARE PROVIDED FOR HISTORICAL REFERENCE ONLY AND SHOULD NOT BE
USED FOR ORIENTATION. (PROVIDED AT PHASE II)
Note: there is no ATTACHMENT 1
| 12314421R0006 - beta.sam.gov Wing 7 and 6 Amednment 0002 SF30 07.08.21 |
| 12314421R0006 - beta.sam.gov Wing 7 and 6 Mod 0002 rev Page 68 |
File details come from the government source that posted it. Updated .